1 Question 1 Single choice Applying SAFe Principles
An RTE is preparing the agenda for the upcoming PI Planning event for a 6-team ART. Two teams have announced they will be fully staffed only after a vendor contract is signed, which is expected three days into the iteration before planning begins. The business owners want the Program Backlog to be ready for the event with features sized and prioritized. The RTE has only two weeks of preparation time and cannot move the event date because the stakeholders are already committed. Which preparation action BEST supports a productive planning event under these constraints?
Correct Answer: AExplanationPre-planning is where the RTE ensures the Program Backlog is ready, with features refined and prioritized by Product Management and the System Architect, and capacity assumptions made explicit so teams can plan realistically. Deferring sizing removes the information the teams need, cancelling the event ignores the stakeholder commitment, and having teams estimate every story point is wasteful and not how features are prepared at the program level. Only the pre-planning refinement with clear capacity assumptions respects the fixed date and the two-week window.
-
2 Question 2 Single choice Applying SAFe Principles
During a Program Increment, a Scrum Program Manager notices that the ART's Inspect and Adapt workshop has been scheduled for the same afternoon as the final system demo, leaving the ART's Scrum Masters and Product Owners with no time to collect the team-level metrics they need. The RTE must keep both events intact because the system demo is externally scheduled and the workshop is required to close the PI. Which action is the MOST appropriate for the RTE to take first?
Correct Answer: BExplanationThe scheduling conflict is best resolved by sequencing the workshop into its own block after the externally fixed system demo, with metrics gathered beforehand so the time is used productively. Removing the demo breaks a stated constraint, and a recorded demo is not the live system demonstration the ART relies on. Shortening the workshop to thirty minutes undermines its purpose of reflecting and problem-solving across the ART. Sequencing the events while preparing inputs early keeps both intact.
-
3 Question 3 Single choice Executing the PI
An ART has completed the first three iterations of a PI. The RTE reviews the Predictability Measure and finds it at 62 percent, well below the target range, and several teams have reported that features are being accepted with partial completion. Leadership wants a quick reason to explain the variance but the RTE has limited time before the next ART Sync. The RTE must produce a credible diagnosis without changing the PI objectives mid-stream. Which action should the RTE take NEXT?
Correct Answer: CExplanationA low Predictability Measure should prompt a diagnosis of why planned work was not delivered as committed, which means comparing planned and actual feature completion with the teams and identifying causes such as dependencies and partial acceptance. Re-baselining business value to hit the target falsifies the metric, removing features mid-PI changes objectives the constraint forbids, and inflating estimates corrupts the velocity data. The diagnosis-first approach gives the RTE a credible explanation for leadership.
-
4 Question 4 Multiple choice Executing the PI
An RTE is reviewing flow metrics for an ART that is struggling with long wait times for features in the Kanban system at the program level. Work items are piling up in the Funnel and Analyzing states while teams report they are idle waiting for approval. The ART also has a rule that no new features can be started until the previous set is accepted. The RTE must improve flow without adding capacity and while keeping the WIP limits already agreed by the ART. Which TWO actions best optimize ART flow under these constraints? (Choose two.)
Correct Answer: B, DExplanationOptimizing flow here means reducing queue time at the bottleneck, which is achieved by a regular cadence and aging limit for items in Analyzing and by streamlining the approval decision that is making teams idle. Raising WIP limits or removing them contradicts the agreed constraint and increases multitasking, and adding more items to the Funnel only grows the queue. Attacking the actual bottleneck and its wait time is the correct flow improvement.
-
5 Question 5 Single choice Serving the ART
An RTE is supporting an ART that is adopting Release on Demand for its customer-facing platform. The business requires that the platform be deployable to production any day, but the compliance team needs a documented approval for each production change and the platform has a regulated audit trail. The RTE must recommend an approach that separates deployment from release decisions without weakening the audit requirement. Which approach BEST meets these needs?
Correct Answer: CExplanationRelease on Demand separates deployment from release, so code can reach production continuously while features are exposed through feature toggles that are switched on only after the release decision, and each toggle change can be recorded to satisfy the audit trail. Post-hoc monthly summaries fail the per-change approval requirement, holding everything to PI end removes the on-demand capability, and a manual weekly window still blocks the any-day deployment requirement. Only the toggle approach satisfies both constraints.
-
6 Question 6 Single choice Serving the ART
An RTE is preparing a value stream analysis for the ART that delivers a customer portal. The current process includes requirement analysis, development, testing, a security review, and a two-week release approval. Cycle time from idea to production is 14 weeks, of which the team reports that 9 weeks are waiting time between steps, not active work. The RTE needs to identify where improvement will yield the largest reduction in lead time, using the value stream mapping outputs. Which action should the RTE take FIRST?
Correct Answer: AExplanationValue stream mapping starts by documenting the current state with process time and wait time at each step, which reveals that most of the 14 weeks is waiting rather than work, and identifies the biggest waiting contributors. Assuming the security review is the largest contributor without measurement is unjustified, shortening iterations targets active work that is not the main cause, and ranking individuals misses the flow focus of value stream analysis. Mapping first gives the evidence for targeted improvement.
-
7 Question 7 Order list Serving the ART
An RTE has been asked to facilitate the first ART Sync after a new ART is formed. Several teams are still ramping up and the RTE must ensure the sync surfaces dependencies and impediments effectively within a single hour. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Have each team representative briefly report progress, objectives status, and new blockers.
- Assign owners and due dates for each impediment and dependency that needs resolution.
- Summarize the actions and confirm the follow-up for the next sync.
- Confirm the agenda and the list of attendees including representatives from all teams.
- Review the ART board for dependencies, impediments, and risks raised since the last sync.
Correct Answer:- Confirm the agenda and the list of attendees including representatives from all teams.
- Review the ART board for dependencies, impediments, and risks raised since the last sync.
- Assign owners and due dates for each impediment and dependency that needs resolution.
- Have each team representative briefly report progress, objectives status, and new blockers.
- Summarize the actions and confirm the follow-up for the next sync.
ExplanationThe ART Sync is facilitated by setting the agenda and attendees first, then reviewing the existing ART board to surface known issues, followed by team reports that add new blockers, then assigning owners so each item has accountability, and closing with a summary and follow-up. Assigning owners before the team reports would leave new blockers without owners, and summarizing before assignment would produce a summary with no accountable follow-up.
-
8 Question 8 Drag and drop Exploring the RTE Role
A newly appointed RTE is reviewing the responsibilities that define the role within the ART, using the SAFe guidance on how the RTE facilitates the ART and supports the Program Increment. Match each responsibility to the RTE activity that best represents it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Coaching the leaders on how to lead the ART through transformation and continuous improvementKeeping the ART moving toward PI objectives by removing systemic impediments outside team controlEnsuring the events of the Program Increment are scheduled, prepared, and facilitated on timeCoaching leadership on Lean-Agile practicesOwning the Product Backlog and setting feature priorityFacilitating the PI cadence and eventsImpediment and risk removal across the ARTAssigning individual story points to each team memberCorrect Answer:- Keeping the ART moving toward PI objectives by removing systemic impediments outside team control → Impediment and risk removal across the ART
- Ensuring the events of the Program Increment are scheduled, prepared, and facilitated on time → Facilitating the PI cadence and events
- Coaching the leaders on how to lead the ART through transformation and continuous improvement → Coaching leadership on Lean-Agile practices
ExplanationThe RTE is responsible for facilitating the ART's events and cadence, removing systemic impediments that sit beyond team control, and coaching leadership in Lean-Agile practices. Owning the Product Backlog and setting priority belongs to the Product Management role, and assigning story points to individuals is not an RTE responsibility at all, so both are distractors.
-
9 Question 9 Dropdown Applying SAFe Principles
An RTE is configuring the Jira-based planning tool for a new ART that uses a PI timeline with five iterations and one Innovation and Planning iteration. The RTE needs the iteration naming to follow the ART convention so that metrics roll up correctly, and the IP iteration must be recognizable as the last iteration in the PI. Complete the iteration definition by selecting the correct values for each blank.
Choose the correct value for each blank.
Iteration name: PI- Iteration-; Type:Correct Answer:Iteration name: PI-2024.2 Iteration-IP; Type: Innovation and Planning
ExplanationThe PI identifier is the program increment label, the IP iteration is named with the IP label as the last iteration, and its type must be Innovation and Planning so that the tool treats it as the planning and improvement window rather than a development iteration. Choosing a numeric iteration name for the IP iteration would break recognition of the final iteration, and the other type values describe iterations that do not apply to the IP window.
-
10 Question 10 Dropdown Executing the PI
An RTE is reviewing an ART's Program Increment metrics in the planning tool and must report progress without overstating predictability. The ART planned 80 story points of committed feature work across the PI and has completed 64 points of accepted work, with 8 points accepted partially. The RTE wants a report that reflects accepted delivery and separates partial acceptance. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
Accepted committed work: of 80 points; partially accepted work reported separately as points; the delivery ratio used in the readout is .Correct Answer:Accepted committed work: 64 of 80 points; partially accepted work reported separately as 8 points; the delivery ratio used in the readout is 64 divided by 80.
ExplanationOnly fully accepted committed work counts toward the delivery readout, so the 64 accepted points are reported against the 80 committed, and the 8 partially accepted points are reported separately rather than being added in, which would overstate predictability. Counting partial work into the accepted total or inverting the ratio would misrepresent delivery to leadership.
These are 10 of the 219 questions in the full SAFe-RTE pack.
Get All 219 QuestionsGet all 219 questions & answers
Full access options for Scaled Agile SAFe-RTE
Self-study
PDF Version
- 219 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 219 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 219 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the SAFe-RTE Exam (SAFe Release Train Engineer (6.0)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.