1 Question 1 Single choice Delivery
A product team delivers a new reporting feature every four weeks. The product owner wants to know whether the customers actually value the recent releases before committing budget to the next quarter. The team has access to a pilot group of twelve customers who meet weekly, and the organisation's sign-off cycle means any change to the roadmap takes three weeks to approve. Customer satisfaction surveys are only sent quarterly. Which action is the BEST way to evaluate customer satisfaction with the recent increments?
Correct Answer: AExplanationThe pilot group meets weekly, so it provides the fastest feedback loop on the increments actually delivered, which is exactly what an agile team needs before the three-week approval cycle makes roadmap changes expensive. Waiting for quarterly surveys delays learning past several releases. Velocity measures team throughput, not customer value, so it cannot stand in for satisfaction. Complaint volume is a lagging and biased signal, since satisfied customers rarely file tickets.
-
2 Question 2 Single choice Delivery
A distributed team has been tracking its defect rate on a dashboard for six sprints. The rate has risen steadily, and the team lead suspects the cause is a recent change in how the testing environment is provisioned. The lead must decide which analysis technique to apply first to identify the underlying cause rather than the symptoms, while avoiding a lengthy formal investigation that would consume a full sprint. Which approach is MOST appropriate as the first step?
Correct Answer: BExplanationIshikawa (fishbone) diagramming is a collaborative root cause technique that lets the team test the environment hypothesis alongside other categories without a lengthy formal process, which fits the sprint constraint. Changing the denominator would distort the metric rather than explain it. Fixing every defect individually treats symptoms and ignores the systemic cause. Adding regression tests raises cost and cycle time without identifying why the defects are increasing.
-
3 Question 3 Single choice Leadership
A newly formed team of eight engineers has been meeting for three weeks. During retrospectives, the two most senior engineers speak for most of the time, and the others give short answers or stay silent. The agile coach notices that junior members look away and shift in their seats whenever a senior engineer disagrees with an idea. The coach wants to build an environment of trust so that everyone contributes candidly and experiments with ideas. Which action should the coach take FIRST?
Correct Answer: CExplanationThe coach has read non-verbal cues such as looking away and shifting, which signal discomfort rather than disengagement. Understanding those concerns first lets the coach choose an intervention that addresses the real cause of low trust. Mandatory turns and anonymous ballots are structural fixes applied before the diagnosis, and a timer for senior members may create resentment and does not build trust. Starting with the private conversation follows an emotional intelligence approach to supporting the team.
-
4 Question 4 Single choice Leadership
A team has a recurring problem: stories routinely spill over into the next sprint, and the team blames an external dependency. The scrum master wants to resolve the problem in a timely way and determine the resolution strategy that adds the most value. Analysis shows that the external dependency accounts for only one of the spillovers, while poorly sized stories and unclear acceptance criteria account for most of them. The product owner wants to escalate the dependency to senior management immediately. Which action BEST enables the team to resolve the problem with the most value?
Correct Answer: AExplanationThe root cause analysis shows that most spillovers come from sizing and acceptance criteria, which the team controls, so improving them delivers the greatest value. The external dependency still matters, so tracking it separately as an impediment keeps it visible without letting it dominate. Escalating the dependency alone addresses a minority of the problem. Lengthening sprints or hiding the metric conceals the problem rather than resolving it.
-
5 Question 5 Single choice Mindset
A company wants to build an internal tool for a regulated financial process. The requirements are not yet defined, and the regulators are still interpreting new rules that may change the process in ways nobody can predict. Leaders want to know which complexity domain describes this situation so they can choose an approach. Using the Cynefin framework, which classification and response BEST fits this scenario?
Correct Answer: CExplanationThe regulatory interpretation is still evolving and outcomes cannot be predicted in advance, which places the work in the complex domain in Cynefin. Here cause and effect emerge over time, so the right response is to probe with small experiments and sense the results. Treating it as clear or complicated assumes the answer can be determined up front, which the scenario explicitly denies. Chaotic would require urgent stabilisation, which the stem does not describe.
-
6 Question 6 Single choice Mindset
A product group is evaluating whether an agile approach suits a new project. The project has a fixed regulatory deadline, a contract that specifies the scope in detail, and a team with no prior agile experience. An agile suitability assessment returns a moderate score, with strong indicators for predictability and weak indicators for collaboration readiness. Leadership wants a recommendation that is both realistic and respects these results. Which recommendation is MOST appropriate?
Correct Answer: CExplanationThe suitability result is mixed, so a hybrid model that respects the fixed milestones while gradually building collaboration capability reflects both the score and the constraints. Adopting full agile ignores the contractual and regulatory limits that the assessment highlights. Rejecting agile outright disregards the real benefits of iteration and the team's need to build readiness. Delaying for a year wastes the opportunity to learn and does not follow from the assessment.
-
7 Question 7 Single choice Product
A product owner has a backlog of sixty items for an e-commerce platform. Stakeholders in marketing and finance disagree strongly about priority, and the development team cannot size several items because the requirements are vague. The sprint planning meeting is in two days. The product owner needs to make the backlog ready in a way that preserves the stakeholders' collaboration and gives the team enough clarity to estimate. Which action should the product owner take FIRST?
Correct Answer: AExplanationA focused refinement session with the stakeholders and the team clarifies the most important items first, which resolves the vague requirements that block sizing and creates shared understanding before prioritisation. Sizing sixty unclear items wastes effort and does not resolve the priority conflict. Letting one stakeholder decide undermines the collaborative prioritisation expected with the customer. Splitting all items into tasks before clarifying them creates detail without shared understanding.
-
8 Question 8 Multiple choice Product
A team is preparing to demonstrate the latest increment to stakeholders. The product goal is to increase self-service order completion, and the sprint goal states a specific target. The stakeholders want evidence that the increment is delivering value rather than just finished features. Which TWO actions would BEST help the team demonstrate measurable value from the increment? (Choose two.)
Correct Answer: C, DExplanationComparing completion rates against a pre-release baseline and reporting against success criteria defined in advance both measure whether the increment moves the product goal, which is what value delivery means. Story points, closed stories and burndown charts measure output and schedule, not customer outcome. Demonstrating every feature emphasises breadth rather than whether the value target was achieved.
-
9 Question 9 Multiple choice Product
A team with a visualised board is struggling to keep its work data current. Team members update cards inconsistently, and the flow metrics shown to stakeholders no longer reflect reality. The Scrum Master wants to re-establish reliable information that stakeholders can trust. Which TWO actions would MOST effectively address this? (Choose two.)
Correct Answer: C, DExplanationShared column definitions and entry criteria give the team a common understanding of state, and reviewing and updating the board during stand-up keeps the data current and collectively owned. A single person updating cards daily creates a bottleneck and reduces ownership. Removing the board hides the problem rather than fixing it, and adding columns increases the update burden without improving accuracy.
-
10 Question 10 Single choice Delivery
A team has been running a retrospective-based improvement cycle for several months. Stakeholders complain that the same impediments keep resurfacing, such as slow environment provisioning, even though the team logs them every sprint. The Scrum Master needs to ensure lessons learned prevent recurrence rather than being recorded and forgotten. Which action would BEST ensure the lessons drive lasting change?
Correct Answer: AExplanationAssigning ownership and a measurable countermeasure, then verifying its effect in later retrospectives, closes the loop so that lessons actually prevent recurrence. Logging more impediments adds records without action. Storing notes for reference is passive and does not change behaviour. Escalating everything removes the team's ability to act on problems it controls and delays the response.
-
11 Question 11 Single choice Mindset
A large organisation is exploring whether a particular team should use Scrum, Kanban or a hybrid approach. The team's work consists of unpredictable production support requests that arrive continuously, along with occasional planned feature work. Leaders want an approach that matches the actual work pattern and avoids forcing artificial sprint boundaries onto interrupt-driven demand. Which recommendation is MOST appropriate?
Correct Answer: AExplanationKanban handles continuous, unpredictable demand through visible flow and work-in-progress limits, and a dedicated lane keeps planned feature work distinct without imposing artificial sprint boundaries. Two-week Scrum sprints would make interrupt-driven requests awkward to plan. One-day sprints are impractical and still force planning overhead onto flow-based work. A monthly change board would delay urgent production support and does not reflect the agile suitability needs described.
These are 11 of the 481 questions in the full PMI-ACP pack.
Get All 481 QuestionsGet all 481 questions & answers
Full access options for PMI PMI-ACP
Self-study
PDF Version
- 481 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 481 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 481 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PMI-ACP Exam (PMI Agile Certified Practitioner) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.