2026 Actual PMI PMI-RMP Dumps, Updated Exam Questions for Guaranteed Pass

PMI Risk Management Professional - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorPMI
Exam codePMI-RMP
Exam namePMI Risk Management Professional
Questions in pack289
Last updatedNovember 21, 2026
Related certificationsProject Management Professional

Free practice questions with explanations

PMI PMI-RMP Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
12
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Monitor and Close Risks

    A pharmaceutical packaging project uses earned value reporting against a baseline approved last quarter. The risk-relevant work packages for a new labelling line show a cost performance index of 0.82 and a schedule performance index of 0.95. The sponsor asks the risk manager to determine whether the residual risk exposure to the enterprise portfolio has changed. The portfolio dashboard only accepts risk exposure restated in the enterprise risk tolerance units, and the regulatory team requires that any closure of a risk be backed by reconciled data. Which action should the risk manager take FIRST?

  2. 2 Question 2 Single choice Risk Analysis

    An aerospace component team is performing qualitative risk analysis on 40 identified risks. The risk management plan defines probability on a five-point scale and impact on schedule, cost and technical performance, with a 5x5 matrix that scores each risk. Three technical risks score identically at 12, but one would delay a flight-certification milestone that carries a contractual penalty, while the others affect internal test schedules only. The project manager wants a prioritised list that the steering committee can act on without rescoring. Which approach BEST meets this need?

  3. 3 Question 3 Single choice Risk Identification

    A logistics company is implementing a warehouse automation project in three countries. During assumption analysis, the team records that the regional customs authority will publish its new electronic declaration rules before the system go-live date. The project schedule has no float after the go-live milestone, and the vendor contract states that any delay in customs rule publication triggers a penalty only if the regulatory change is formally notified. Two interviews with customs officials suggest the notice may come late. Which action BEST addresses this assumption?

  4. 4 Question 4 Single choice Risk Response

    A telecom operator is rolling out a 5G core upgrade. Quantitative analysis shows a 35 percent probability that a vendor firmware defect will force a rollback in a regional data centre, costing an estimated 1.2 million dollars. The operator has a fixed cutover window and cannot extend the outage budget. Options under consideration include buying an additional standby appliance for 400,000 dollars that cuts rollback time from 36 hours to 8 hours, or accepting the risk and funding a contingency reserve. Leadership asks for the option whose effectiveness is shown against the project objectives. Which response plan BEST meets the stated constraints?

  5. 5 Question 5 Single choice Risk Strategy and Planning

    A government digital services agency is starting a citizen portal project. The organisation has recently moved to a hybrid delivery model, with fixed-scope regulatory deliverables run in waterfall and feature work run in agile sprints. Before risk identification, the risk manager must assess the project environment. Historical lessons learned from a previous portal project show frequent late scope changes, and the enterprise risk culture is described by auditors as risk-averse with limited tolerance for schedule slippage. Which activity should the risk manager perform FIRST to determine how the risk process should be tailored?

  6. 6 Question 6 Multiple choice Monitor and Close Risks

    A rail signalling upgrade project has completed 60 percent of its work packages. The risk manager finds that two work packages linked to a high-impact interface risk are showing actual costs that do not match the timesheet and supplier invoice records, and a residual risk from a previous mitigation has not been re-evaluated since a design change. The steering group wants the risk register updated, and the regulator requires traceable closure records. (Choose two.)

  7. 7 Question 7 Single choice Risk Analysis

    A hospital IT programme is running a sensitivity analysis on a clinical records migration. Its schedule model has five risks feeding a critical path, and the programme must decide which risk to mitigate first with limited funds. Results show that risk B has a wide range in duration impact but a low correlation with total finish date, while risk D has a narrower range and drives most of the variance in finish date. The programme manager wants the analysis to guide funding rather than just rank probability. Which conclusion is BEST supported by the sensitivity analysis?

  8. 8 Question 8 Single choice Risk Identification

    An energy company is preparing a risk identification workshop for a new offshore wind farm. Documents include meeting transcripts, telemetry from a pilot turbine, and vendor proposals. The facilitator wants to identify risks that are both threats and opportunities and to understand the business context behind statements that seem contradictory. A senior engineer says the pilot telemetry shows lower vibration than expected, which the commercial lead calls a sign of schedule savings. Which action BEST supports accurate identification?

  9. 9 Question 9 Multiple choice Risk Response

    A construction firm building a hospital wing faces a risk that a key steel supplier may fail to deliver within the critical path window. The procurement team has a secondary supplier that charges a premium and requires a 10-day qualification period, and the contract allows a partial delivery penalty clause. The project has a fixed completion date and limited budget for response actions. (Choose two.)

  10. 10 Question 10 Single choice Risk Response

    A software company is running a product launch with a risk that a third-party payment library will not pass a security audit before release. The release date is fixed by a marketing commitment, and the security team says a full audit takes six weeks. The team considers replacing the library with an in-house module that could be built in four weeks but would carry its own unknown defects. Which response strategy BEST fits the stated risk and constraints?

  11. 11 Question 11 Multiple choice Risk Strategy and Planning

    A regional bank is planning a core banking replacement under a hybrid delivery approach. Before identification, the risk manager reviews project environment factors and must set up the risk process. The bank's enterprise risk committee has a low appetite for regulatory breaches, moderate appetite for cost overrun, and high appetite for technology experimentation. Previous projects had poor risk data quality because no common scale was used across delivery teams. (Choose three.)

  12. 12 Question 12 Single choice Monitor and Close Risks

    A mining company's extraction project tracks risk exposure against an enterprise-level risk threshold. Over six months, three project-level risks were closed as expired, but a secondary risk arising from a mitigation has been reported to have a rising probability in two monthly reports. The programme office wants to update the risk register, the lessons learned log and the change log consistently after closure decisions. Which action should the project team take to meet this governance need?

These are 12 of the 289 questions in the full PMI-RMP pack.

Get All 289 Questions

Get all 289 questions & answers

711 Satisfied customers
94.8% Pass rate feedback
82.2% Said questions matched
93% Found material helpful

Full access options for PMI PMI-RMP

Self-study

PDF Version

$40.00 $20.00
  • 289 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 289 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PMI-RMP Exam (PMI Risk Management Professional) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed