1 Question 1 Single choice Developing People and Teams
A Scrum Master notices that the Developers on a team consistently wait for the Product Owner to assign them work during the Sprint, and two senior engineers have taken all the complex items while junior members pick up only trivial tasks. The team is otherwise healthy, and the Product Owner is supportive. Which action is the BEST next step for the Scrum Master to help the team become self-managing?
Correct Answer: CExplanationSelf-managing Developers decide how the work gets done, including who does what, and the Scrum Master's job is to create the conditions for that rather than take the decision over. Raising the pattern in the Retrospective and letting the Developers redesign their own selection practice builds the capability. Having the Product Owner pre-assign work contradicts the Developers' accountability for the Sprint Backlog, and naming a lead reintroduces a hierarchy Scrum does not define. Splitting the team treats a symptom and breaks the cohesion of a single Scrum Team.
-
2 Question 2 Single choice Managing Products with Agility
A company is building a product for a regulated market. The Product Owner wants a firm release date for a Q3 launch to satisfy a partner contract. Forecasting shows the Product Backlog's highest-ordered items would deliver a viable release in Q3 only if two lower-value compliance items are dropped, which the Legal stakeholder refuses. The Developers estimate using relative sizing and their velocity has varied by about 40 percent over the last six Sprints. The Scrum Master must help the Scrum Team communicate the forecast honestly. Which approach BEST meets these needs?
Correct Answer: CExplanationBecause velocity varies widely, a single-number commitment built on an average hides real risk, so a forecast expressed as a range or probability tied to remaining scope is the empirical answer. Showing what can be delivered by each date with the compliance items retained respects Legal's constraint while being transparent. Averaging still produces a false point estimate, inflating estimates to reorder the Backlog corrupts the Product Backlog's transparency, and freezing the Backlog does not change the underlying uncertainty of delivery.
-
3 Question 3 Single choice Understanding and Applying the Scrum Framework
During a Sprint, the Scrum Team discovers that a feature the Developers planned to ship cannot be released because the production environment lacks a required configuration that the operations group controls. The Developers have already marked the increment as Done for two other backlog items. The Product Owner asks whether the Sprint Goal is still achievable. The Sprint is halfway complete and the Team's Definition of Done includes deployment-ready verification. What is the MOST appropriate action regarding the Definition of Done and the Increment?
Correct Answer: DExplanationThe Definition of Done describes the quality of the Increment, so a feature whose required deployment readiness cannot be met is not Done, and an Increment must never contain undone work. The Team should check whether the operations dependency is genuinely part of its Done criteria, and then adapt the Sprint with the Product Owner while the Sprint still has time. Keeping items Done based on earlier checks ignores the new information, and relabelling the feature falsifies the Increment's status. Holding exceptions until the Review hides the problem from stakeholders when transparency matters most.
-
4 Question 4 Single choice Managing Products with Agility
A Product Owner manages a Product Backlog with 400 items, many of which are vague, duplicated, and aged more than a year. The stakeholders are frustrated that the Sprint Review never surfaces their priorities. The Developers have started asking the Product Owner about items they cannot yet estimate. The Scrum Master wants the Product Owner to refine the Product Backlog in a way that supports transparency and short-term forecasting. Which action is the MOST appropriate?
Correct Answer: DExplanationProduct Backlog refinement is an ongoing activity in which the Developers provide estimates and the Product Owner keeps the top of the backlog detailed and ordered, while the lower items remain less refined. Pruning duplicates and stale items reduces noise and makes the ordering meaningful to stakeholders. Ordering all 400 items at once is wasteful and does not address the lack of readiness, a separate document breaks the single source of truth, and estimating everything in one session is unnecessary effort for items that may never be built.
-
5 Question 5 Single choice Developing People and Teams
A Scrum Master has been asked to coach a team that treats the Scrum Master as the person who assigns impediments and tracks follow-up actions. Team members have started bringing every problem to the Scrum Master, and the Developers rarely raise issues during the Daily Scrum. The Scrum Master wants to shift accountability to the team without abandoning support. Which coaching approach is MOST effective?
Correct Answer: AExplanationCoaching builds the team's capacity by using questions that lead Developers to consider options and take ownership of impediment removal, which is consistent with the Scrum Master's role as a servant-leader for the team. Keeping the impediment tracker personal reinforces dependence on the Scrum Master, assigning impediments by decree is still directive, and escalating every issue to the Product Owner misplaces responsibility for team-level obstacles.
-
6 Question 6 Single choice Understanding and Applying the Scrum Framework
An organisation runs a Sprint of three weeks. In the middle of the Sprint, the CEO asks the Scrum Team to add two new features that would strengthen a sales presentation. The Product Owner agrees without consulting the Developers. The Developers estimate the new features would take about one week and say the existing Sprint Goal would be at risk. The Scrum Master is asked how to resolve the situation within Scrum. Which response is MOST consistent with the Scrum framework?
Correct Answer: DExplanationA Sprint's Goal is protected, and the Product Owner can cancel a Sprint only when the Sprint Goal becomes obsolete, which is not the case here. New work belongs in the Product Backlog and is planned into a future Sprint, not slipped into the current one. The Product Owner cannot unilaterally change the Sprint Backlog, overtime does not fix the scope problem, and canceling merely because of a scope request is not a valid reason.
-
7 Question 7 Single choice Managing Products with Agility
A Scrum Team has delivered working increments for six Sprints. The Product Owner is preparing a stakeholder forecast for a major launch. Stakeholders want a single date. The Product Owner has a fixed budget and wants to measure progress toward the launch in terms the business understands. The Scrum Master proposes a measure that focuses on whether the product is delivering value, rather than on output activity. Which measure is MOST aligned with Scrum's product value focus?
Correct Answer: DExplanationScrum emphasises delivering value, and measured outcomes show whether delivered increments actually achieve the product's goals, which is the evidence stakeholders need to decide on investment. Story points, Done counts and hours are all output or activity measures that can rise while value stays flat, so they do not show whether the product is working.
-
8 Question 8 Single choice Understanding and Applying the Scrum Framework
The Developers of a Scrum Team are required to test manually in a separate test phase after each Sprint, and the Product Owner wants that phase removed to shorten release cycles. The Scrum Team has no automated test suite, and the organisation prohibits releases without evidence of test coverage. The Scrum Master is discussing how to incorporate testing into the Definition of Done. Which change BEST aligns with Scrum's commitment to transparency and quality?
Correct Answer: CExplanationThe Definition of Done must describe the quality the Increment needs, and the organisation's evidence requirement means testing must be complete within each Increment. Building automated tests so verification happens during the Sprint makes quality visible and removes the hand-off delay. Deferring testing to release leaves undone work in Increments, moving manual testing into the Review pushes quality checks into an event meant for inspection, and letting the Product Owner decide per Sprint makes the Definition of Done inconsistent.
-
9 Question 9 Single choice Developing People and Teams
A Scrum Master facilitates a Sprint Retrospective for a team that has missed its Sprint Goal three times in a row. Several team members are quiet, and one senior Developer dominates the discussion and blames the Product Owner for shifting priorities. The Scrum Master wants the session to produce concrete improvements that the team owns. Which facilitation technique is MOST effective here?
Correct Answer: BExplanationSilent writing followed by grouping and voting gives quieter members an equal voice and surfaces the team's shared concerns, which produces actionable, team-owned improvements. Letting the dominant voice lead undermines psychological safety, having the Product Owner present shifts the focus to blame, and skipping the Retrospective removes the team's main opportunity to inspect and adapt.
-
10 Question 10 Single choice Managing Products with Agility
A business analyst asks the Scrum Team to commit to delivering a specific set of features by a contractual date that is four months away. The Developers' forecast, based on recent throughput, shows they can deliver roughly two-thirds of the requested scope by that date. The Product Owner has authority to set priorities but cannot change the contract. The Scrum Master needs to help the Product Owner deal with the gap in a Scrum-consistent way. What should the Product Owner do FIRST?
Correct Answer: AExplanationThe Product Owner is accountable for ordering the Product Backlog and for maximising value, so the first step is to order the work and make the forecast visible to the people who own the contract. This allows an informed decision about scope or date. Forcing the full scope through velocity pressure produces unreliable commitments, weakening the Definition of Done hides the gap, and splitting teams immediately adds cost and coordination without a basis for the forecast.
-
11 Question 11 Single choice Understanding and Applying the Scrum Framework
A Scrum Master reviews the Daily Scrum at a team that has grown from five to twelve people split across two time zones. The meeting has become a series of status reports to the Scrum Master, lasting 45 minutes, and the Developers rarely talk to each other. The Scrum Master wants the event to fulfil its purpose of inspecting progress toward the Sprint Goal and adapting the Sprint Backlog. Which change is the MOST appropriate?
Correct Answer: DExplanationThe Daily Scrum is a fifteen-minute event for the Developers to inspect progress toward the Sprint Goal and adapt the Sprint Backlog, and it is not a status report to the Scrum Master. Keeping it time-boxed and refocusing it on the Sprint Goal restores its purpose. Written reports to the Scrum Master recreate the status-reporting pattern, a weekly meeting breaks the daily inspection cadence, and adding stakeholder updates changes the event's audience and purpose.
-
12 Question 12 Single choice Managing Products with Agility
A Product Owner is deciding whether to include a feature that a key customer has requested. Analysis shows the feature would take three Sprints, and the customer has said they might switch vendors if it is not delivered in two Sprints. Meanwhile, a large group of users has reported a usability problem that affects far more customers daily. The Product Owner is trying to choose the next Product Backlog item to work on. Which decision BEST reflects Scrum's approach to ordering the Product Backlog?
Correct Answer: AExplanationThe Product Owner orders the Product Backlog to maximise value, and a usability problem affecting many customers daily outweighs a single customer's request, even a valuable one, whose timing needs to be managed transparently with that stakeholder. Ordering the single feature first assumes its risk exceeds the broad value loss, splitting into an unfinished version compromises the feature's usefulness without evidence, and handing ordering to the Developers violates the Product Owner's accountability.
These are 12 of the 298 questions in the full PSM-I pack.
Get All 298 QuestionsGet all 298 questions & answers
Full access options for Scrum PSM-I
Self-study
PDF Version
- 298 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 298 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 298 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PSM-I Exam (Professional Scrum Master I) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.