2026 Actual Scrum PSM-II Dumps, Updated Exam Questions for Guaranteed Pass

Professional Scrum Master II - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorScrum
Exam codePSM-II
Exam nameProfessional Scrum Master II
Questions in pack75
Last updatedNovember 22, 2026
Related certificationsProfessional Scrum Master

Free practice questions with explanations

Scrum PSM-II Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
14
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Understanding and Applying the Scrum Framework

    A Scrum Team at a payments company has delivered a Sprint Increment every two weeks for six months. The Product Owner reports that stakeholders now mostly review the Increment at the Sprint Review and then ask for changes in a separate weekly steering meeting, so the Sprint Review has become a status presentation. The Scrum Master notices that the Developers rarely adapt their plan when the Sprint Goal becomes obsolete mid-Sprint, because they treat the Sprint Backlog as fixed. The organisation requires each Sprint Review to influence the Product Backlog without adding new meetings. Which action should the Scrum Master take FIRST?

  2. 2 Question 2 Single choice Understanding and Applying the Scrum Framework

    A product team building a logistics platform has a Definition of Done that includes unit tests, code review, and deployment to a staging environment. In the last Sprint, the Developers marked a feature Done, but during the Sprint Review it was discovered that the feature had no integration test coverage and the performance team had not validated it. The Product Owner wants the Increment released to production tonight to meet a client date. The company's regulator requires that every released change is verified against the organisation's quality standard. What should the Scrum Master recommend?

  3. 3 Question 3 Single choice Developing People and Teams

    A newly formed Scrum Team of seven people in a government agency has a Product Owner who assigns tasks to individual Developers each morning and approves every technical design decision. The Developers are experienced but have been trained to wait for instructions. The agency's leadership wants the team to be self-managing within three months, but the Product Owner believes the team needs close supervision because of a recent failed project. The Scrum Master has been asked to move the team toward self-management. Which action is the BEST first step?

  4. 4 Question 4 Multiple choice Developing People and Teams

    A Scrum Master coaches a team whose Developers have just started to self-organise. Two Developers keep escalating technical disagreements to the Product Owner, who then makes architecture decisions for them. The Scrum Master wants the team to resolve these disagreements internally while keeping the Product Owner focused on value. Which TWO actions best support this goal? (Choose two.)

  5. 5 Question 5 Drag and drop Managing Products with Agility

    A Product Owner for a healthcare scheduling product must manage the Product Backlog for three teams and a large group of stakeholders with conflicting priorities. The Scrum Master wants to help the Product Owner match each practice to the purpose it serves. Match each practice to the Product Backlog management purpose it primarily supports.

    Drag each item onto its matching target. On a phone: tap an item, then tap a target.

    Ordering backlog items by value and risk before each Sprint Planning
    Keeping the Product Backlog visible to all stakeholders in a shared tool
    Refining the top items so they are ready for selection in Sprint Planning
    Fixed scope agreed with the sponsor
    Ready items available for the Sprint
    Maximising the value of work
    Transparency of the backlog
  6. 6 Question 6 Single choice Managing Products with Agility

    A Product Owner for an insurance claims application receives requests from the legal department, the call centre, and the finance team. Each group insists that its request is the highest priority and demands delivery in the next Sprint. The Product Backlog currently has 140 items with no ordering beyond the order they were entered. Developers complain that they cannot start Sprint Planning until someone decides what matters most. The Scrum Master wants a sustainable approach that gives the Product Owner clear authority. What should the Product Owner do FIRST?

  7. 7 Question 7 Dropdown Managing Products with Agility

    A Product Owner has a Product Backlog with items whose forecasts keep changing as the team learns more. The Product Owner wants a concise way to show stakeholders the remaining work and how it changes over time, without implying a fixed delivery date. The Scrum Master suggests using a Product Backlog commitment measure. Complete the statement by selecting the correct value for each blank.

    Choose the correct value for each blank.

    The Product Owner tracks progress toward the using a that shows remaining work against the total scope, so that changes in scope are visible.
  8. 8 Question 8 Single choice Managing Products with Agility

    A product company is developing a mobile banking app. A key enterprise customer has asked for a feature that would take the team about four Sprints. The customer's account manager has promised a delivery date to the customer's board. Meanwhile, the Product Owner has learned from usage data that the most valuable improvement is a faster login flow, which would take one Sprint. The Scrum Team has agreed that the customer feature should still be considered. The account manager insists the promised feature must be included in the next Sprint. What should the Product Owner do?

  9. 9 Question 9 Order list Developing and Delivering Products Professionally

    A Scrum Team at an e-commerce company discovers during a Sprint that a third-party payment library they depend on has a security vulnerability that affects their checkout flow. The Sprint Goal is at risk and the Developers need to respond in a way that respects the Scrum framework and the team's Definition of Done. Arrange the steps in the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Record the vulnerability and the response as a learning item for the next Sprint Retrospective.
    2. Assess the vulnerability's impact on the Sprint Goal and the Increment with the Developers.
    3. Inform the Product Owner and make the risk transparent to stakeholders.
    4. Decide with the Product Owner whether to renegotiate the Sprint scope or the Sprint Goal.
    5. Adjust the Sprint Backlog so the security fix is included and the Definition of Done is still met.
  10. 10 Question 10 Single choice Developing and Delivering Products Professionally

    A team building a trading platform has a Sprint Backlog item to replace an outdated encryption module. The Developers are concerned that the new module has never been tested under production load, and the platform handles millions of transactions per day. The Product Owner wants the replacement finished within the Sprint to meet a regulatory deadline. The organisation's security policy prohibits deploying unverified cryptographic code to production. The Scrum Master is asked how the team should manage this technical risk within Scrum. What is the BEST recommendation?

  11. 11 Question 11 Multiple choice Developing and Delivering Products Professionally

    A Scrum Team in a medical device company is reviewing a backlog of technical risks, including fragile legacy modules, a shortage of automated regression tests, and an unclear deployment process. The Product Owner asks the Scrum Master which practices will help the team manage technical risk on an ongoing basis without stopping delivery. Which TWO practices best meet this need? (Choose two.)

  12. 12 Question 12 Single choice Evolving the Agile Organization

    A large bank has adopted Scrum in twelve teams, but the annual performance review still rewards individual contributors for personal output, and project managers still approve every Sprint Backlog. Team members say they feel pressure to protect their individual metrics and avoid raising impediments in the Sprint Retrospective. Senior leaders want the teams to become genuinely accountable for outcomes, but changes to the reward system require HR approval, which takes six months. Which action should the Scrum Master recommend FIRST?

  13. 13 Question 13 Dropdown Evolving the Agile Organization

    A Scrum Master at an insurance company wants to help leaders understand the organisation's current state of Scrum adoption before proposing structural changes. The Scrum Master decides to observe the teams, interview stakeholders, and review how decisions are made. Complete the statement by selecting the correct value for each blank.

    Choose the correct value for each blank.

    The Scrum Master is practising by inspecting the organisation's culture and decision-making, and then adapting the change plan through .
  14. 14 Question 14 Single choice Evolving the Agile Organization

    A retail company has three Scrum Teams that depend on a shared platform team. Each Sprint, the platform team receives requests from all three product teams and works on whichever request is loudest, causing frequent conflicts and missed Sprint Goals. The platform team's manager insists that a single standard process is needed to resolve the conflicts, and the Scrum Masters believe the teams should decide their own dependencies. The Scrum Masters want an approach that improves collaboration without creating a new layer of approval. What should they propose?

These are 14 of the 75 questions in the full PSM-II pack.

Get All 75 Questions

Get all 75 questions & answers

747 Satisfied customers
93.1% Pass rate feedback
82.7% Said questions matched
95% Found material helpful

Full access options for Scrum PSM-II

Self-study

PDF Version

$40.00 $20.00
  • 75 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 75 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PSM-II Exam (Professional Scrum Master II) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed