- 326 Actual Exam Questions
- Compatible with all Devices
- Printable Format
- No Download Limits
- 90 Days Free Updates
Get All PMI Scheduling Professional Exam Questions with Validated Answers
Vendor: | PMI |
---|---|
Exam Code: | PMI-SP |
Exam Name: | PMI Scheduling Professional |
Exam Questions: | 326 |
Last Updated: | October 6, 2025 |
Related Certifications: | PMI Scheduling Professional |
Exam Tags: | Project Management Intermediate Level Operations Management SpecialistProgram Management ExpertProgram Project Manager |
Looking for a hassle-free way to pass the PMI Scheduling Professional exam? DumpsProvider provides the most reliable Dumps Questions and Answers, designed by PMI certified experts to help you succeed in record time. Available in both PDF and Online Practice Test formats, our study materials cover every major exam topic, making it possible for you to pass potentially within just one day!
DumpsProvider is a leading provider of high-quality exam dumps, trusted by professionals worldwide. Our PMI-SP exam questions give you the knowledge and confidence needed to succeed on the first attempt.
Train with our PMI-SP exam practice tests, which simulate the actual exam environment. This real-test experience helps you get familiar with the format and timing of the exam, ensuring you're 100% prepared for exam day.
Your success is our commitment! That's why DumpsProvider offers a 100% money-back guarantee. If you don’t pass the PMI-SP exam, we’ll refund your payment within 24 hours no questions asked.
Don’t waste time with unreliable exam prep resources. Get started with DumpsProvider’s PMI-SP exam dumps today and achieve your certification effortlessly!
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 100 percent done by this date. She has spent $490,000 to date and other than the project schedule, which was delayed because of a vendor, the project is going well. What should Billy report as her schedule performance index for this project?
Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula: SPI = Earned Value (EV) / Planned Value (PV)
If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value
is less than 1, it shows poor
performance. The SPI value of 1 indicates that the project is right on target. You can find the planned
value by multiplying where Billy should
be in the project, 100 percent, by the project's budget. In this instance the planned value is $655,000
because she is to be 100 percent
complete.
Answer option B is incorrect. The SPI simply reports a value not an explanation.
Answer option A is incorrect. 1.23 is the cost performance index for the project.
Answer option D is incorrect. $524,000 is the earned value for the project.
The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?
Noise is anything that disrupts the communication method such as static on the telephone line, distracting conversations, or misunderstandings. Answer option A is incorrect. Static is an example of noise, but it is not part of the communication model. Answer option D is incorrect. A barrier to communication is when communication cannot happen under the present conditions. Answer option B is incorrect. A deterrent is not a valid part of the communication model.
George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule. What value should George report in this instance?
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. The earned value in this instance is forty percent of the project budget, $778,000, and the planned value is $398,000 because George is to be fifty percent done at the end of the second quarter, as the work is spread evenly across all quarters. The schedule variance is -$77,800 for the project. Answer option A is incorrect. .96 represents the cost performance index. Answer option C is incorrect. -$34,500 represents the project's variance at completion if the project continues as is. Answer option D is incorrect. -$13,800 is the cost variance for the project.
You work as the project manager for BlueWell Inc. You are recording the activity status for your project team's performance in the project. Based on the current performance your project is likely to be three months late. What type of communication should be generated based on this performance issue?
A performance report is needed to communicate the variance between planned work and actual
work.
A performance report is made by the project team detailing activities, milestones, problems,
accomplishments, and identified issues.
Performance reports are used to report some key information as follows:
Current status
Scheduled activities
Significant accomplishment for the period
Forecasts
Issues
Answer option A is incorrect. An issue report is not the best answer for this scenario. Issues are
recorded in the issue log and an issue owner
is assigned.
Answer option B is incorrect. An exceptions report is a tempting answer as this is an exception to the
project. PMI does not use this
terminology.
Answer option C is incorrect. Variance analysis is the activity of reviewing the variance to determine
why it exists.
In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved?
The various techniques of group decision making are as follows:
Unanimity: In this technique, everyone agrees on a single course of action.
Majority: In this technique, more than 50% of the members of the group support the decisions.
Plurality: In this technique, the largest block in a group decides even if a bulk is not achieved.
Dictatorship: In this technique, one individual makes the decision for the group.
Security & Privacy
Satisfied Customers
Committed Service
Money Back Guranteed