Exam Information
Free practice questions with explanations
PMI PMI-PBA Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Needs Assessment
A regional logistics company wants to reduce late deliveries. Its sponsor has proposed a new route-optimisation tool, but the business analyst finds that late deliveries stem from three different causes: driver shortages at two depots, outdated address data in the dispatch system, and a weekly batch process that delays route updates. The sponsor has asked for a solution scope statement within two weeks, and the steering committee will only fund initiatives whose scope is tied to a measurable problem statement. Budget is limited and the analyst must avoid committing to a solution before the problem is understood. Which action should the business analyst take FIRST?
Correct Answer: BExplanationA solution scope statement and business case depend on a clearly defined, measurable problem. Because the late deliveries have three distinct root causes, the analyst must first define and validate the problem in measurable terms before drafting any scope, otherwise the steering committee would fund a solution to an unverified problem. Drafting the tool scope first inverts the correct sequence and locks in an assumption. Costing causes and funding the cheapest ignores the value proposition, which is the wrong basis for prioritisation. Interviewing drivers about adoption is a later stakeholder concern and does not clarify the problem itself.
-
2 Question 2 Multiple choice Analysis
A public health agency is eliciting requirements for a new vaccination registry that must integrate with three existing clinic systems. The clinics use different data formats, and several regulatory rules restrict where patient data may be stored. The analyst has collected a long list of requests from clinic managers, auditors, and the IT team, and must now determine which requirements to accept, defer, or reject while keeping the baseline within a fixed budget. Which TWO actions best support this evaluation and allocation? (Choose two.)
Correct Answer: A, DExplanationRecording origin and rationale supports traceability and justifies accept, defer, or reject decisions to stakeholders. Interface analysis reveals which requirements depend on clinic data formats, which must be understood before allocation so that a deferred item does not block an accepted one. Auditor requests are not automatically accepted because regulation constrains the solution, not the budget decision. Ranking by stakeholder count ignores value and dependencies. Deferring by pilot membership alone ignores dependency analysis, which is required before allocation.
-
3 Question 3 Order list Planning
A financial services firm is preparing a requirements management plan for a multi-year core banking replacement. Several business units will request changes throughout delivery, and the change control board meets monthly. The analyst must establish the plan before elicitation begins so that all later activities follow an agreed protocol. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Select the methods for eliciting, analysing, documenting, and approving requirements.
- Define the traceability level required to monitor and validate requirements against the business case.
- Establish the channels and process for submitting and managing requirements change requests.
- Review the approved business case and project goals to set the context for requirements activities.
- Identify stakeholders and their roles, responsibilities, and communication protocols for requirements.
Correct Answer:- Review the approved business case and project goals to set the context for requirements activities.
- Identify stakeholders and their roles, responsibilities, and communication protocols for requirements.
- Define the traceability level required to monitor and validate requirements against the business case.
- Select the methods for eliciting, analysing, documenting, and approving requirements.
- Establish the channels and process for submitting and managing requirements change requests.
ExplanationThe requirements management plan follows from the business case and project context, so the plan starts with reviewing the business case and goals. Stakeholders and their roles must be identified before communication protocols can be set. The traceability strategy depends on which requirements and stakeholders exist and how they must be validated. Elicitation and approval methods are then selected, and change control channels are defined last, because change processes must align with how requirements are approved. Placing change control earlier would create a process with no defined approval methods to reference.
-
4 Question 4 Single choice Evaluation
A retail bank deployed a new mobile payment feature. Test evidence shows that 96 percent of acceptance test cases pass, but the two failing cases both relate to a requirement that transfers over 5,000 dollars must require a second authentication factor. The product owner argues that the failing cases are edge cases and proposes signing off the solution to meet the release date next week. Regulatory audit requires that every mandatory security requirement be verified before go-live. Which action should the business analyst take NEXT?
Correct Answer: CExplanationThe analyst must validate test results against the requirement's acceptance criteria. Because the failing cases belong to a mandatory regulatory requirement, the gap must be traced and communicated so stakeholders can resolve it before sign-off. A high aggregate pass rate does not satisfy a specific mandatory requirement. Removing failing tests falsifies the evidence, and disabling a mandatory control violates the audit condition.
-
5 Question 5 Dropdown Traceability and Monitoring
A pharmaceutical company tracks regulated requirements in a traceability matrix that must show each requirement's status and its upstream and downstream links. The analyst is updating the matrix for a requirement that was approved last month and is now under a change request. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
In the traceability artifact, the status of requirement REQ-27 should be set to while the change request is open, and the link to the affected test case should be recorded as a relationship so that impacted tests can be identified.Correct Answer:In the traceability artifact, the status of requirement REQ-27 should be set to Under Change while the change request is open, and the link to the affected test case should be recorded as a dependency relationship so that impacted tests can be identified.
