Exam Information
Free practice questions with explanations
PMI PMI-SP Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 11
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Schedule Monitoring and Controlling
A construction program uses a integrated schedule covering six subcontractors. At the monthly status cycle, two subcontractors report activity percent-complete values that conflict with their timesheet-based resource logs; one reports 100 percent complete on a foundation pour while its crew hours show only 70 percent of planned effort. The program's change control board meets weekly and the sponsor has asked that the reported schedule remain defensible for the next audit. The scheduler must decide how to proceed with the status update before the baseline variance report is issued. What is the BEST next action?
Correct Answer: BExplanationStatus should be collected from activity owners but validated before it changes the schedule, especially when an audit trail is required. Holding the activity at its last verified progress and reconciling the claim with timesheets and inspections keeps the schedule defensible while the owner is queried. Recording the 100 percent claim unchecked lets an unsupported figure distort variance reporting. Resetting the activity to baseline discards valid progress that the program has already verified. Deriving percent complete purely from hours assumes a linear effort-to-progress relationship that the foundation pour may not follow, so it is not a reliable replacement for the owner's evidence.
-
2 Question 2 Single choice Schedule Planning and Development
A medical device company is developing a schedule for a regulated product release. The clinical validation work package can start only after the software build is frozen, and the regulatory submission cannot begin until both validation and documentation are complete. The team has been asked to show the critical path without inflating it with unnecessary links. The schedule planner has entered the software freeze as a finish-to-start predecessor of validation, but has also linked documentation to validation with a start-to-start relationship and an overall lag of ten days. Auditors require that the schedule logic reflect true dependencies. What is the MOST appropriate correction to the sequencing logic?
Correct Answer: BExplanationThe regulatory submission depends on both validation and documentation being complete, and the documentation dependency on validation is a true completion dependency that should be finish-to-start. The ten-day lag is an artificial padding that hides the real logic and distorts the critical path, so removing it is correct. A negative lead on a start-to-start link still encodes a start relationship that does not match the stated dependency. Deleting the link and using a hard constraint breaks the dependency and hides the true constraint from auditors. Converting the freeze to start-to-start would allow validation to begin before the build is frozen, which violates the stated predecessor.
-
3 Question 3 Single choice Schedule Strategy
A government transport agency is establishing scheduling governance for a portfolio of rail upgrade projects. The agency's contract requires that the schedule baseline be archived and that any change to the baseline after approval goes through a formal control process. Project teams have been updating baselines directly in their scheduling tool after minor scope adjustments, leaving the audit trail incomplete. The program manager wants a configuration management approach that keeps the baseline controlled without preventing legitimate schedule maintenance. Which policy BEST meets these requirements?
Correct Answer: DExplanationSeparating a controlled baseline from a working schedule model, with changes routed through a documented change request and saved as new baseline versions, gives the audit trail the contract requires while still allowing maintenance. Allowing edits under an effort threshold bypasses change control on the basis of size rather than governance. Moving the baseline to a spreadsheet breaks the link to the scheduling tool and weakens traceability. Freezing edits for the whole contract makes the schedule unusable for management and ignores the legitimate need to rebaseline after approved changes.
-
4 Question 4 Single choice Stakeholder Communications Management
An enterprise software rollout is running two months late on its schedule because a third-party integration vendor has not delivered its interface. The executive steering committee meets in four days and expects a status update. The communication management plan requires that senior stakeholders receive written schedule status along with the impact of corrective actions. The scheduler has already produced a revised forecast showing a sixty-day slip for the go-live milestone, but the project manager is considering a recovery plan that might bring the slip to twenty days if the vendor accelerates. What is the MOST appropriate way to report this to the steering committee?
Correct Answer: CExplanationThe committee needs the current forecast stated plainly, with the recovery option shown as a conditional scenario whose assumptions and required decision are explicit. Presenting only the optimistic twenty-day figure hides the real exposure and risks losing credibility if the vendor does not accelerate. Waiting for vendor confirmation delays a required update the communication plan calls for. Sending a raw network diagram puts an interpretive burden on executives and fails the requirement for a clear written status and corrective-action impact.
