Exam Information
Free practice questions with explanations
Scaled Agile SP-SAFe-Practitioner Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Plan the Work
A team on an Agile Release Train is preparing for PI Planning. Its Product Owner has a backlog of twelve Stories. The team has been estimating Stories in story points, but the Stories vary widely in size, and during the last iteration two Stories that were estimated at three points each took nearly the full iteration. The Scrum Master wants a more reliable estimation approach that the team can use before committing Stories to the Program Increment, without spending a long session on each Story. The team has only ninety minutes before the next planning session and must give the Release Train Engineer an estimate-based capacity view. Which action should the team take FIRST?
Correct Answer: DExplanationRelative sizing is the estimation practice that fixes inconsistent point assignment: teams compare Stories to a known reference Story and place them on a shared scale, which is fast enough for a ninety-minute window. Splitting every Story into one-day tasks is too time-consuming before the session and does not address the scale inconsistency. Cutting the backlog to match velocity forces scope rather than improving estimates, and counting Stories discards the sizing information capacity planning needs. Estimating in hours would also be a regression from the team's point-based approach without solving the calibration problem.
-
2 Question 2 Order list Get Feedback
A distributed team building a payments reconciliation feature runs its Team Demo at the end of each iteration, but feedback from the Product Owner and a compliance stakeholder typically arrives days later through email, and defects are discovered only at the System Demo. The Agile Team wants to shorten the feedback loop within the next iteration, using only practices already available in the SAFe for Teams toolkit. Arrange the steps in the order the team should perform them.
Drag the steps into the correct order, or use the arrows.
- Prioritize the feedback items with the Product Owner so that they are sequenced into the next iteration's backlog.
- Hold a short review of the Stories demonstrated against the iteration goals to confirm which were accepted and which need rework.
- Invite the Product Owner and compliance stakeholder to the Team Demo and walk them through the Stories against their acceptance criteria.
- Record the feedback received during the demo directly in the team backlog as new or refined Stories.
Correct Answer:- Invite the Product Owner and compliance stakeholder to the Team Demo and walk them through the Stories against their acceptance criteria.
- Record the feedback received during the demo directly in the team backlog as new or refined Stories.
- Prioritize the feedback items with the Product Owner so that they are sequenced into the next iteration's backlog.
- Hold a short review of the Stories demonstrated against the iteration goals to confirm which were accepted and which need rework.
ExplanationFeedback loops are shortened by getting the stakeholders into the demonstration itself, so the feedback is captured live rather than afterwards. Once feedback is captured in the room, it must be recorded in the backlog so it is not lost, then prioritized with the Product Owner for sequencing. The review of accepted and rework Stories against iteration goals comes last, because it depends on the feedback having been recorded and placed. Doing prioritization before the demonstration would mean ranking feedback that has not yet been gathered.
-
3 Question 3 Dropdown Deliver Value
A payments platform team uses a Continuous Delivery Pipeline with automated build, test, and deployment stages. Compliance requires that each release candidate be promoted to production only after it has passed automated tests in the staging environment, and that the pipeline's stage state be visible to auditors. The team wants to apply a built-in quality practice that keeps defects from progressing downstream and ensures tests run on every change. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
To ensure defects are caught before promotion, the team applies at every stage so that each change is verified immediately, and it relies on to confirm that staging tests passed before production deployment is allowed.Correct Answer:To ensure defects are caught before promotion, the team applies continuous integration with automated tests at every stage so that each change is verified immediately, and it relies on a pipeline gate that checks staging test results to confirm that staging tests passed before production deployment is allowed.
ExplanationBuilt-in quality in SAFe depends on continuous integration with automated tests so that every change is verified as it is integrated, not held for a later batch or manual cycle. A pipeline gate tied to staging test results enforces the compliance rule automatically and leaves a visible stage state for auditors. A manual sign-off is slower and less verifiable than an automated gate, and post-release logs or deployment history reviews occur after the defect may already have reached production, which breaks the requirement that promotion depends on passing tests.
-
4 Question 4 Single choice Connect to the Customer
A team at a healthcare software company is asked to build a patient scheduling feature. The product manager has written a Feature that describes the desired capability, but the team notices that two of the Stories beneath it are purely technical tasks with no user value, and the business owner cannot explain how the Feature maps to any customer outcome. The Product Owner must restore a customer-centric framing before the next Program Increment planning event, and the Feature must remain small enough to fit within a single PI. Which action should the Product Owner take FIRST?
Correct Answer: AExplanationFeature descriptions and their benefit statements anchor the work to customer value, and Stories should describe what a user can do. Rewriting the benefit around the customer outcome and reshaping the Stories from the user's viewpoint fixes the disconnect before planning. Splitting by technical component just multiplies valueless pieces, and moving the Stories to Enablers hides the problem rather than fixing it. Architect approval does not establish customer value and skips validation entirely.
-
5 Question 5 Single choice Deliver Value
A financial services organization runs a Continuous Delivery Pipeline for its payments platform. Compliance requires that every release candidate passes automated regression, security scanning, and a performance baseline before reaching staging. Recently, teams have been bypassing the performance baseline when the pipeline is slow, and a defect reached production undetected. The release train wants to shorten lead time without weakening the quality evidence the auditors require. Which change BEST meets these requirements?
Correct Answer: DExplanationRunning the performance baseline in parallel with regression shortens the pipeline while keeping it as a mandatory, automated quality gate that auditors can verify. Making it optional or removing it breaks the compliance evidence requirement and reproduces the original bypass problem. Manual sign-off on every build adds delay and replaces built-in automated quality with human checks, which works against continuous delivery.
-
6 Question 6 Single choice Forming Agile Teams as Trains
An Agile Release Train has eleven teams spread across three time zones. Two teams are Scrum teams that plan in two-week iterations, while the others use Kanban with continuous flow for production support. A team member on a Kanban team asks why the team does not have a fixed iteration length like the Scrum teams. The Release Train Engineer is preparing a clarification for all teams. Which statement BEST describes how the teams should work within the train?
Correct Answer: BExplanationAgile teams on a train may use Scrum or Kanban, but they participate in the shared Program Increment cadence and synchronization events so the train delivers together. Forcing a single method or identical iteration lengths contradicts the flexibility the framework allows. Requiring conversion within one PI is not a rule, and having no coordinated cadence would prevent the train from synchronizing its planning and integration.
-
7 Question 7 Single choice Get Feedback
A team building a mobile banking feature has a Team Demo at the end of each iteration, but stakeholders rarely attend and feedback arrives weeks later through email. The team also needs to validate a new onboarding flow that the Product Owner believes customers will struggle with. The organization restricts external user access to production data for privacy reasons, and the team has only two weeks to decide on the onboarding design. Which feedback technique is the MOST appropriate next step?
Correct Answer: BExplanationUsability testing with representative users on prototypes and non-production data gives fast, direct feedback that respects the privacy restriction and fits the two-week window. Waiting for a PI-level System Demo is too slow for the decision, and recordings do not solve the timing problem. Production analytics is blocked by the privacy constraint for the new design and cannot reveal reasons for a flow that does not yet exist.
-
8 Question 8 Single choice Improve Relentlessly
A release train has been measuring its flow with lead time and throughput. In the last two Program Increments, the trains' lead time increased sharply, but the teams have all improved their individual velocity. Leadership wants to see improvement from the teams' perspective, and the Scrum Masters propose several changes. The train has a limited improvement budget and must choose the action that most directly addresses the system-level symptom. Which action should the train take?
Correct Answer: DExplanationIndividual team velocity can rise while system lead time grows, which points to waiting and handoffs between teams rather than team-level throughput. Value stream mapping exposes where work queues, letting the train target the largest bottleneck. Increasing story points or shortening iterations optimizes local metrics and may worsen the flow problem, and adding capacity does not address the queues between steps.
-
9 Question 9 Single choice Introducing SAFe
An enterprise is transitioning several departments to a lean-agile operating model. Senior managers want to know how the organization's leadership should change to support the new model. The company has a strong functional hierarchy, and managers currently approve every deviation from the annual budget. The transformation sponsor wants the leadership change to reinforce lean-agile principles rather than simply relabel existing processes. Which leadership behavior BEST demonstrates the Lean-Agile mindset that the organization needs?
Correct Answer: DExplanationLean-Agile leadership decentralizes decision making, funds value streams persistently, and bases decisions on evidence from delivered value rather than on approvals of individual changes. Centralized budget approvals and detailed task-level plans recreate the command-and-control model the transformation is meant to replace. Mandating identical tooling standardizes process without addressing the mindset the sponsor asked for.
-
10 Question 10 Single choice Plan the Work
A team is preparing for PI Planning and has several Stories that were estimated in the previous iteration. The Product Owner notices that one Story was estimated at 13 points, while the team's average Story size is much lower. The team is about to commit to this Story without decomposing it. The team's capacity for the iteration is 42 points and the Story would consume nearly one third of it. Which action should the team take BEFORE committing the Story to the iteration?
Correct Answer: CExplanationStories should be small enough to complete within an iteration, and a 13-point Story that consumes a third of capacity is a candidate for splitting into smaller Stories that each deliver user value. Lowering the estimate artificially changes the estimate without changing the scope, and deferring the Story leaves the problem unaddressed. Committing it as-is ignores the team's typical Story size and the risk to iteration delivery.
-
11 Question 11 Single choice Plan the Work
During PI Planning, a train has identified several dependencies between teams. One team's plan depends on a shared API that another team is building, and the dependent team has not yet committed to a delivery date within the Program Increment. The ART Planning session is nearing its end. The Release Train Engineer must ensure that the plan is realistic and that risks are visible to leadership. Which action BEST reflects the expected practice for handling this situation?
Correct Answer: CExplanationDependencies are made visible on the program board, linked to the affected features and the owning team, and reviewed so that feasibility is confirmed before planning closes. Removing dependent Features hides the work, and assuming delivery without recording the risk is exactly the kind of unseen risk the event is designed to expose. Deferring planning to a separate event breaks the coordinated PI Planning cadence the train depends on.
-
12 Question 12 Single choice Forming Agile Teams as Trains
An ART has nine teams, each containing a Product Owner, Scrum Master, and developers. A senior leader proposes assigning the Product Owner role to the team's Scrum Master to reduce headcount, arguing that the two roles have overlapping responsibilities. The Release Train Engineer must explain why the proposal should not be adopted. Which justification BEST supports keeping these roles separate?
Correct Answer: DExplanationThe Product Owner is accountable for the team backlog and maximizing value, while the Scrum Master is accountable for facilitating team process and removing impediments. Merging the roles creates a conflict of interest between prioritizing value and protecting process. The claim about one role per person is not a framework rule, and the proposed estimating split misstates how the roles are accountable.
These are 12 of the 269 questions in the full SP-SAFe-Practitioner pack.
Get All 269 QuestionsGet all 269 questions & answers
Full access options for Scaled Agile SP-SAFe-Practitioner
Self-study
PDF Version
- 269 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 269 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 269 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the SP-SAFe-Practitioner Exam (SAFe for Teams SP (6.0) - SAFe Practitioner) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.