ExplanationWhile a change request is open, the requirement must reflect that it is under change rather than remaining Approved, because approved status would hide pending impact. Recording the link to a test case as a dependency captures the relationship that allows the analyst to find which tests are affected when the requirement changes. Closed applies only after the change is completed and verified, and Deferred describes a scope decision rather than a change in progress. Derived describes requirements decomposed from others, not links to test cases, and parent and ancestor describe hierarchy rather than the impact relationship needed here.
-
6 Question 6 Drag and drop Needs Assessment
A hospital network is starting an initiative to reduce patient wait times in its emergency departments. The business analyst is preparing the needs assessment and must align each activity with the output it produces. Match each activity to the output it supports.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Surveying patients and referring physicians about their expectations for serviceAnalysing emergency department admission records and staff rosters from the last twelve monthsInterviewing the chief nursing officer and department heads about their performance targetsProblem statement grounded in measured evidenceTraceability matrix linking requirements to test casesProject goals and objectives aligned to organisational strategySigned-off test evidence for the deployed admission workflowStakeholder values used as a baseline for prioritising requirementsCorrect Answer:- Analysing emergency department admission records and staff rosters from the last twelve months → Problem statement grounded in measured evidence
- Interviewing the chief nursing officer and department heads about their performance targets → Project goals and objectives aligned to organisational strategy
- Surveying patients and referring physicians about their expectations for service → Stakeholder values used as a baseline for prioritising requirements
ExplanationHistorical admission records and rosters provide measured evidence that defines the business problem, which is the input to the solution scope. Interviews with senior leaders clarify goals and objectives so the initiative aligns with organisational targets. Surveys of patients and physicians reveal stakeholder values, which provide the baseline for later prioritisation. Test evidence and traceability matrices belong to later evaluation and monitoring work, not to the needs assessment, so they are the correct distractors.
-
7 Question 7 Single choice Analysis
A utilities provider is developing a smart-meter billing system. The product team has identified twelve candidate requirements but only enough budget and developer capacity for seven in the first release. Four candidate requirements depend on a meter data format that is still under vendor negotiation, and two of those four carry the highest stakeholder value. The sponsor wants the highest-value requirements in the first release. Which allocation approach creates a sound requirements baseline?
Correct Answer: AExplanationDependency analysis shows that the high-value requirements cannot be delivered reliably until the meter data format is settled. Including them would commit capacity to work blocked by an external negotiation, so the sound baseline defers them and includes independent requirements that can proceed. Including dependent requirements that cannot yet be built would leave the baseline unachievable. Accepting all twelve ignores the stated capacity limit, and including items regardless of dependencies pushes conflicts into the build phase where they are more costly.
-
8 Question 8 Order list Analysis
A telecommunications company is documenting requirements for a new customer billing workflow. The analyst has elicited requirements from several business units and must produce a requirements package that stakeholders can approve. Arrange the steps in the order they must be performed.
Drag the steps into the correct order, or use the arrows.
- Capture each requirement with its origin, rationale, and supporting details from elicitation sessions.
- Review the detailed requirements with stakeholders to uncover conflicts and clarify product options.
- Obtain formal sign-off on the requirements baseline from the designated approvers.
- Decompose high-level requirements into detailed functional requirements using data and process models.
Correct Answer:- Decompose high-level requirements into detailed functional requirements using data and process models.
- Capture each requirement with its origin, rationale, and supporting details from elicitation sessions.
- Review the detailed requirements with stakeholders to uncover conflicts and clarify product options.
- Obtain formal sign-off on the requirements baseline from the designated approvers.
ExplanationRequirements must be captured with their origin and rationale before they can be decomposed, because decomposition and modelling build on the captured source information. Once decomposed, the detailed requirements are reviewed collaboratively to uncover conflicts and clarify options. Sign-off on the baseline is the final step, since approvers need a validated package. Placing sign-off before review would ask approvers to approve unresolved conflicts.
-
9 Question 9 Single choice Planning
A government agency is replacing a legacy licensing system. Requirements are being managed in a shared document repository, and several contractors submit edits to the same specifications. An audit found that two contractors approved different versions of the same specification, and the auditors now require every approved version to be uniquely identifiable and recoverable. The agency's document control standard must be followed, and the repository must remain available to all contractors during the project. Which document control method should the analyst select?
Correct Answer: BExplanationVersion control with check-out, check-in, and approval states prevents concurrent conflicting edits, gives each approved version a unique identifier, and keeps every version recoverable, which meets the audit requirement. Emailing changes creates uncontrolled copies and manual merges that increase error risk. A single shared account removes accountability and conflicts with the need for traceable approvals. Copies with identical file names make versions indistinguishable and defeat unique identification.
