Scaled Agile SAFe-SGP Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 13
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Advance Lean-Agile in Government
A federal agency has run its citizen benefits modernization as a series of fixed-scope projects for six years, each with a separate budget and a go-live date set by statute. Leadership wants to move toward Lean-Agile delivery but must keep the statutory deadlines and cannot restructure appropriations this fiscal year. A transformation lead is asked to determine the core problem to solve first so the SAFe constructs can be applied appropriately. Which problem statement should the lead adopt as the starting point?
Correct Answer: AExplanationThe decisive constraint is the statutory go-live dates combined with fixed project funding, which together cause large batches and late feedback. That is the systemic problem SAFe's constructs address, such as moving from projects to value streams and Lean flow. Choosing a tool or a role staffing fix treats symptoms, and cancelling projects ignores the statutory obligations the agency must still meet.
-
2 Question 2 Single choice Apply SAFe Principles
A state transportation department is deciding whether to release a new traffic-signal control capability. The team has developed two architectural options. Option one is fully designed and will take 14 months to reach production. Option two is a smaller increment that can be in production in 3 months, but it constrains the later full design. The sponsor argues the larger option should be chosen because the upfront investment is already committed. The department applies SAFe's principle of taking an economic view. Which decision best reflects that principle?
Correct Answer: CExplanationAn economic view weighs the cost of delay and the value of earlier feedback against the remaining cost, and treats sunk cost as irrelevant to the forward decision. The 3-month increment delivers value and learning sooner. Recovering sunk cost is the classic fallacy the principle is meant to avoid, building both in parallel wastes capacity and delays value, and waiting for complete documentation contradicts building incrementally.
-
3 Question 3 Multiple choice Create High-Performing Teams and Programs
A health agency has formed an Agile Release Train spanning six teams that deliver a shared case-management platform. The train has a product management team, a solution architect group, and a vendor delivering two teams' worth of work under a fixed-price contract. Teams report that dependencies between them are discovered only during the end-of-iteration demo, and the vendor's work is planned on a separate schedule. The release train engineer wants to improve coordination and integration across the train and the supplier. Which two actions best address these conditions? (Choose two.)
Correct Answer: C, EExplanationBringing the supplier into PI Planning and onto the same cadence synchronizes planning and integration across the train and its external partner. Coordinating cross-team dependencies in a scrum of scrums, with vendor representation, surfaces dependencies early instead of at demos. Writing the vendor's stories as the release train engineer undermines team ownership, moving to waterfall reintroduces batching, and a central dependency team creates a bottleneck contrary to decentralized coordination.
-
4 Question 4 Order list Map the Path to Agency and Program Agility
A federal agency is moving a major acquisition program from a traditional project budget to Lean budgeting aligned with value streams. The program has an existing approved annual appropriation, and the finance office must remain able to report obligations to Congress. Leadership wants the transition to proceed without breaking current reporting or stopping delivery. Arrange the steps in the order they must be performed.
Drag the steps into the correct order, or use the arrows.
- Establish a portfolio-level budget allocation for each value stream using the approved appropriation.
- Review spending and value delivery metrics at a regular cadence and adjust the guardrails as needed.
- Identify the value streams that the program's epics and solution work will support.
- Define the guardrails that govern how funds can shift between value streams during the year.
- Transition funding from project-based allocations to value stream funding while keeping financial reporting intact.
Correct Answer:- Identify the value streams that the program's epics and solution work will support.
- Establish a portfolio-level budget allocation for each value stream using the approved appropriation.
- Define the guardrails that govern how funds can shift between value streams during the year.
- Transition funding from project-based allocations to value stream funding while keeping financial reporting intact.
- Review spending and value delivery metrics at a regular cadence and adjust the guardrails as needed.
ExplanationLean budgeting starts by identifying the value streams, since funding must follow them. Allocations are then set within the approved appropriation, and guardrails define permissible reallocation before the funding is actually moved. The transition happens only once those controls exist, and regular review closes the loop. Transitioning before guardrails exist would leave the finance office without a control mechanism, and reviewing before the transition has any effect to measure.
-
5 Question 5 Drag and drop Support Program Execution
A tax agency's program is building a large digital filing system. The program backlog contains work at several levels, and the program management team needs each element matched to the correct artifact that governs it. Match each requirement to the artifact that best governs it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
A system-level capability that delivers a benefit to filers and spans multiple teamsA multi-year direction describing where the filing solution will be in three yearsA prioritized list of program-level work awaiting refinement and sequencingBusiness owner charterProgram vision and roadmapFeatureTeam iteration planProgram backlogCorrect Answer:- A multi-year direction describing where the filing solution will be in three years → Program vision and roadmap
- A system-level capability that delivers a benefit to filers and spans multiple teams → Feature
- A prioritized list of program-level work awaiting refinement and sequencing → Program backlog
ExplanationThe program vision and roadmap describe the long-range direction and are updated as learning occurs. A feature is the system-level capability that spans teams and is the unit prioritized in the program backlog. The program backlog is the ordered list that backlog refinement keeps current. The team iteration plan covers only one team's near-term work, and a business owner charter defines roles rather than system capabilities or backlog content.
-
6 Question 6 Dropdown Plan with Cadence and Synchronization
A defense logistics program is preparing for its next PI Planning event. The program has a fixed calendar with an iteration cadence of two weeks and a single program increment of five iterations. The planning team wants the draft plan reviewed by business owners before the event and the final plan committed by the teams at its close. Complete the sentences by selecting the correct values for each blank. The draft plan is reviewed by business owners at the [1] of the planning event, and the teams commit to PI objectives at the [2] of the event.
Choose the correct value for each blank.
The draft plan is reviewed by business owners at the of the planning event, and the teams commit to PI objectives at the of the event.Correct Answer:The draft plan is reviewed by business owners at the middle of the planning event, and the teams commit to PI objectives at the end of the event.
ExplanationIn PI Planning, teams draft plans and business owners and stakeholders review them in the middle of the event so that feedback can be incorporated before the teams finalize their plans. Teams then commit to their PI objectives and confidence at the end of the event. Beginning-of-event review would precede the teams' draft work, and start-of-event commitment would precede planning. The closing review is a readout, not the commitment point.
-
7 Question 7 Single choice Embrace a Lean-Agile Mindset
A ministry's delivery organization has adopted sprint-length work intervals, but managers still assign each person to several concurrent projects and track individual utilization. Teams report that work waits for days in queues between handoffs, and cycle times have grown. A coach proposes a change that aligns with the Lean principle of managing work in process. Which action best reflects that principle in this environment?
Correct Answer: AExplanationLimiting work in process and making queue lengths visible is the Lean way to reduce wait time and cycle time, because it stops new starts from piling into queues. Maximizing utilization pushes more work into the system and worsens queues. Adding concurrent projects increases work in process, and shorter sprints without a WIP limit still allow unlimited starts, so queues persist.
-
8 Question 8 Single choice Lead Successful Change
A regional revenue department has begun a SAFe transformation. Senior managers attend training but continue to require detailed status reports every Friday and approve individual timesheets for each developer's tasks. Staff say that the new approach is being imposed on them, and several teams have reverted to old practices. The transformation lead must choose the most effective next step to lead the change by example. What should the lead do first?
Correct Answer: BExplanationLeading by example means leaders visibly change their own behaviors, and here that means replacing status reporting with flow data and taking part in the events. Mandating compliance or adding more training leaves the managers' contradictory behavior intact and sends a message that the change is for others. Running old reporting alongside the new practices signals that the change is optional, which is why teams reverted.
-
9 Question 9 Single choice Apply SAFe Principles
An environmental protection agency is building a permit-processing system. The product owner wants to finish the complete data model before any team begins work on the user interface, because the agency has learned that late changes to shared data structures are expensive. The architect proposes that the team instead deliver a thin vertical slice end to end, then expand it. Constraints include a regulatory requirement to demonstrate working functionality to an oversight board at the end of the next quarter. Which approach best satisfies the principle of building incrementally with fast feedback under these constraints?
Correct Answer: BExplanationA thin end-to-end slice builds incrementally, produces working functionality that can be demonstrated on the required date, and supplies feedback that corrects the design early, which reduces the expensive late data-model changes. Completing the data model first delays any working feedback until too late. Layer-by-layer integration in the final week creates integration risk that the schedule cannot absorb, and a frozen specification prevents learning from being applied.
-
10 Question 10 Multiple choice Plan with Cadence and Synchronization
A public utility regulator runs a program with four Agile Release Trains. Before the next program increment, the planning team reviews its readiness. The regulator requires that the planning event produce a documented business value estimate for each team and that all dependencies are visible across trains. The team has limited time and wants to prepare efficiently. Which two actions are most important to take in preparation for PI Planning? (Choose two.)
Correct Answer: C, DExplanationPreparing for PI Planning centers on having refined, prioritized features with acceptance criteria and identified dependencies, so teams can estimate and plan against them. Fixed iteration-level schedules are not the intent of preparation, since the plan is created by the teams at the event. Postponing until the next increment ends defeats the purpose of planning, and design documents are not required to establish business value estimates.
-
11 Question 11 Single choice Support Program Execution
A federal grants office has a program backlog containing a large number of epics, several of which were added as stakeholders requested them. The program has strict limits on how many features the teams can start in a single increment, and the grants office wants to make sure the highest-value features are selected next. Backlog refinement has become inconsistent. Which practice best sets priorities through backlog refinement in this environment?
Correct Answer: BExplanationWeighted shortest job first ranks work by the cost of delay divided by job size, which directly supports selecting the highest-value features under a start limit, and reassessing it in refinement keeps the ordering current. Priority by requester influence and alphabetical sorting ignore value, and freezing the order at the start prevents response to new information.
-
12 Question 12 Dropdown Create High-Performing Teams and Programs
A transportation agency runs an Agile Release Train with several teams and a shared services group. The release train engineer needs to describe the duties of key roles accurately in a governance charter, and wants to use the correct role names. The engineer is reviewing a draft that contains two errors in role assignment. Complete the statements by selecting the correct role for each blank. The [1] facilitates the program's ART events and removes impediments for the teams, while the [2] owns and prioritizes the program backlog for the train.
Choose the correct value for each blank.
The facilitates the program's ART events and removes impediments for the teams, while the owns and prioritizes the program backlog for the train.Correct Answer:The Release Train Engineer facilitates the program's ART events and removes impediments for the teams, while the Product Manager owns and prioritizes the program backlog for the train.
ExplanationThe Release Train Engineer facilitates ART events and removes impediments at the train level, which is the coordinating role the charter describes. The Product Manager owns and prioritizes the program backlog and defines the features that the train delivers. A Product Owner works at the team level on team backlogs, a Scrum Master serves a single team, a Solution Architect focuses on architecture, and the Business Owner represents stakeholder value rather than owning the backlog.
-
13 Question 13 Single choice Map the Path to Agency and Program Agility
A federal education department is adapting its acquisition practices for a large content-platform program that will be delivered by a vendor in incremental releases. The contracting officer must keep the contract within regulatory requirements, including a fixed total ceiling. The program wants to stop writing fixed requirements up front, but the department needs enforceable milestones for payment. Which acquisition approach best meets both needs?
Correct Answer: DExplanationA contract that ties milestone payments to objective evaluation of working, released increments keeps enforceable checkpoints while letting scope be refined inside the total ceiling, which matches the principle of basing milestones on objective evaluations. Removing the ceiling breaks the regulatory constraint. Keeping requirements fixed and paying only at final delivery conflicts with the goal of avoiding up-front requirements. Per-iteration contracts without a ceiling again violate the stated requirement.
These are 13 of the 45 questions in the full SAFe-SGP pack.
Get All 45 QuestionsGet all 45 questions & answers
Full access options for Scaled Agile SAFe-SGP
Self-study
PDF Version
- 45 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 45 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 45 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the SAFe-SGP Exam (SAFe 5 Government Practitioner Exam (5.0)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.