1 Question 1 Single choice Becoming a Lean-Agile leader
A transformation leader at a regional insurer sees that its Agile Release Trains report near-100 percent utilization of every team member, yet the number of features delivered per Program Increment has dropped for three consecutive PIs. Leadership wants to raise delivery throughput next quarter without hiring. Work is queued in front of every team, and cycle times have grown. Which action BEST reflects the Lean principle that should guide the leader's first response?
Correct Answer: BExplanationHigh utilization combined with growing queues and cycle times is the classic signature of too much work in process, which Lean treats as the root of poor flow. The Lean-Agile leader should limit WIP and make bottlenecks visible before pushing for more output, because maximizing individual utilization lengthens wait times for everyone. Raising planned load, committing to bigger point totals, or splitting the train all add pressure or structure without reducing queues, so they leave the flow problem intact.
-
2 Question 2 Multiple choice Building solutions with Agile product delivery
A retail bank's Solution Train is preparing for PI Planning. The Product Management group has written features that each describe a internal system change, with no link to a customer outcome. Several features are expected to take two full PIs, and the business wants to know value earlier. Which TWO actions best apply Customer Centricity and Design Thinking to improve how features are prepared before the Program Backlog is prioritized? (Choose two.)
Correct Answer: D, EExplanationDesign Thinking begins with understanding the customer and testing assumptions, so framing features as hypotheses tied to measurable outcomes and validating them early puts value at the center. Decomposing long features into increments that deliver observable value within one PI both speeds feedback and aligns with the Lean goal of smaller batches. Fixed dates and architecture-first sequencing reinforce internal focus, and a bloated backlog increases waste rather than improving customer value.
-
3 Question 3 Order list Establishing team and technical agility
A product group has been running its teams in traditional functional silos, with testers receiving completed code only at the end of each sprint. The Agile Release Train leader wants to reorganize around the flow of value and build quality in from the start of each iteration. Arrange the steps in the order they should be performed.
Drag the steps into the correct order, or use the arrows.
- Measure the flow of value through the train and tune the structure based on what the measures show
- Map the end-to-end value stream and identify the hand-offs between functional groups
- Form stable cross-functional Agile teams that contain the skills needed to deliver a story end to end
- Organize the teams into one Agile Release Train aligned to the value stream they serve
- Introduce built-in quality practices such as test automation and definition of done that apply inside each iteration
Correct Answer:- Map the end-to-end value stream and identify the hand-offs between functional groups
- Form stable cross-functional Agile teams that contain the skills needed to deliver a story end to end
- Introduce built-in quality practices such as test automation and definition of done that apply inside each iteration
- Organize the teams into one Agile Release Train aligned to the value stream they serve
- Measure the flow of value through the train and tune the structure based on what the measures show
ExplanationThe train's organization should follow from understanding the value stream, so the hand-offs must be mapped before any teams are formed. Only then can stable cross-functional teams be assembled with the skills needed to deliver end to end, and those teams are grouped into a train aligned to the value stream. Built-in quality is adopted once the teams and their work are established, and measurement with tuning closes the loop. Forming teams before mapping the value stream would reproduce the existing silo boundaries.
-
4 Question 4 Drag and drop Exploring Lean Portfolio Management
A diversified manufacturer is establishing its SAFe portfolio. Leadership has a strategic theme to shift revenue toward subscription services, but funding decisions are still made per project with annual approvals, and value streams have no stable budgets. Match each portfolio-level practice to the portfolio responsibility it fulfills.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Translating the subscription shift theme into a small set of portfolio epics with stated business outcomesAllocating a persistent budget to each value stream and reviewing its spending against outcomes each quarterReviewing the Kanban system of portfolio epics to limit work in process and expose blocked initiativesLead by ExampleConnect the Portfolio to Enterprise StrategyFund Value StreamsDefine a SAFe PortfolioEstablish Portfolio FlowCorrect Answer:- Translating the subscription shift theme into a small set of portfolio epics with stated business outcomes → Connect the Portfolio to Enterprise Strategy
- Allocating a persistent budget to each value stream and reviewing its spending against outcomes each quarter → Fund Value Streams
- Reviewing the Kanban system of portfolio epics to limit work in process and expose blocked initiatives → Establish Portfolio Flow
ExplanationTurning a strategic theme into epics that carry business outcomes is how the portfolio stays connected to enterprise strategy. Persistent value-stream budgets, reviewed against outcomes, replace per-project funding and represent the funding responsibility. Limiting work in process and exposing blockers on the portfolio Kanban is how flow is established at the portfolio level. Defining the portfolio's structure and leading by example are real objectives but do not match these three practices.