-
10 Question 10 Dropdown Analysis
A logistics firm is modelling its order-fulfilment process to identify requirements for a new warehouse system. The analyst is writing a requirement for how the system must record order status changes so that downstream teams can audit fulfilment. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
The data model must store each order status change as a entity linked to the order, so that the history of changes can be queried, and the order record must reference the current status through a attribute.Correct Answer:The data model must store each order status change as a historical entity linked to the order, so that the history of changes can be queried, and the order record must reference the current status through a foreign key attribute.
ExplanationOrder status changes must be preserved as a historical entity so that the full sequence can be audited rather than overwritten. The current status on the order is best modelled as a foreign key that references the status reference data, which keeps the link consistent and queryable. A derived or calculated attribute would not hold the state independently. Transient or aggregated descriptions would discard history, and a surrogate key identifies rows rather than linking to status values.
-
11 Question 11 Single choice Needs Assessment
A university is reviewing an initiative to introduce online course registration. The sponsor's goal is to increase enrolment in under-subscribed courses by 15 percent within one year. Stakeholders include the registrar's office, faculty, students, and the finance department, which is concerned about tuition revenue changes. The analyst has identified that the registrar's office has not been consulted, and that finance has a conflicting view about the revenue goal. Which action best ensures the appropriate parties are represented, informed, and involved?
Correct Answer: BExplanationStakeholder identification must ensure that every party with an interest in the goals is represented and involved, and the registrar's office and finance both have a material stake. Engaging them together addresses the conflicting revenue view while the needs assessment is still open. Limiting consultation to users omits decision-makers with a direct interest in the outcome. Leaving resolution to the sponsor alone sidelines the parties affected, and deferring stakeholder analysis until elicitation misses the chance to align goals early.
-
12 Question 12 Multiple choice Evaluation
A manufacturing company deployed a new production scheduling solution six weeks ago. The business case projected a 20 percent reduction in machine idle time within the first quarter. Post-deployment data shows idle time has fallen by 9 percent, and operators report that the system does not handle split production runs, a requirement that was accepted and tested. The steering committee wants to know whether the solution meets the value proposition and which actions to take. Which TWO actions should the business analyst take? (Choose two.)
Correct Answer: B, EExplanationEvaluating a deployed solution means measuring realised value against the business case, so comparing the 9 percent result with the 20 percent projection gives the committee an objective basis for decisions. The split production run gap is a delta between an accepted requirement and what was delivered, and documenting it for stakeholder resolution is the appropriate evaluation output. Stability alone does not establish value, and recommending removal goes beyond the analyst's role without analysis. Revising the business case targets to fit results would undermine the value assessment.
-
13 Question 13 Drag and drop Planning
A healthcare software vendor is establishing its requirements management approach for a patient portal project with clinical, legal, and technical stakeholders. The analyst must set up the plan components so that each stakeholder group interacts with requirements through a defined channel. Match each planning element to the decision it governs.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Defined escalation path for urgent clinical safety change requestsMatrix showing which roles approve each class of requirementSchedule of weekly review meetings with clinical leadsCommunication protocol for requirementsLevel of traceability to tests for vendor-supplied components onlyRoles and responsibilities for approvalFormat standard for the final regulatory submission packageRequirements change control channelsCorrect Answer:- Defined escalation path for urgent clinical safety change requests → Requirements change control channels
- Matrix showing which roles approve each class of requirement → Roles and responsibilities for approval
- Schedule of weekly review meetings with clinical leads → Communication protocol for requirements
ExplanationAn escalation path for urgent change requests defines the channel through which change requests move, which is the change control element. An approval matrix defines which roles are responsible for approving requirements. Scheduled review meetings define how stakeholders communicate about requirements. The traceability level and submission format are real planning decisions but do not match the three elements described here, so they serve as the distractors.
-
14 Question 14 Single choice Traceability and Monitoring
A bank is tracking a set of security requirements in its traceability tool during an upgrade to its online banking platform. Requirement SEC-08 was deferred to a later release six weeks ago with stakeholder agreement, but the team has since begun building functionality that appears to depend on it. The project manager asks the analyst to confirm the status of all requirements for the monthly steering report. The steering committee needs accurate status, and the tool must show the dependency evidence. Which action should the analyst take?
Correct Answer: BExplanationA deferred requirement that has an active dependency is a risk that must be surfaced, and the traceability tool must capture the dependency so the conflict is visible. Recording the link, flagging the conflict, and communicating it allows the stakeholders to decide whether to reinstate the requirement or rework the dependent functionality. Keeping the deferred status unchanged hides the dependency conflict in the report. Changing the status to Approved misrepresents the release scope, and deleting the requirement destroys the evidence needed for monitoring.
These are 14 of the 200 questions in the full PMI-PBA pack.
Get All 200 QuestionsGet all 200 questions & answers
Full access options for PMI PMI-PBA
Self-study
PDF Version
- 200 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 200 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 200 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PMI-PBA Exam (PMI Professional in Business Analysis) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.