-
5 Question 5 Single choice Schedule Closeout
A telecommunications program has completed its final network cutover and the sponsor is preparing to accept the contractual schedule deliverables. The schedule team needs to produce the final reports and close out the schedule files. The contract requires that the final schedule model, the schedule management plan, and the periodic status reports be retained for seven years for regulatory audit. The team also wants to capture lessons learned from the schedule performance. Which action should be taken FIRST to support formal closeout of the schedule?
Correct Answer: DExplanationFormal acceptance of the contractual schedule components by the sponsor is the gate that precedes closeout activities, since archiving and reporting should reflect the accepted final versions. Archiving first risks retaining versions the sponsor has not accepted, which could later be disputed. Publishing variance reports before acceptance produces figures that may change. Updating process assets with lessons learned is valuable but is a later step that depends on the performance evaluation being complete and accepted.
-
6 Question 6 Single choice Schedule Monitoring and Controlling
A defense contractor is managing a schedule that includes four subcontractors. Subcontractor schedules are delivered in different tool formats and at different levels of granularity, and the prime contractor must audit them against scheduling best practices before integrating them into the master schedule. One subcontractor's schedule shows 412 activities with no logic links to the rest of its network, 38 activities with hard constraints, and a critical path that runs through summary tasks. The audit must identify issues that affect the master schedule. Which audit finding is MOST significant and should be escalated first?
Correct Answer: BExplanationActivities with no logic links make the network unreliable, because the scheduling engine cannot determine their true dependencies and the critical path computed from the file is not trustworthy. This defect invalidates integration into the master schedule and must be escalated first. Hard constraints are a concern but are generally visible and can be reviewed after logic is repaired. A critical path routed through summary tasks is a logic-quality issue that depends on the network being sound. Tool format differences are a practical integration matter, not a schedule-integrity defect requiring purchase of software.
-
7 Question 7 Multiple choice Schedule Planning and Development
A pharmaceutical manufacturer is building a schedule for a new packaging line. The team is sequencing activities for equipment installation, qualification, and operator training, and must ensure that the schedule reflects real dependencies rather than convenience links. Which TWO actions best support sound activity sequencing under these conditions? (Choose two.)
Correct Answer: B, CExplanationQualification runs require both installed equipment and trained operators, so explicit finish-to-start predecessors from installation and training to qualification capture the real dependencies, and external vendor delivery should appear as its own predecessor. Fixing qualification to calendar dates detaches it from the work it depends on and produces an unreliable schedule. Collapsing installation and qualification into a summary hides logic that auditors need to see. Blanket contingency on durations does not represent sequencing and conceals the critical path.
-
8 Question 8 Order list Schedule Strategy
A healthcare IT organization is preparing a schedule management plan for a multi-year electronic records migration that will be audited by a regulator. The schedule approach must reflect the project's unique characteristics, including enterprise governance and the regulator's review requirements. Arrange the steps in the order they must be performed to establish the schedule approach and its controls.
Drag the steps into the correct order, or use the arrows.
- Define performance thresholds and the schedule change approval authorities.
- Obtain approval of the schedule management plan from the steering committee and the regulator liaison.
- Review enterprise environmental factors and organizational process assets to identify constraints on scheduling.
- Document the scheduling methodology, tool selection, and activity granularity rules in the schedule management plan.
- Establish the baseline schedule configuration policies for storage, retrieval, and change control.
Correct Answer:- Document the scheduling methodology, tool selection, and activity granularity rules in the schedule management plan.
- Review enterprise environmental factors and organizational process assets to identify constraints on scheduling.
- Define performance thresholds and the schedule change approval authorities.
- Obtain approval of the schedule management plan from the steering committee and the regulator liaison.
- Establish the baseline schedule configuration policies for storage, retrieval, and change control.
ExplanationThe schedule approach must begin with a review of the enterprise environment and process assets so that the methodology and tool choices reflect real constraints. Once that context is understood, the methodology, tool, and granularity rules can be documented in the plan. Thresholds and approval authorities come next, since they depend on the documented method. Baseline configuration policies follow so that storage and change control align with the approvals, and the complete plan is approved last so that all its parts are reviewed together.
-
9 Question 9 Drag and drop Stakeholder Communications Management
A water utility is running a capital program with three distinct audiences: the board of directors, the regulator, and the field operations crews. The communication management plan requires each group to receive schedule information suited to its decisions. Match each stakeholder requirement to the schedule communication that best meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Field crews need to know which work packages are released for the coming two weeksRegulator requires evidence that the commissioning date is supported by a defensible critical pathBoard needs to decide whether to approve additional funding to protect the commissioning dateMonthly earned value summary for the program management office onlyOne-page milestone forecast with the funding-dependent scenarios and their decision pointsSchedule network extract with logic, float, and constraint documentationFull resource histogram across all programs for the financial yearFiltered look-ahead schedule showing released work packages and their predecessorsCorrect Answer:- Board needs to decide whether to approve additional funding to protect the commissioning date → One-page milestone forecast with the funding-dependent scenarios and their decision points
- Regulator requires evidence that the commissioning date is supported by a defensible critical path → Schedule network extract with logic, float, and constraint documentation
- Field crews need to know which work packages are released for the coming two weeks → Filtered look-ahead schedule showing released work packages and their predecessors
ExplanationThe board needs a concise milestone forecast that frames the funding decision, so the one-page scenario view is the fit. The regulator needs the underlying network with logic and constraints to judge defensibility, which an extract with float and constraint documentation supplies. Field crews act on near-term released work, which a filtered look-ahead schedule with predecessors delivers. The resource histogram and the PMO-only EVM summary do not serve any of these three stated decisions.
-
10 Question 10 Dropdown Schedule Monitoring and Controlling
A logistics firm is using its scheduling tool to run a what-if analysis on a warehouse fit-out project. The scheduler wants to test whether adding a second shift to the flooring activity, which is on the critical path, shortens the overall finish without changing the logic. The scenario must be run on a copy so that the approved baseline is untouched. Complete the procedure by selecting the correct value for each blank.
Choose the correct value for each blank.
Step 1: Create a copy of the current schedule using . Step 2: In the copy, change the flooring activity calendar to the two-shift calendar and recalculate using so that the effect on the finish date is reviewed without altering the baseline.Correct Answer:Step 1: Create a copy of the current schedule using Save As. Step 2: In the copy, change the flooring activity calendar to the two-shift calendar and recalculate using the scenario schedule so that the effect on the finish date is reviewed without altering the baseline.
ExplanationSaving the working schedule under a new file name creates an independent copy, so changes in the what-if run cannot touch the approved baseline. The recalculation must be performed on that scenario schedule, since recalculating the baseline or archive would alter controlled records. Baseline Save overwrites the baseline reference rather than producing a copy, and Rename Only and Export Template do not produce a working scenario file.
-
11 Question 11 Single choice Schedule Planning and Development
An energy company is estimating durations for a wind farm construction schedule. The foundation pour activity is unusual because the site is new and there is no historical data for this terrain, but the company has completed eight comparable foundations at other sites with recorded durations ranging from 14 to 26 working days. The estimator must produce a duration that accounts for uncertainty and is defensible to the investment committee. Which estimating approach BEST fits this situation?
Correct Answer: DExplanationThe company has analogous data with a meaningful range and terrain-specific uncertainty, so a three-point estimate built from the comparables and expert judgment captures both the spread and the most likely value. A single average hides the variability the committee needs to see. A parametric estimate requires a validated productivity rate for this terrain, which is not available here. Using the longest historical value is a padding approach that overstates the duration and misrepresents the most likely outcome.
These are 11 of the 326 questions in the full PMI-SP pack.
Get All 326 QuestionsGet all 326 questions & answers
Full access options for PMI PMI-SP
Self-study
PDF Version
- 326 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 326 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 326 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PMI-SP Exam (PMI Scheduling Professional) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.