-
5 Question 5 Dropdown Thriving in the digital age with business agility
A logistics company has adopted SAFe at the team and program level but still measures success with on-time project completion. Executives now want to move to a business-agility operating model and need a framing that spans strategy, operations, and culture. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
SAFe is described as an operating system for business agility, and its Seven Core Competencies include as the capability that links strategic themes to execution, and as the capability that keeps the enterprise responsive to changes in market conditions.Correct Answer:SAFe is described as an operating system for business agility, and its Seven Core Competencies include Business solutions as the capability that links strategic themes to execution, and Organizational agility as the capability that keeps the enterprise responsive to changes in market conditions.
ExplanationBusiness solutions is the competency that connects strategic themes to the delivery of value through solutions, which is why it sits at the center of the link between strategy and execution. Organizational agility is the competency that lets the enterprise sense and respond to changing market conditions quickly across the whole business. Lean-Agile leadership and team and technical agility are also core competencies, but they describe people and engineering rather than the strategy-to-execution link or enterprise responsiveness.
-
6 Question 6 Single choice Leading the change
A digital services firm began its SAFe transformation six months ago. Senior managers continue to approve every change in team scope personally and rarely attend team events, while telling teams to be empowered. Staff are cynical, and adoption has stalled in two of four business units. The transformation office has limited time to act before the next quarterly review. Which action BEST addresses the leadership gap?
Correct Answer: DExplanationLeading by example means the leaders must practice the behavior they ask of others, and empowerment that is announced but not demonstrated is not believed by staff. Having managers delegate scope decisions and show up at team events signals the change in a way the cynical teams can see and gives the transformation credibility in the stalled units. A certification program, a compliance-based policy, or replacing leaders addresses the symptoms or the people rather than the modeled behavior that is actually blocking adoption.
-
7 Question 7 Multiple choice Becoming a Lean-Agile leader
A product development organization with five Agile Release Trains is struggling because each train runs its own planning process and holds separate reviews, creating duplicate work and inconsistent priorities. The head of the transformation wants the leaders to adopt a Lean-Agile mindset that aligns with SAFe Principles. Which TWO actions best embody that mindset? (Choose two.)
Correct Answer: B, CExplanationSystems thinking, a SAFe Principle, asks leaders to optimize the whole value stream rather than isolated parts, which is exactly the problem with five separately optimized trains. Applying economic decision-making by weighing the value and cost of options with data supports consistent priorities across trains without rigid templates. Forcing identical templates ignores context, keeping planning independent is the cause of duplication, and resolving conflicts by hierarchy undermines decentralized decision-making.
-
8 Question 8 Single choice Building solutions with Agile product delivery
A healthcare software vendor releases a patient-portal application through its pipeline. The company must keep its release frequency flexible so it can release a fix to a regulator-mandated feature in a few days, while other features ship on a regular cadence every two weeks. Currently, all features are bundled into a single release train event that occurs every quarter. Which approach BEST satisfies both needs?
Correct Answer: CExplanationRelease on Demand is achieved by decoupling deployment from release, so the business chooses when a feature becomes available to customers while the pipeline keeps the software deployable at any time. This supports the fast regulatory fix and the regular cadence for other features at once. A quarterly bundle with a manual gate, a monthly cadence, or a development freeze each still ties urgent changes to a fixed event, which breaks the few-day requirement.
-
9 Question 9 Dropdown Building solutions with Agile product delivery
A payments company is configuring its continuous delivery pipeline and wants automated checks to stop a faulty build before it moves toward production. Its platform team reviews the pipeline definition for a service and needs to fill in the stage relationships. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
In the pipeline, the stage runs automated unit and integration tests, and a build that fails these tests must not reach the stage before it is fixed.Correct Answer:In the pipeline, the build and test stage runs automated unit and integration tests, and a build that fails these tests must not reach the production deployment stage before it is fixed.
ExplanationAutomated unit and integration testing belongs in the build-and-test stage, where faults are caught early and the pipeline halts before anything is promoted. Only a build that has passed those checks may move on to production deployment, which is the gate that protects customers. Release and deploy, monitoring, and planning activities either happen after this gate or are not pipeline stages at all, so they cannot serve as the blocking point.
-
10 Question 10 Order list Establishing team and technical agility
A software team has been asked to reduce defects reaching system integration, where testing frequently discovers issues weeks after the code was written. The release train has committed to building quality in during each iteration. Arrange the steps in the order the team should perform them to adopt built-in quality.
Drag the steps into the correct order, or use the arrows.
- Integrate the changes continuously into a shared branch and run the automated test suite on every commit
- Run a system-level integration check at the end of the iteration to confirm the combined behavior
- Review the defect and escape measures in the retrospective and adjust the definition of done accordingly
- Define the acceptance criteria and the definition of done for each story before development begins
- Write automated tests alongside the code so that each story is verified as it is built
Correct Answer:- Define the acceptance criteria and the definition of done for each story before development begins
- Write automated tests alongside the code so that each story is verified as it is built
- Integrate the changes continuously into a shared branch and run the automated test suite on every commit
- Run a system-level integration check at the end of the iteration to confirm the combined behavior
- Review the defect and escape measures in the retrospective and adjust the definition of done accordingly
ExplanationBuilt-in quality starts with clear acceptance criteria and a definition of done agreed before any code is written. Tests are then written alongside the code so each story is verified as it is built, and continuous integration runs those tests on every commit to catch issues immediately. The end-of-iteration integration check confirms combined behavior, and the retrospective reviews escapes to refine the definition of done. Deferring verification until integration, as in the original process, is what caused the late discoveries.
-
11 Question 11 Drag and drop Building solutions with Agile product delivery
A regional airline is preparing for its next PI Planning event. Its Solution Train leaders want to make sure the program backlog and the event itself support delivery of value. Match each planning activity to the purpose it serves.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Ranking the features on the Program Backlog by weighted shortest job first to maximize economic valueEach team presenting its draft plan and surfacing dependencies with other teams during the program eventAgreeing on a fixed two-week iteration rhythm that all teams follow for the whole Program IncrementExperience PI PlanningPrioritize the Program BacklogLead by ExampleDevelop on CadenceRelease on DemandCorrect Answer:- Ranking the features on the Program Backlog by weighted shortest job first to maximize economic value → Prioritize the Program Backlog
- Each team presenting its draft plan and surfacing dependencies with other teams during the program event → Experience PI Planning
- Agreeing on a fixed two-week iteration rhythm that all teams follow for the whole Program Increment → Develop on Cadence
ExplanationRanking the Program Backlog by weighted shortest job first is the prioritization technique that sequences work to maximize economic value. Teams presenting plans and surfacing cross-team dependencies is the core of the planning event itself. Agreeing a shared iteration rhythm across the Program Increment is what allows teams to develop on cadence. Release on demand concerns decoupling release decisions from deployment, and leading by example is a leadership objective, so neither matches these three activities.
-
12 Question 12 Single choice Exploring Lean Portfolio Management
A government agency has created a portfolio of value streams funded through a fixed annual budget per project. A new citizen-services initiative has produced strong early results, but the funding for the value stream delivering it is locked until next year's budget cycle. Leaders want to respond to the improved evidence without disrupting governance or inflating spending. Which action BEST supports the portfolio's intent to fund value streams?
Correct Answer: CExplanationFunding value streams means giving them a persistent budget that they can adjust within guardrails as evidence arrives, rather than locking funds to projects. Allowing quarterly reallocation within the value stream, governed by lean budget guardrails and reviewed against outcomes, responds to the new evidence while keeping spending controlled. A one-off supplemental budget reverts to project thinking, delaying decisions ignores the evidence, and per-item executive approval reintroduces the bottleneck the portfolio is meant to remove.
-
13 Question 13 Multiple choice Thriving in the digital age with business agility
A national retail chain recognizes that its traditional annual planning cycle cannot keep pace with changing customer demand from digital channels. The executive team wants to adopt SAFe as an operating system for business agility. Which TWO outcomes most directly reflect the business agility the organization is trying to achieve? (Choose two.)
Correct Answer: A, CExplanationBusiness agility means the enterprise can sense and respond to changing market conditions quickly, which is reflected in short review cycles that redirect investment toward current evidence. A shared operating rhythm across business units lets the whole enterprise respond together rather than in isolated pockets. Departmental optimization of annual targets, maximizing work in flight, and isolating digital work from the core each reinforce the silos and overload that business agility is meant to remove.
-
14 Question 14 Single choice Becoming a Lean-Agile leader
A transformation leader at a regional insurer notices that her Agile Release Train (ART) teams are reporting high utilization, yet the value delivered per program increment has flatlined for three quarters. Senior managers ask her to raise individual team velocity targets by 20 percent to show progress. Several team members have privately warned that the work queue is growing and features wait weeks between teams. Which leadership action best applies Lean thinking to address the root cause?
Correct Answer: BExplanationLean thinking holds that high utilization across every team creates queues and long wait times, which is why flow slows even when people look busy. Reducing utilization targets, visualizing work in progress, and limiting queues addresses the system-level bottleneck that the scenario describes. Raising velocity targets only amplifies the problem by increasing work in progress without improving flow. Reassigning engineers moves the bottleneck rather than removing it, and stricter status reporting measures activity instead of delivered value. The correct answer aligns leadership action with the Lean principle of optimizing the whole value stream.
These are 14 of the 87 questions in the full SAFe-Agilist pack.
Get All 87 QuestionsGet all 87 questions & answers
Full access options for Scaled Agile SAFe-Agilist
Self-study
PDF Version
- 87 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 87 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 87 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the SAFe-Agilist Exam (SAFe Agilist - Leading SAFe (SA)(6.0)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.