2026 Actual Scrum PSD Dumps, Updated Exam Questions for Guaranteed Pass

Professional Scrum Developer - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorScrum
Exam codePSD
Exam nameProfessional Scrum Developer
Questions in pack163
Last updatedNovember 21, 2026
Related certificationsProfessional Scrum Developer

Free practice questions with explanations

Scrum PSD Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
12
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Developing & Delivering Products Professionally

    A Scrum Team is building a payment feature. Their Definition of Done requires that all code is covered by automated tests and that changes are integrated continuously. A developer has written a new billing module and wants to design the work so that the tests drive the implementation and defects are caught within minutes of being introduced. The module must be delivered by the end of the Sprint, and the team has no dedicated QA role. Which approach BEST meets these constraints?

  2. 2 Question 2 Single choice Understanding and Applying the Scrum Framework

    A Scrum Team has completed three Sprints. Each Sprint Review shows a working increment, but stakeholders repeatedly say the product is not improving in the ways they expected. The Product Owner reports that the Product Backlog is ordered by the order in which stakeholders raised items, and the Developers have been completing items without checking whether they move any value measure. The Scrum Master wants the team to apply empiricism more rigorously. Which action should the Scrum Team take FIRST?

  3. 3 Question 3 Single choice Developing People and Teams

    A Scrum Team of eight Developers has a recurring pattern: one senior engineer makes most design decisions in private and then assigns tasks to others during the Daily Scrum. Junior members rarely challenge these decisions, and the Sprint Backlog is updated only by the senior engineer. The Scrum Master has been asked to help the team become self-managing within two Sprints, without removing the senior engineer from the team. Which intervention is MOST appropriate?

  4. 4 Question 4 Single choice Managing Products with Agility

    A product team forecasts release dates using a single Sprint Velocity figure averaged over the last four Sprints. The Sprints have varied from 28 to 61 points because the team recently absorbed two large legacy migrations. Stakeholders want a release date they can commit to externally in six weeks. The Product Owner must present a forecast that is honest about uncertainty and remains useful for release planning. Which approach BEST supports this?

  5. 5 Question 5 Single choice Developing & Delivering Products Professionally

    A Developer team maintains a service with a nightly build pipeline that runs unit tests, static analysis and a packaging step. Recently the pipeline has begun to fail intermittently because two integration tests share a database schema and occasionally run in parallel. The team must keep the pipeline under 15 minutes and must not disable the tests, because the Definition of Done requires them. Which change is the BEST fix?

  6. 6 Question 6 Single choice Managing Products with Agility

    A Product Owner manages a product with three customer segments whose needs conflict. Enterprise customers want advanced reporting, small business customers want faster onboarding, and a regulator requires audit logging by a fixed date. The Developers estimate that all three together exceed the capacity of the next two Sprints. Stakeholders are pressing for all items to be started at once. Which action is MOST consistent with product backlog management in Scrum?

  7. 7 Question 7 Single choice Understanding and Applying the Scrum Framework

    During a Sprint, a Developer discovers that an item selected for the Sprint Backlog cannot meet the Definition of Done because a dependency owned by another team will not be delivered until the next month. The Sprint has four days remaining. The Product Owner is unavailable until the Sprint Review. Which action is correct under the Scrum Framework?

  8. 8 Question 8 Multiple choice Developing & Delivering Products Professionally

    A Scrum Team wants its code and design decisions to remain understandable as the system grows, and it wants documentation to stay current without slowing delivery. Which TWO practices BEST achieve this? (Choose two.)

  9. 9 Question 9 Single choice Developing People and Teams

    A newly formed Scrum Team wants each of the following practices matched to the Scrum Team member or facilitative role primarily responsible for it. Match each item to its target.
    1. Facilitating the Daily Scrum so that the Developers stay focused on the Sprint Goal
    2. Keeping the team's working agreement visible and helping the team inspect how it works together
    3. Deciding the order of the Product Backlog items for the next Sprint
    Targets: Developers, Scrum Master, Product Owner

  10. 10 Question 10 Single choice Developing & Delivering Products Professionally

    A team building a mobile app uses continuous integration. A Developer's merge request modifies a shared authentication library. The pipeline shows that unit tests pass, but a static analysis gate fails with a warning about an unvalidated input path in code the Developer did not change. The release is scheduled for the end of the Sprint. Which response is BEST?

  11. 11 Question 11 Dropdown Managing Products with Agility

    Choose the correct value for each blank.

    Choose the correct value for each blank.

    A Product Owner wants stakeholders to see whether the product is delivering value between releases. The team tracks the number of Sprint Backlog items completed per Sprint and the proportion of Product Backlog items still open. The Product Owner decides to measure outcomes instead of output. The team chooses as a leading indicator of the product's value and as the Scrum artifact commitment that makes the measurement visible at each Sprint Review.
  12. 12 Question 12 Order list Understanding and Applying the Scrum Framework

    A Scrum Team is preparing a new Increment for release to a customer. The following steps are part of their release readiness process, but they are listed out of order. Put the steps in the correct order. Drag the steps into the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Deploy the verified Increment to production and record the release
    2. Run the automated deployment pipeline to a staging environment and verify behaviour
    3. Inspect the Increment with stakeholders at the Sprint Review and gather feedback
    4. Confirm each Product Backlog item in the release meets the Definition of Done

These are 12 of the 163 questions in the full PSD pack.

Get All 163 Questions

Get all 163 questions & answers

712 Satisfied customers
93.4% Pass rate feedback
82.5% Said questions matched
94% Found material helpful

Full access options for Scrum PSD

Self-study

PDF Version

$40.00 $20.00
  • 163 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 163 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PSD Exam (Professional Scrum Developer) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed