Exam Information
Free practice questions with explanations
PMI PMP Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 11
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Business Environment
A regional logistics company is running a predictive project to replace its warehouse management system. The steering committee has asked the project manager to define success metrics before the design phase begins. The sponsor wants to be able to judge the project's benefits within six months of go-live, not just at project closure, and the finance office requires that any metric be measurable from existing operational data without building new reporting tools. The project manager has drafted four candidate metrics. Which metric should be adopted as the primary success measure?
Correct Answer: DExplanationSuccess metrics should link to the benefits the project is meant to realise and be measurable within the stated window using existing data. A baseline-referenced reduction in picking errors can be tracked from current warehouse logs within six months of go-live, which satisfies both the sponsor and finance constraints. Schedule and budget adherence measure project delivery rather than benefit realisation, so they cannot show value at six months. Satisfaction surveys require new data collection that the finance office has ruled out. Change request counts reflect control activity, not outcomes.
-
2 Question 2 Single choice Business Environment
A healthcare software project is delivering a patient scheduling module that will store personal health information. During an audit-readiness review, the compliance lead discovers that the test environment has been populated with copies of live patient records, and the privacy regulation applicable to the project prohibits such use outside production. The project is 70 percent complete and the release is due in three weeks. The project manager must determine the appropriate response. What should the project manager do first?
Correct Answer: BExplanationThe first step in compliance management is to understand the consequences of the noncompliance and bring it to the governance body, which holds the escalation thresholds for issues of this severity. Only after that analysis can an approach such as masking or rebuilding be selected and authorised. Masking the data immediately skips the analysis and escalation. Seeking a regulator waiver is not a project manager decision and would not be granted quickly enough. Deleting and rebuilding the environment is a remediation action taken before the impact is understood.
-
3 Question 3 Single choice Business Environment
A construction firm is delivering a hybrid project to build a regional data center. The change control board has a rule that any change increasing the project budget by more than 5 percent, or delaying a milestone by more than 10 working days, must be escalated to the executive steering group. A subcontractor reports that a supplier price increase will add 4 percent to the cost of electrical materials and a cooling-system redesign will delay the commissioning milestone by 12 working days. Each change is individually below the escalation threshold, but the project manager notes that the combined effect of both changes exceeds the cost threshold. What is the most appropriate action for the project manager?
Correct Answer: DExplanationThe governance rules set escalation thresholds, and the project manager must recognise when cumulative effects breach them. The schedule delay alone exceeds the 10-day threshold, so it requires escalation regardless of cost, and the combined cost effect also needs assessing against the 5 percent limit. Approving at project level ignores the delay breach. Waiting for a monthly meeting breaks the escalation path timing. Splitting the change to avoid thresholds is a deliberate attempt to circumvent governance and would be a serious ethics breach.
-
4 Question 4 Single choice People
A product development team of twelve people has been working on a mobile banking feature for four months. The sponsor and the product owner have each described the target outcome differently in recent meetings. The sponsor talks about reducing call-center volume, while the product owner talks about increasing the number of active app users. Team members are building features that serve each interpretation, and the sprint reviews have become tense. The project manager needs to restore a common vision. What should the project manager do first?
Correct Answer: BExplanationA shared vision requires the key stakeholders to align, and the root cause here is two stakeholders holding different assumptions about the purpose of the project. Bringing them together to examine those assumptions and agree on one outcome addresses the source of the misunderstanding. Editing the backlog unilaterally would not resolve the stakeholder disagreement. A vision statement imposed on the team without stakeholder agreement would not be a shared vision. Deferring the issue lets the divergent interpretations keep producing conflicting work.
-
5 Question 5 Single choice People
In a hybrid software project, two senior engineers disagree about whether the API should be versioned in the URL or in request headers. The disagreement has escalated into personal comments in the team chat, and a third developer has stopped attending design discussions. The team agreed a ground rule two weeks ago that technical disagreements must be resolved in the design review using written trade-off summaries. One engineer has ignored this rule and posted a sarcastic message to the wider channel. The project manager is considering how to proceed. What is the most appropriate response?
Correct Answer: DExplanationGround rule violations should be managed and rectified directly, and the agreed resolution strategy here is the design review with written trade-offs. A private conversation addresses the violation respectfully while reinforcing the agreed process, and facilitating the structured review gives the conflict a legitimate path to resolution. Public reminders to the whole team can embarrass the individual and do not correct the behaviour. Handing the decision to the architecture lead bypasses the agreed process. Removing an engineer from discussions punishes the conflict rather than resolving it.
-
6 Question 6 Single choice People
A project manager has just taken over a predictive infrastructure project from a colleague who was reassigned. The project team of eight includes two contractors whose contracts end in six weeks, and one member who has recently requested reduced hours due to caregiving responsibilities. The team is behind schedule and morale is low. Upper management wants a recovery plan within ten working days. Which leadership action best helps the project manager establish expectations and empower the team at this point?
Correct Answer: BExplanationEstablishing expectations and empowering a team that is struggling starts with understanding each person's capacity, skills, and constraints, including the contractors' end dates and the reduced-hours arrangement. Facilitating a session to agree on roles and decision rights then gives the team ownership of the recovery plan. A directive style would remove the empowerment the team needs. A written list from the original plan ignores the changed circumstances and the new project manager's need to understand the team. Appointing a lead shifts responsibility away from the project manager without addressing expectations.
-
7 Question 7 Single choice Process
A financial services firm is initiating a project to modernise its customer onboarding process. The requirements are poorly understood, regulators may change rules during the project, and the sponsor expects frequent demonstrations of working functionality. The organisation has a strict policy requiring fixed-price contracts for all external vendors, and the board needs an approved budget envelope before the next funding cycle. The project manager must recommend a development approach. Which recommendation best fits these conditions?
Correct Answer: DExplanationThe situation combines a need for an approved budget envelope and fixed-price vendor contracts with uncertain requirements and frequent demonstration needs. A hybrid approach keeps governance anchors such as the budget envelope and compliance milestones while using iterative delivery for the uncertain feature work. A full predictive baseline is unrealistic given changing regulation and poor requirements understanding. A purely adaptive approach without a budget envelope conflicts with the board's funding cycle. Time-and-materials contracts conflict with the firm's fixed-price policy.
-
8 Question 8 Single choice Process
A project manager is maintaining an integrated project management plan for a three-year hospital expansion. Six months in, the schedule baseline shows that the structural steel delivery depends on a permit that the planning department has not yet issued, while the electrical subcontractor has been scheduled to start work before the structural frame is complete. The plan has been updated for each change, but no one has reviewed the consolidated plan for dependency conflicts since the baseline was first approved. The sponsor asks for assurance that the plan remains viable. What should the project manager do next?
Correct Answer: BExplanationMaintaining the integrated plan includes assessing the consolidated plans for dependencies, gaps, and continued business value, which has not been done since the baseline. Reassessing the consolidated plan surfaces the permit and sequencing conflicts and allows the schedule and resource assumptions to be corrected. Approving each change individually does not guarantee the whole plan is coherent. Requesting a new plan from another department and suspending subcontractors is a reactive delay without analysing the existing plan. Reducing scope is a drastic response to a scheduling conflict that can be addressed through re-sequencing.
-
9 Question 9 Single choice Process
A company is delivering a customer relationship management upgrade. The project has a scope statement and a work breakdown structure, but the sponsor has been asked to accept deliverables that are described only at the level of 'reporting module' and 'data migration'. Stakeholders from sales and finance hold different expectations of what the reporting module must include, and the data migration work package has no defined acceptance criteria. The project manager is preparing the scope definition for formal approval. Which action best supports obtaining stakeholder agreement on the project scope?
Correct Answer: BExplanationObtaining stakeholder agreement on scope requires that deliverables be broken down enough to show what is included and what the acceptance criteria are, and that the relevant stakeholders review them before baseline approval. Decomposing the two named deliverables with acceptance criteria and reviewing them with sales, finance, and the sponsor addresses the conflicting expectations directly. Deferring the question to user acceptance testing invites rework. Excluding sales input creates a new stakeholder dispute. Expanding to activity level adds detail on effort but does not resolve what the deliverables must do.
-
10 Question 10 Multiple choice Process
A project team is delivering a regulatory reporting system for a utility company. The sponsor wants a value-based delivery approach so that early releases generate benefits. Stakeholders disagree on which features deliver the most value, and the compliance deadline is fixed. Which TWO actions best help the project manager help ensure value-based delivery? (Choose two.)
Correct Answer: B, EExplanationValue-based delivery starts with identifying value components with key stakeholders and using them to sequence delivery, so that high-value features arrive earliest. Linking value components to release planning also ensures the fixed compliance requirements are met in the right releases. Delaying value discussions removes the ability to prioritise early. Counting features ignores whether they deliver value. Ranking by implementation effort alone ignores stakeholder-defined benefits.
-
11 Question 11 Multiple choice Business Environment
A public-sector agency is implementing a case-management system that must comply with data protection legislation, accessibility standards, and the agency's information security policy. The project is governed by a board that has set an escalation threshold: any unresolved compliance issue expected to exceed two weeks must be escalated. During a readiness review, the project manager identifies several compliance concerns. Which TWO actions best support managing compliance on this project? (Choose two.)
Correct Answer: B, EExplanationCompliance management begins by classifying requirements into categories and assigning ownership, which makes threats and responsibilities visible. Measuring the extent of compliance with verification evidence and reporting it to the board gives governance the information it needs to apply escalation thresholds. Treating accessibility as optional ignores a stated requirement. Deferring security to closure leaves risks unaddressed throughout delivery. Hiding gaps below the threshold from the board undermines governance, because the threshold applies to expected duration and the board must still have visibility.
These are 11 of the 187 questions in the full PMP pack.
Get All 187 QuestionsGet all 187 questions & answers
Full access options for PMI PMP
Self-study
PDF Version
- 187 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 187 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 187 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PMP Exam (Project Management Professional (PMBOK 7th Version)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.