2026 Actual Scrum PSK-I Dumps, Updated Exam Questions for Guaranteed Pass

Professional Scrum with Kanban - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorScrum
Exam codePSK-I
Exam nameProfessional Scrum with Kanban
Questions in pack73
Last updatedNovember 21, 2026
Related certificationsProfessional Scrum Certifications

Free practice questions with explanations

Scrum PSK-I Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
13
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Scrum Framework Mastery

    A Scrum Team has been running Sprints of three weeks. During the Sprint, the Product Owner discovers that a competitor has released a feature that makes half of the Sprint Goal obsolete. The Developers are two days into the Sprint and have not yet finished any Product Backlog items. The Product Owner proposes cancelling the Sprint immediately and starting a new one next week to save time. The Scrum Master is asked what the team should do according to the Scrum Guide. Which response is most consistent with the Scrum Guide?

  2. 2 Question 2 Single choice Agile Metrics for Kanban in Scrum

    A Scrum Team using the Kanban Guide for Scrum Teams tracks its workflow on a board with columns for Ready, In Progress, Review and Done. Over the last eight weeks, the cycle time has been rising steadily while throughput has stayed roughly flat. A stakeholder asks the Scrum Master for a single metric that shows how predictable delivery timing is, so the team can set realistic expectations for customers. Which metric should the Scrum Master recommend, and what is its main purpose?

  3. 3 Question 3 Single choice Scrum Teams

    A Scrum Team has a board with a WIP limit of 4 on the In Progress column. Currently, 4 items are In Progress and a Developer has finished one of them and wants to pull a new item from Ready so that the team stays busy. Another Developer notices that the finished item is blocked waiting for a security review that has been pending for six days. The team is unsure whether to pull the new item or to address the blocked work. What is the best action to take?

  4. 4 Question 4 Single choice Integrating Scrum and Kanban

    A Scrum Team has been asked to combine Scrum with Kanban because its stakeholders want continuous delivery of support requests as they arrive, while the team still wants the regular rhythm of Sprint Reviews with stakeholders. The Product Owner proposes to drop the Sprint entirely and run only Kanban, since the flow of incoming requests is unpredictable. The Scrum Master points out that the Scrum Guide requires the Sprint timebox. Which approach best integrates Scrum and Kanban without compromising Scrum's fundamental principles?

  5. 5 Question 5 Multiple choice Scrum Framework Mastery

    A Scrum Team is reviewing its use of the Scrum artifacts. The Product Owner asks which of the following statements about Scrum artifacts and their commitments are correct according to the Scrum Guide. (Choose two.)

  6. 6 Question 6 Single choice Agile Metrics for Kanban in Scrum

    A Scrum Team has adopted the Kanban Guide for Scrum Teams and wants to understand why a recent backlog of work has stalled. The team has its workflow stages defined and tracks each item's start and finish times. The Scrum Master proposes to use the flow efficiency metric to find where the time is lost. Which statement best describes what flow efficiency reveals and how it should be used?

  7. 7 Question 7 Order list Scrum Teams

    A Scrum Team notices that items are frequently stuck in the Review column of its Kanban board, and the workflow definition no longer reflects how work actually moves. The Scrum Master wants the team to inspect and adapt its workflow definition in an appropriate sequence. The steps are: Drag the steps into the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Agree on the proposed change to the workflow definition, such as adding a step or changing a policy.
    2. Apply the change to the board and observe its effect over the next period of work.
    3. Gather flow data, such as cycle time and blocked item counts, for the Review column.
    4. Discuss the observed data with the team to identify where the workflow definition does not match reality.
  8. 8 Question 8 Dropdown Agile Metrics for Kanban in Scrum

    Choose the correct value for each blank.

    Choose the correct value for each blank.

    A Scrum Team's Kanban board shows that its average cycle time over the last 20 items is 6 days, while its throughput has been 4 items per week. Using Little's Law, the average number of items in progress equals throughput multiplied by average cycle time. The team wants to know the expected average number of items in progress, which is items, and the team should therefore review whether its WIP limit of is sensible.
  9. 9 Question 9 Single choice Scrum Framework Mastery

    A Scrum Team is working on a product with a Product Goal that will take several Sprints to achieve. At the Sprint Review, stakeholders present a new market opportunity that could significantly change the Product Goal. The Product Owner is unsure whether to update the Product Goal now or wait until the next Sprint Planning. The Scrum Guide states the Product Backlog is the single source of work and that the Product Goal is the commitment for it. What should the Product Owner do?

  10. 10 Question 10 Single choice Scrum Teams

    A Scrum Team uses a Kanban board with a Ready column, an In Progress column and a Done column. A Developer frequently moves items from Ready to In Progress without checking the Definition of Ready, leaving acceptance criteria undefined. The team observes that many items are returned from Done back to In Progress. The Scrum Master wants to improve how work items are managed. Which change best addresses the root cause while keeping the team's flow visible?

  11. 11 Question 11 Multiple choice Integrating Scrum and Kanban

    A Scrum Team wants to make its work more transparent by combining its Scrum practices with Kanban visualization. Which of the following practices are consistent with both frameworks and preserve the fundamental principles of Scrum? (Choose two.)

  12. 12 Question 12 Single choice Integrating Scrum and Kanban

    A Scrum Team plans to combine its Scrum events with Kanban practices. The team needs to match each of the following practices to the Scrum event where it is most appropriately applied:
    1. Reviewing the board's flow metrics to find the bottleneck
    2. Agreeing the Sprint Goal and selecting items for the Sprint Backlog
    3. Inspecting the Increment with stakeholders and adapting the Product Backlog
    Targets: Sprint Planning, Sprint Review, Sprint Retrospective

    Which mapping is correct?

  13. 13 Question 13 Single choice Agile Metrics for Kanban in Scrum

    A Scrum Team tracks its work on a Kanban board and has set up a metric to visualize how long items have been in each column. A Product Owner asks the Scrum Master to show the expected delivery date for a large set of items the business wants in the next quarter. The Scrum Master knows that the team's cycle times vary widely, from 2 days to 25 days. Which approach best supports a realistic forecast?

These are 13 of the 73 questions in the full PSK-I pack.

Get All 73 Questions

Get all 73 questions & answers

749 Satisfied customers
93.9% Pass rate feedback
83.8% Said questions matched
97% Found material helpful

Full access options for Scrum PSK-I

Self-study

PDF Version

$40.00 $20.00
  • 73 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 73 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PSK-I Exam (Professional Scrum with Kanban) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed