- 326 Actual Exam Questions
- Compatible with all Devices
- Printable Format
- No Download Limits
- 90 Days Free Updates
Get All PMI Scheduling Professional Exam Questions with Validated Answers
| Vendor: | PMI |
|---|---|
| Exam Code: | PMI-SP |
| Exam Name: | PMI Scheduling Professional |
| Exam Questions: | 326 |
| Last Updated: | January 10, 2026 |
| Related Certifications: | PMI Scheduling Professional |
| Exam Tags: | Project Management Intermediate Level Operations Management SpecialistProgram Management ExpertProgram Project Manager |
Looking for a hassle-free way to pass the PMI Scheduling Professional exam? DumpsProvider provides the most reliable Dumps Questions and Answers, designed by PMI certified experts to help you succeed in record time. Available in both PDF and Online Practice Test formats, our study materials cover every major exam topic, making it possible for you to pass potentially within just one day!
DumpsProvider is a leading provider of high-quality exam dumps, trusted by professionals worldwide. Our PMI-SP exam questions give you the knowledge and confidence needed to succeed on the first attempt.
Train with our PMI-SP exam practice tests, which simulate the actual exam environment. This real-test experience helps you get familiar with the format and timing of the exam, ensuring you're 100% prepared for exam day.
Your success is our commitment! That's why DumpsProvider offers a 100% money-back guarantee. If you don’t pass the PMI-SP exam, we’ll refund your payment within 24 hours no questions asked.
Don’t waste time with unreliable exam prep resources. Get started with DumpsProvider’s PMI-SP exam dumps today and achieve your certification effortlessly!
Which of the following is NOT an output of the control schedule process?
The project termination request is not an output of the control schedule. Early
termination of a project is a closing process and usually does
not stem from the project manager.
The outputs of the control schedule process are as follows:
Work Performance Measurements: The work packages and control accounts are documented and
communicated to the stakeholders.
Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen
and the reasons, causes of
variance, and other types of lessons learned from project schedule control.
Change Requests: It is processed for reviews and disposition through the Perform Integrated Change
Control process.
Project Management Plan Updates: The elements that need to be updated are: schedule baseline,
schedule management plan, cost
baseline.
Project Document Updates: The elements that need to be updated in project document updates are:
schedule data and project
schedule.
You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?
The project staffing management plan will define how resources are brought onto the project team,
how they are managed while on the project team, and how they may be released from the project
team.
The staffing management plan is part of human resources plan. It is a subsidiary plan of the overall
project management plan and defines
when project team members will be brought onto and released from the project. It describes when
and how human resource requirements
will be met. Depending upon the needs of the project, it can be formal or informal, highly detailed or
broadly framed. The staffing management
plan may include the following items: Staff acquisition, resource calendars, staff release plan,
training needs, recognition and rewards,
compliance, and safety.
Answer option D is incorrect. The communications management plan defines project communication
requirements and expectations.
Answer option C is incorrect. This is not a valid project management plan.
Answer option A is incorrect. The project schedule management will define when resources are
needed and scheduled. But it will not define how resources are allowed to be released from the
project.
Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?
Because this project needs the specific resource of Henry, the application developer, and Henry is not available, it is considered as a resource constraint. Recall that a constraint is anything that limits the project manager's option. Answer option C is incorrect. A resource requirement is simply the need for an application developer. Answer option B is incorrect. This is likely a matrix organization, but it is not the best answer for this question. Answer option A is incorrect. While there may be some competition for skilled resources, such as
Henry, the application developer, it is not the
best answer for this question.
Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?
This is an example of corrective action. The project team will fix the mistake and they
have learned from their mistake so it won't happen again.
Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce
the probability and impact of an identified
risk event.
Answer option A is incorrect. A risk response is an action to counteract an identified risk.
Answer option B is incorrect. There may be some team development happening in this instance but
we don't have enough information to know
for certain. Team development is an activity that brings the whole team cohesion, interdependency,
and trust.
with an appropriate phrase.
The _______contains the schedule components and the rules for relating and using the components
to represent the process for completing a project.
A scheduling tool consists of the schedule components and the rules for connecting and using the
components to characterize
the process for completing a project. It is used to gather the schedule model and provide the means
of adjusting various parameters and
components that are typical in a modeling process.
Security & Privacy
Satisfied Customers
Committed Service
Money Back Guranteed