Exam Information
Free practice questions with explanations
PMI PMI-RMP Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Monitor and Close Risks
A pharmaceutical packaging project uses earned value reporting against a baseline approved last quarter. The risk-relevant work packages for a new labelling line show a cost performance index of 0.82 and a schedule performance index of 0.95. The sponsor asks the risk manager to determine whether the residual risk exposure to the enterprise portfolio has changed. The portfolio dashboard only accepts risk exposure restated in the enterprise risk tolerance units, and the regulatory team requires that any closure of a risk be backed by reconciled data. Which action should the risk manager take FIRST?
Correct Answer: BExplanationReconciling performance data and reports from the risk-relevant work packages comes before any variance or exposure analysis, because the regulatory requirement makes closure decisions dependent on reconciled data. Closing risks on a tolerance band skips the reconciliation the closure must rest on. Recalculating reserves assumes the data is already valid, and escalating for a change request is premature when the variance has not yet been explained against the baseline.
-
2 Question 2 Single choice Risk Analysis
An aerospace component team is performing qualitative risk analysis on 40 identified risks. The risk management plan defines probability on a five-point scale and impact on schedule, cost and technical performance, with a 5x5 matrix that scores each risk. Three technical risks score identically at 12, but one would delay a flight-certification milestone that carries a contractual penalty, while the others affect internal test schedules only. The project manager wants a prioritised list that the steering committee can act on without rescoring. Which approach BEST meets this need?
Correct Answer: CExplanationThe risk management plan's matrix produces a score, but prioritisation in qualitative analysis also considers urgency, so a secondary urgency rating separates risks that tie on score yet differ in how soon and how seriously the contract penalty bites. Nominal category grouping does not rank risks, switching to expected monetary value is quantitative work the stem does not call for, and leaving the order to the committee fails the request for a usable prioritised list.
-
3 Question 3 Single choice Risk Identification
A logistics company is implementing a warehouse automation project in three countries. During assumption analysis, the team records that the regional customs authority will publish its new electronic declaration rules before the system go-live date. The project schedule has no float after the go-live milestone, and the vendor contract states that any delay in customs rule publication triggers a penalty only if the regulatory change is formally notified. Two interviews with customs officials suggest the notice may come late. Which action BEST addresses this assumption?
Correct Answer: CExplanationAssumptions with schedule dependencies should be assessed for risk and given triggers and thresholds, and here the contract makes formal notification the measurable event. Defining a trigger tied to missing notice by a date, with an owner, gives the team an actionable signal. Dropping the assumption ignores the interview evidence, a blanket buffer on all milestones is an untargeted response, and calling a late notice an opportunity misreads the threat, since the exposure is delay.
-
4 Question 4 Single choice Risk Response
A telecom operator is rolling out a 5G core upgrade. Quantitative analysis shows a 35 percent probability that a vendor firmware defect will force a rollback in a regional data centre, costing an estimated 1.2 million dollars. The operator has a fixed cutover window and cannot extend the outage budget. Options under consideration include buying an additional standby appliance for 400,000 dollars that cuts rollback time from 36 hours to 8 hours, or accepting the risk and funding a contingency reserve. Leadership asks for the option whose effectiveness is shown against the project objectives. Which response plan BEST meets the stated constraints?
Correct Answer: DExplanationThe standby appliance reduces both probability-weighted impact and rollback duration, and a risk burndown chart or similar visual lets leadership compare residual exposure against the fixed cutover window. The stem states the outage budget is fixed but does not say the appliance cost is unaffordable, so accepting the risk would leave the outage exposure unchanged. Insurance does not shorten the outage, and postponing the upgrade ignores the purpose of the project.
-
5 Question 5 Single choice Risk Strategy and Planning
A government digital services agency is starting a citizen portal project. The organisation has recently moved to a hybrid delivery model, with fixed-scope regulatory deliverables run in waterfall and feature work run in agile sprints. Before risk identification, the risk manager must assess the project environment. Historical lessons learned from a previous portal project show frequent late scope changes, and the enterprise risk culture is described by auditors as risk-averse with limited tolerance for schedule slippage. Which activity should the risk manager perform FIRST to determine how the risk process should be tailored?
Correct Answer: CExplanationEnvironmental assessment in planning determines which methodology and organisational process assets apply and how much risk the organisation will accept, and that shapes the tailored risk process before identification begins. Simulation requires a risk model that does not yet exist, assigning owners for every deliverable is premature without identified risks, and interviews for identification skip the environment assessment the stem signals is needed.
-
6 Question 6 Multiple choice Monitor and Close Risks
A rail signalling upgrade project has completed 60 percent of its work packages. The risk manager finds that two work packages linked to a high-impact interface risk are showing actual costs that do not match the timesheet and supplier invoice records, and a residual risk from a previous mitigation has not been re-evaluated since a design change. The steering group wants the risk register updated, and the regulator requires traceable closure records. (Choose two.)
Correct Answer: B, CExplanationPerformance data must be reconciled across sources before conclusions are drawn, and residual risks must be re-evaluated when the project changes so their impact on objectives is current and traceable. Closing on a green status ignores the reconciliation gap, deleting the residual risk loses traceability, and substituting a reserve without impact assessment does not satisfy the regulator's requirement.
-
7 Question 7 Single choice Risk Analysis
A hospital IT programme is running a sensitivity analysis on a clinical records migration. Its schedule model has five risks feeding a critical path, and the programme must decide which risk to mitigate first with limited funds. Results show that risk B has a wide range in duration impact but a low correlation with total finish date, while risk D has a narrower range and drives most of the variance in finish date. The programme manager wants the analysis to guide funding rather than just rank probability. Which conclusion is BEST supported by the sensitivity analysis?
Correct Answer: DExplanationSensitivity analysis shows which inputs most influence the outcome, and here risk D explains most of the finish-date variance, so it deserves funding priority despite its narrower range. Widest range without correlation to finish date misleads the funding decision. Equal funding ignores the differentiation the analysis provides, and waiting for qualitative ratings abandons the quantitative evidence already available.
-
8 Question 8 Single choice Risk Identification
An energy company is preparing a risk identification workshop for a new offshore wind farm. Documents include meeting transcripts, telemetry from a pilot turbine, and vendor proposals. The facilitator wants to identify risks that are both threats and opportunities and to understand the business context behind statements that seem contradictory. A senior engineer says the pilot telemetry shows lower vibration than expected, which the commercial lead calls a sign of schedule savings. Which action BEST supports accurate identification?
Correct Answer: DExplanationIdentification should analyse documents and telemetry in their business context and indicate risks as threats or opportunities, so the lower vibration can carry both a possible reliability concern and a schedule benefit that the team must examine. Discarding the data or adopting one interpretation loses information, and asking the vendor to restate proposals does not address the analysis of the pilot evidence.
-
9 Question 9 Multiple choice Risk Response
A construction firm building a hospital wing faces a risk that a key steel supplier may fail to deliver within the critical path window. The procurement team has a secondary supplier that charges a premium and requires a 10-day qualification period, and the contract allows a partial delivery penalty clause. The project has a fixed completion date and limited budget for response actions. (Choose two.)
Correct Answer: C, EExplanationPre-qualifying a contingency supplier gives the response time to take effect within the 10-day qualification constraint, and assigning owners and dated actions with effectiveness measured against the completion date is required for time-bound response planning. Removing the risk on past performance ignores the exposure, delaying qualification until failure would breach the critical window, and switching all supply without capacity checks is unsupported.
-
10 Question 10 Single choice Risk Response
A software company is running a product launch with a risk that a third-party payment library will not pass a security audit before release. The release date is fixed by a marketing commitment, and the security team says a full audit takes six weeks. The team considers replacing the library with an in-house module that could be built in four weeks but would carry its own unknown defects. Which response strategy BEST fits the stated risk and constraints?
Correct Answer: DExplanationA mitigation that starts the audit now and prepares a time-bound fallback, with a defined decision point, addresses both the audit timeline and the fixed launch date. Enhancing with a second provider does not reduce the audit risk, accepting it without contingency exposes the company to a compliance failure, and cancelling the launch avoids the objective rather than managing the risk.
-
11 Question 11 Multiple choice Risk Strategy and Planning
A regional bank is planning a core banking replacement under a hybrid delivery approach. Before identification, the risk manager reviews project environment factors and must set up the risk process. The bank's enterprise risk committee has a low appetite for regulatory breaches, moderate appetite for cost overrun, and high appetite for technology experimentation. Previous projects had poor risk data quality because no common scale was used across delivery teams. (Choose three.)
Correct Answer: B, C, EExplanationScales and matrices calibrated to the stated appetites, a shared categorisation that fixes the earlier data-quality problem, and a documented environmental analysis all belong to the planning step. Setting identical tolerance for breach and experimentation contradicts the stated appetites, and letting each team define scales would repeat the inconsistency the stem describes.
-
12 Question 12 Single choice Monitor and Close Risks
A mining company's extraction project tracks risk exposure against an enterprise-level risk threshold. Over six months, three project-level risks were closed as expired, but a secondary risk arising from a mitigation has been reported to have a rising probability in two monthly reports. The programme office wants to update the risk register, the lessons learned log and the change log consistently after closure decisions. Which action should the project team take to meet this governance need?
Correct Answer: BExplanationClosing expired risks with evidence, keeping the secondary risk open while its probability is rising, and updating the lessons learned and change logs together keeps the project documents consistent and traceable. Waiting for project closure to update logs delays knowledge capture, deleting closed risks loses audit history, and closing a risk whose probability is rising ignores the monitoring evidence.
These are 12 of the 289 questions in the full PMI-RMP pack.
Get All 289 QuestionsGet all 289 questions & answers
Full access options for PMI PMI-RMP
Self-study
PDF Version
- 289 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 289 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 289 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PMI-RMP Exam (PMI Risk Management Professional) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.