Exam Information
Free practice questions with explanations
Scrum PSM-II Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understanding and Applying the Scrum Framework
A Scrum Team at a payments company has delivered a Sprint Increment every two weeks for six months. The Product Owner reports that stakeholders now mostly review the Increment at the Sprint Review and then ask for changes in a separate weekly steering meeting, so the Sprint Review has become a status presentation. The Scrum Master notices that the Developers rarely adapt their plan when the Sprint Goal becomes obsolete mid-Sprint, because they treat the Sprint Backlog as fixed. The organisation requires each Sprint Review to influence the Product Backlog without adding new meetings. Which action should the Scrum Master take FIRST?
Correct Answer: AExplanationThe Sprint Review exists to inspect the Increment and adapt the Product Backlog with stakeholders, so the first step is coaching the Product Owner and stakeholders toward that purpose rather than changing the schedule or adding ceremonies. Moving the steering meeting into the review only relocates the status-report pattern and does not change how stakeholders engage with the Increment. Adding a daily re-planning checkpoint creates a new event that conflicts with the Daily Scrum's purpose and the fixed Sprint Goal approach. Extending the review to half a day deepens the status presentation rather than making the Increment the focus of adaptation.
-
2 Question 2 Single choice Understanding and Applying the Scrum Framework
A product team building a logistics platform has a Definition of Done that includes unit tests, code review, and deployment to a staging environment. In the last Sprint, the Developers marked a feature Done, but during the Sprint Review it was discovered that the feature had no integration test coverage and the performance team had not validated it. The Product Owner wants the Increment released to production tonight to meet a client date. The company's regulator requires that every released change is verified against the organisation's quality standard. What should the Scrum Master recommend?
Correct Answer: DExplanationThe Definition of Done is the shared quality standard that defines when an Increment is Done, and an item that does not meet it cannot be released as Done. The regulator's requirement reinforces that every release must satisfy the organisation's standard, so the feature must stay out of the release. Releasing now and fixing the standard later violates transparency and the regulatory constraint. Letting the Product Owner pick items per feature undermines the shared commitment, and per-client Definitions of Done fragment the Increment's meaning.
-
3 Question 3 Single choice Developing People and Teams
A newly formed Scrum Team of seven people in a government agency has a Product Owner who assigns tasks to individual Developers each morning and approves every technical design decision. The Developers are experienced but have been trained to wait for instructions. The agency's leadership wants the team to be self-managing within three months, but the Product Owner believes the team needs close supervision because of a recent failed project. The Scrum Master has been asked to move the team toward self-management. Which action is the BEST first step?
Correct Answer: BExplanationSelf-managing teams need explicit agreement on who decides what, and the Scrum Master's first move is to facilitate that conversation so the Product Owner and Developers share a common picture of decision rights. A rotating task-assignment role mimics management without resolving the authority question and may reinforce dependence. Removing the Product Owner and adding a project manager contradicts Scrum's accountabilities. Increasing the frequency of planning sessions gives the Product Owner more control and works against self-management.
-
4 Question 4 Multiple choice Developing People and Teams
A Scrum Master coaches a team whose Developers have just started to self-organise. Two Developers keep escalating technical disagreements to the Product Owner, who then makes architecture decisions for them. The Scrum Master wants the team to resolve these disagreements internally while keeping the Product Owner focused on value. Which TWO actions best support this goal? (Choose two.)
Correct Answer: B, EExplanationCoaching Developers toward shared decision methods such as spikes or small experiments builds their ability to resolve technical questions without escalation, and making disagreements visible in the Daily Scrum lets the whole team contribute. Making the Product Owner the approver for architecture decisions reinforces the escalation pattern the Scrum Master is trying to break. Bringing in an external architect removes ownership from the team entirely. Excluding technical disagreements from the Retrospective hides the very friction the team needs to examine and learn from.
-
5 Question 5 Drag and drop Managing Products with Agility
A Product Owner for a healthcare scheduling product must manage the Product Backlog for three teams and a large group of stakeholders with conflicting priorities. The Scrum Master wants to help the Product Owner match each practice to the purpose it serves. Match each practice to the Product Backlog management purpose it primarily supports.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Ordering backlog items by value and risk before each Sprint PlanningKeeping the Product Backlog visible to all stakeholders in a shared toolRefining the top items so they are ready for selection in Sprint PlanningFixed scope agreed with the sponsorReady items available for the SprintMaximising the value of workTransparency of the backlogCorrect Answer:- Ordering backlog items by value and risk before each Sprint Planning → Maximising the value of work
- Keeping the Product Backlog visible to all stakeholders in a shared tool → Transparency of the backlog
- Refining the top items so they are ready for selection in Sprint Planning → Ready items available for the Sprint
ExplanationOrdering items by value and risk is how the Product Owner maximises the value delivered by the Developers, which is the central Product Backlog management purpose. Keeping the backlog visible in a shared tool supports transparency so that stakeholders and Developers share the same understanding of what is planned. Refining top items so they are ready makes work available for selection in Sprint Planning. The fixed scope option conflicts with the empirical, emergent nature of the Product Backlog, which is never a fixed commitment.
-
6 Question 6 Single choice Managing Products with Agility
A Product Owner for an insurance claims application receives requests from the legal department, the call centre, and the finance team. Each group insists that its request is the highest priority and demands delivery in the next Sprint. The Product Backlog currently has 140 items with no ordering beyond the order they were entered. Developers complain that they cannot start Sprint Planning until someone decides what matters most. The Scrum Master wants a sustainable approach that gives the Product Owner clear authority. What should the Product Owner do FIRST?
Correct Answer: DExplanationThe Product Owner is the single person accountable for ordering the Product Backlog, and ordering by the value each item contributes to agreed outcomes gives the authority a defensible basis. Representatives arguing in Sprint Planning turns the event into a negotiation and places the ordering decision in the wrong forum. Separate backlogs per group violate the single Product Backlog principle and fragment the product's value. Rotating Sprint Goals by stakeholder group sacrifices the coherent goal each Sprint should pursue.
-
7 Question 7 Dropdown Managing Products with Agility
A Product Owner has a Product Backlog with items whose forecasts keep changing as the team learns more. The Product Owner wants a concise way to show stakeholders the remaining work and how it changes over time, without implying a fixed delivery date. The Scrum Master suggests using a Product Backlog commitment measure. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
The Product Owner tracks progress toward the using a that shows remaining work against the total scope, so that changes in scope are visible.Correct Answer:The Product Owner tracks progress toward the Product Goal using a burndown chart that shows remaining work against the total scope, so that changes in scope are visible.
ExplanationThe Product Goal is the long-term objective that the Product Backlog is committed to, and progress toward it is measured against the Product Backlog, which is where remaining work and total scope are visible. A burndown chart shows remaining work over time and makes scope changes visible when the total line moves. The Sprint Goal is scoped to a single Sprint, while the Definition of Done describes quality and says nothing about progress. The Sprint Backlog board tracks only the current Sprint, and velocity shows throughput rather than remaining work.
-
8 Question 8 Single choice Managing Products with Agility
A product company is developing a mobile banking app. A key enterprise customer has asked for a feature that would take the team about four Sprints. The customer's account manager has promised a delivery date to the customer's board. Meanwhile, the Product Owner has learned from usage data that the most valuable improvement is a faster login flow, which would take one Sprint. The Scrum Team has agreed that the customer feature should still be considered. The account manager insists the promised feature must be included in the next Sprint. What should the Product Owner do?
Correct Answer: CExplanationThe Product Owner's accountability is to maximise value, and transparency about the trade-off with the account manager and customer lets the decision rest on real evidence rather than a promise already made. Pushing the customer feature into the Sprint regardless of value ignores the usage data and turns the Sprint Backlog into a promise. Splitting the team dilutes focus and the Scrum Team does not dictate what the Developers work on that way. Negotiating a fixed date and deleting valuable work reverses empiricism and treats the Product Backlog as fixed scope.
-
9 Question 9 Order list Developing and Delivering Products Professionally
A Scrum Team at an e-commerce company discovers during a Sprint that a third-party payment library they depend on has a security vulnerability that affects their checkout flow. The Sprint Goal is at risk and the Developers need to respond in a way that respects the Scrum framework and the team's Definition of Done. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Record the vulnerability and the response as a learning item for the next Sprint Retrospective.
- Assess the vulnerability's impact on the Sprint Goal and the Increment with the Developers.
- Inform the Product Owner and make the risk transparent to stakeholders.
- Decide with the Product Owner whether to renegotiate the Sprint scope or the Sprint Goal.
- Adjust the Sprint Backlog so the security fix is included and the Definition of Done is still met.
Correct Answer:- Assess the vulnerability's impact on the Sprint Goal and the Increment with the Developers.
- Inform the Product Owner and make the risk transparent to stakeholders.
- Decide with the Product Owner whether to renegotiate the Sprint scope or the Sprint Goal.
- Adjust the Sprint Backlog so the security fix is included and the Definition of Done is still met.
- Record the vulnerability and the response as a learning item for the next Sprint Retrospective.
ExplanationThe team first assesses the impact so that the response is based on evidence, then makes the risk transparent to the Product Owner so that the decision on scope rests with the accountable person. With the Product Owner, they decide whether the Sprint Goal or scope must change, and only then do they adjust the Sprint Backlog, keeping the Definition of Done intact. Recording the event for the Retrospective comes last because it captures the learning after the response is complete. Adjusting the backlog before assessing impact or consulting the Product Owner would bypass transparency and the shared decision-making the framework requires.
-
10 Question 10 Single choice Developing and Delivering Products Professionally
A team building a trading platform has a Sprint Backlog item to replace an outdated encryption module. The Developers are concerned that the new module has never been tested under production load, and the platform handles millions of transactions per day. The Product Owner wants the replacement finished within the Sprint to meet a regulatory deadline. The organisation's security policy prohibits deploying unverified cryptographic code to production. The Scrum Master is asked how the team should manage this technical risk within Scrum. What is the BEST recommendation?
Correct Answer: BExplanationA Definition of Done that includes verification ensures that Increments meet the quality the policy requires, and making the risk visible lets the Product Owner and stakeholders decide with accurate information. Deploying unverified cryptographic code breaks the security policy even behind a feature flag. Delaying the review hides the progress and does not solve the verification gap. Relying on vendor figures bypasses the team's own evidence and the policy requirement for verification.
-
11 Question 11 Multiple choice Developing and Delivering Products Professionally
A Scrum Team in a medical device company is reviewing a backlog of technical risks, including fragile legacy modules, a shortage of automated regression tests, and an unclear deployment process. The Product Owner asks the Scrum Master which practices will help the team manage technical risk on an ongoing basis without stopping delivery. Which TWO practices best meet this need? (Choose two.)
Correct Answer: A, DExplanationAdding technical risk and debt items to the Product Backlog makes them visible and orderable alongside other work, so the Product Owner can weigh them against value. Strengthening the Definition of Done with automated testing and repeatable deployment builds quality into every Increment and reduces risk continuously. A separate team delivering only at year end defers risk and breaks the single-team accountability. Postponing all releases conflicts with the goal of frequent delivery, and concentrating knowledge in one person increases the risk rather than reducing it.
-
12 Question 12 Single choice Evolving the Agile Organization
A large bank has adopted Scrum in twelve teams, but the annual performance review still rewards individual contributors for personal output, and project managers still approve every Sprint Backlog. Team members say they feel pressure to protect their individual metrics and avoid raising impediments in the Sprint Retrospective. Senior leaders want the teams to become genuinely accountable for outcomes, but changes to the reward system require HR approval, which takes six months. Which action should the Scrum Master recommend FIRST?
Correct Answer: DExplanationMaking impediments visible and coaching leaders to remove them addresses the organisational obstacles now, while the longer HR process runs in parallel, which is the most effective first step under the constraint. Leaders bypassing HR would create governance problems and undermine trust in the change. Turning the Retrospective into an HR review destroys the psychological safety it depends on. Removing project managers abruptly ignores the organisation's current constraints and does not change the incentives that drive the behaviour.
-
13 Question 13 Dropdown Evolving the Agile Organization
A Scrum Master at an insurance company wants to help leaders understand the organisation's current state of Scrum adoption before proposing structural changes. The Scrum Master decides to observe the teams, interview stakeholders, and review how decisions are made. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
The Scrum Master is practising by inspecting the organisation's culture and decision-making, and then adapting the change plan through .Correct Answer:The Scrum Master is practising empiricism by inspecting the organisation's culture and decision-making, and then adapting the change plan through frequent inspection and adaptation.
ExplanationObserving teams and inspecting decisions to learn what is actually happening reflects empiricism, which relies on evidence from direct observation rather than assumption. Adapting the change plan through frequent inspection and adaptation keeps the transformation responsive as new evidence emerges. A fixed transformation roadmap and an annual reorganisation both assume the answers are known in advance, which contradicts empiricism. A single top-down mandate skips the learning the Scrum Master is trying to build.
-
14 Question 14 Single choice Evolving the Agile Organization
A retail company has three Scrum Teams that depend on a shared platform team. Each Sprint, the platform team receives requests from all three product teams and works on whichever request is loudest, causing frequent conflicts and missed Sprint Goals. The platform team's manager insists that a single standard process is needed to resolve the conflicts, and the Scrum Masters believe the teams should decide their own dependencies. The Scrum Masters want an approach that improves collaboration without creating a new layer of approval. What should they propose?
Correct Answer: DExplanationA joint cross-team planning forum with visible shared dependencies lets the Product Owners and platform team negotiate priorities directly without adding a new approval layer, which matches the constraint. Merging backlogs would create an unmanageable single backlog and conflicts with each team's accountability. A fixed schedule set by the platform manager reintroduces top-down control and removes the teams' ability to inspect and adapt. Building duplicate platform capability in every product team is wasteful and ignores the value of shared infrastructure.
These are 14 of the 75 questions in the full PSM-II pack.
Get All 75 QuestionsGet all 75 questions & answers
Full access options for Scrum PSM-II
Self-study
PDF Version
- 75 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 75 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 75 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PSM-II Exam (Professional Scrum Master II) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.