2026 Actual Scrum PSM-I Dumps, Updated Exam Questions for Guaranteed Pass

Professional Scrum Master I - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorScrum
Exam codePSM-I
Exam nameProfessional Scrum Master I
Questions in pack298
Last updatedNovember 21, 2026
Related certificationsProfessional Scrum Master

Free practice questions with explanations

Scrum PSM-I Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
12
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Developing People and Teams

    A Scrum Master notices that the Developers on a team consistently wait for the Product Owner to assign them work during the Sprint, and two senior engineers have taken all the complex items while junior members pick up only trivial tasks. The team is otherwise healthy, and the Product Owner is supportive. Which action is the BEST next step for the Scrum Master to help the team become self-managing?

  2. 2 Question 2 Single choice Managing Products with Agility

    A company is building a product for a regulated market. The Product Owner wants a firm release date for a Q3 launch to satisfy a partner contract. Forecasting shows the Product Backlog's highest-ordered items would deliver a viable release in Q3 only if two lower-value compliance items are dropped, which the Legal stakeholder refuses. The Developers estimate using relative sizing and their velocity has varied by about 40 percent over the last six Sprints. The Scrum Master must help the Scrum Team communicate the forecast honestly. Which approach BEST meets these needs?

  3. 3 Question 3 Single choice Understanding and Applying the Scrum Framework

    During a Sprint, the Scrum Team discovers that a feature the Developers planned to ship cannot be released because the production environment lacks a required configuration that the operations group controls. The Developers have already marked the increment as Done for two other backlog items. The Product Owner asks whether the Sprint Goal is still achievable. The Sprint is halfway complete and the Team's Definition of Done includes deployment-ready verification. What is the MOST appropriate action regarding the Definition of Done and the Increment?

  4. 4 Question 4 Single choice Managing Products with Agility

    A Product Owner manages a Product Backlog with 400 items, many of which are vague, duplicated, and aged more than a year. The stakeholders are frustrated that the Sprint Review never surfaces their priorities. The Developers have started asking the Product Owner about items they cannot yet estimate. The Scrum Master wants the Product Owner to refine the Product Backlog in a way that supports transparency and short-term forecasting. Which action is the MOST appropriate?

  5. 5 Question 5 Single choice Developing People and Teams

    A Scrum Master has been asked to coach a team that treats the Scrum Master as the person who assigns impediments and tracks follow-up actions. Team members have started bringing every problem to the Scrum Master, and the Developers rarely raise issues during the Daily Scrum. The Scrum Master wants to shift accountability to the team without abandoning support. Which coaching approach is MOST effective?

  6. 6 Question 6 Single choice Understanding and Applying the Scrum Framework

    An organisation runs a Sprint of three weeks. In the middle of the Sprint, the CEO asks the Scrum Team to add two new features that would strengthen a sales presentation. The Product Owner agrees without consulting the Developers. The Developers estimate the new features would take about one week and say the existing Sprint Goal would be at risk. The Scrum Master is asked how to resolve the situation within Scrum. Which response is MOST consistent with the Scrum framework?

  7. 7 Question 7 Single choice Managing Products with Agility

    A Scrum Team has delivered working increments for six Sprints. The Product Owner is preparing a stakeholder forecast for a major launch. Stakeholders want a single date. The Product Owner has a fixed budget and wants to measure progress toward the launch in terms the business understands. The Scrum Master proposes a measure that focuses on whether the product is delivering value, rather than on output activity. Which measure is MOST aligned with Scrum's product value focus?

  8. 8 Question 8 Single choice Understanding and Applying the Scrum Framework

    The Developers of a Scrum Team are required to test manually in a separate test phase after each Sprint, and the Product Owner wants that phase removed to shorten release cycles. The Scrum Team has no automated test suite, and the organisation prohibits releases without evidence of test coverage. The Scrum Master is discussing how to incorporate testing into the Definition of Done. Which change BEST aligns with Scrum's commitment to transparency and quality?

  9. 9 Question 9 Single choice Developing People and Teams

    A Scrum Master facilitates a Sprint Retrospective for a team that has missed its Sprint Goal three times in a row. Several team members are quiet, and one senior Developer dominates the discussion and blames the Product Owner for shifting priorities. The Scrum Master wants the session to produce concrete improvements that the team owns. Which facilitation technique is MOST effective here?

  10. 10 Question 10 Single choice Managing Products with Agility

    A business analyst asks the Scrum Team to commit to delivering a specific set of features by a contractual date that is four months away. The Developers' forecast, based on recent throughput, shows they can deliver roughly two-thirds of the requested scope by that date. The Product Owner has authority to set priorities but cannot change the contract. The Scrum Master needs to help the Product Owner deal with the gap in a Scrum-consistent way. What should the Product Owner do FIRST?

  11. 11 Question 11 Single choice Understanding and Applying the Scrum Framework

    A Scrum Master reviews the Daily Scrum at a team that has grown from five to twelve people split across two time zones. The meeting has become a series of status reports to the Scrum Master, lasting 45 minutes, and the Developers rarely talk to each other. The Scrum Master wants the event to fulfil its purpose of inspecting progress toward the Sprint Goal and adapting the Sprint Backlog. Which change is the MOST appropriate?

  12. 12 Question 12 Single choice Managing Products with Agility

    A Product Owner is deciding whether to include a feature that a key customer has requested. Analysis shows the feature would take three Sprints, and the customer has said they might switch vendors if it is not delivered in two Sprints. Meanwhile, a large group of users has reported a usability problem that affects far more customers daily. The Product Owner is trying to choose the next Product Backlog item to work on. Which decision BEST reflects Scrum's approach to ordering the Product Backlog?

These are 12 of the 298 questions in the full PSM-I pack.

Get All 298 Questions

Get all 298 questions & answers

726 Satisfied customers
94.3% Pass rate feedback
82.1% Said questions matched
94% Found material helpful

Full access options for Scrum PSM-I

Self-study

PDF Version

$40.00 $20.00
  • 298 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 298 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PSM-I Exam (Professional Scrum Master I) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed