2026 Actual PMI CAPM Dumps, Updated Exam Questions for Guaranteed Pass

Certified Associate in Project Management - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorPMI
Exam codeCAPM
Exam nameCertified Associate in Project Management
Questions in pack1320
Last updatedNovember 21, 2026
Related certificationsCertified Associate in Project Management

Free practice questions with explanations

PMI CAPM Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
13
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Project Management Fundamentals and Core Concepts

    A project coordinator at a regional logistics company is reviewing a request from a sales director. The director wants the team to start a new customer onboarding portal that will be delivered in six months, after which it will be handed to the operations group to run indefinitely as a service. Midway through the discussion, the sales director asks whether the portal is a project or an operation. The coordinator must answer accurately and recommend how the work should be governed. The company has a temporary funding window, a defined end date for the build, and an expectation that the output will be maintained by a separate group afterward.
    Which statement BEST characterises the initiative and its governance?

  2. 2 Question 2 Single choice Business Analysis Frameworks

    A business analyst is preparing requirements for a claims-processing system at an insurance firm. Adjusters are geographically dispersed across three time zones and are not available for a full-day workshop. The product owner has asked for detailed functional requirements within two weeks, and the analyst has noticed that the adjusters disagree on several approval rules. The analyst must choose an elicitation approach that surfaces the conflicting rules early and keeps adjusters engaged without pulling them off casework for long periods.
    Which approach is MOST appropriate as the next step?

  3. 3 Question 3 Single choice Predictive, Plan-Based Methodologies

    A project manager is planning a warehouse relocation. The schedule has the following activities with durations in days: Site survey 3, Racking design 5, Racking installation 8, Inventory move 4, and Systems cutover 2. Dependencies are: Racking design follows Site survey; Racking installation follows Racking design; Inventory move follows Racking installation; Systems cutover follows Inventory move. Separately, Systems cutover depends on a vendor license that is not expected until day 14, and the project manager also has a parallel activity called Staff training of 6 days that can start after Site survey and must finish before Inventory move.
    What is the duration of the critical path, and which sequence is critical?

  4. 4 Question 4 Single choice Agile Frameworks/Methodologies

    A product team at a software firm uses a predictive plan for a regulated banking module. Management is now asking whether to adopt an adaptive approach for the next enhancement, a mobile budgeting feature whose requirements the customers have described as uncertain. The team is colocated in one office, has an experienced product owner available full-time, and the firm's compliance function requires an auditable record of approved scope changes. The sponsor wants the team to learn from early customer feedback before committing to the full feature set.
    Which action BEST supports an adaptive approach while satisfying the compliance requirement?

  5. 5 Question 5 Single choice Project Management Fundamentals and Core Concepts

    During the planning of a hospital IT upgrade, the project manager lists several items. The vendor has said it may not deliver a required interface module until the second quarter, which the team has noted as a possible delay. The hospital's chief executive has mandated that the system must be live before the next accreditation audit, a fixed date that cannot move. A nurse informatics lead has raised the concern that the current clinical workflow is not documented, which may cause rework. The team has also recorded that the upgrade will assume the existing network hardware is sufficient, but this has not yet been verified.
    Which classification of these items is MOST accurate?

  6. 6 Question 6 Multiple choice Predictive, Plan-Based Methodologies

    A project manager at a construction firm is calculating performance on a bridge-repair project at the end of week 10. The planned value to date is 180,000 currency units, the earned value is 150,000, and the actual cost incurred is 165,000. The schedule has the project behind plan, and the project manager needs to report schedule and cost performance to the sponsor. (Choose two.)

  7. 7 Question 7 Single choice Project Management Fundamentals and Core Concepts

    A project manager is building the risk register for a software migration and must place each entry in the correct register field. The entries are:
    1. The data migration tool may not support the legacy file encoding.
    2. The steering committee has directed that go-live must occur before the fiscal year ends.
    3. The team assumes the legacy vendor will remain available for support questions during cutover.
    The targets are: Risk description, Constraint, Assumption.
    Which mapping is correct?

  8. 8 Question 8 Single choice Agile Frameworks/Methodologies

    A product owner at a telecommunications company is preparing the first iteration for a customer billing redesign. The team has a backlog of forty-two items, many of which are poorly understood. The product owner wants to release a usable increment at the end of each iteration. The Scrum master notes that the organisation's leadership expects predictable monthly reporting, and the development group is split across two sites in different time zones with limited overlap.
    Which planning decision BEST balances these conditions?

  9. 9 Question 9 Order list Predictive, Plan-Based Methodologies

    A project manager at a manufacturing plant is developing the work breakdown structure for a new production line. The following steps have been listed in no particular order: Drag the steps into the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Identify the major deliverables from the approved scope statement.
    2. Decompose each deliverable into work packages small enough to estimate and assign.
    3. Assign a unique identifier to each WBS element and build the dictionary entries.
    4. Confirm the scope statement and gather stakeholder agreement on the included deliverables.
  10. 10 Question 10 Dropdown Business Analysis Frameworks

    Which pair of values correctly completes the statement? Choose the correct value for each blank.

    Choose the correct value for each blank.

    A business analyst at a retail bank is reviewing a requirements traceability plan for a new loan-approval workflow. The analyst recognises that each approved requirement must be linked to the stakeholder who requested it and to the test case that verifies it. The product owner asks the analyst to record which element connects requirements to their verification and which role is accountable for approving each requirement. The sponsor specifies the traceability matrix should map to test cases and the requirement sign-off should be owned by .
  11. 11 Question 11 Single choice Project Management Fundamentals and Core Concepts

    A project manager at a pharmaceutical company is reviewing a proposal to add a new reporting feature to a validated laboratory information system. The feature would be useful, but the change would require revalidation of the affected modules, which the quality team estimates at four months and substantial cost. The sponsor has asked the project manager to recommend how to handle the scope request. Under the project management code of ethics, the project manager must be honest with stakeholders and avoid conflicts of interest, and the company's quality policy requires all changes to validated systems to be assessed for compliance impact before approval.
    Which action is the MOST appropriate next step?

  12. 12 Question 12 Single choice Agile Frameworks/Methodologies

    A team at an insurance company runs its quarterly digital claims project using an adaptive approach. At the end of the second iteration, the team notices that three features were completed but two stakeholder-requested items were not started because the team underestimated the effort of integrating with a legacy policy system. The product owner wants to understand what the adaptive tracking should show to leadership, and the sponsor has asked why the team cannot simply report the percentage of a fixed baseline schedule completed.
    Which tracking approach BEST fits the adaptive environment?

  13. 13 Question 13 Single choice Business Analysis Frameworks

    A business analyst at a government agency is coordinating between the policy team, the systems development team, and external contractors building a benefits portal. The policy team writes detailed legal rules in lengthy documents, the developers prefer concise functional statements tied to features, and the contractors need acceptance criteria they can test against. Several rounds of change have caused confusion because each team interprets the same requirement differently. The agency wants a single communication approach that reduces misinterpretation across these groups.
    Which approach is MOST effective for this situation?

These are 13 of the 1320 questions in the full CAPM pack.

Get All 1320 Questions

Get all 1320 questions & answers

730 Satisfied customers
93.4% Pass rate feedback
84.8% Said questions matched
95% Found material helpful

Full access options for PMI CAPM

Self-study

PDF Version

$40.00 $20.00
  • 1320 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 1320 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CAPM Exam (Certified Associate in Project Management) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed