1 Question 1 Single choice Know tasks associated with each stage of the sourcing process
A regional hospital trust is re-sourcing its sterile surgical gloves. The user group has asked for a specification requiring a minimum thickness and an 'ISO-certified' label. Procurement is concerned that the specification may exclude capable suppliers and invite non-conforming bids. The trust wants a specification approach that allows suppliers to propose different products while still guaranteeing the clinical outcome, and it must be defined before the market survey is published. Which approach should the procurement team adopt?
Correct Answer: AExplanationAn output-based specification describes what the glove must achieve, such as barrier integrity and clinical performance, rather than how it is manufactured, which widens the market and protects against bids that meet a paper standard but fail in use. Citing conformance standards as minimums and attaching KPIs for defects and delivery gives measurable tests for evaluating bids. Retaining the prescriptive specification and screening afterwards wastes market engagement and still excludes capable suppliers at the wrong stage. A brand-based specification restricts competition and breaches fair-treatment principles. Deferring specification until after bids are received makes the bids incomparable and undermines the evaluation.
-
2 Question 2 Multiple choice Know techniques that can achieve added value and its contribution to organisational success
A manufacturer of industrial pumps is reviewing a component bought from an external supplier at a high unit price, with a 4-week lead time. Engineers suspect the component is over-specified for the duty required. The board wants a solution that reduces total cost without degrading the pump's performance or reliability, and that does not extend the product development timeline by more than a month. Which TWO actions best deliver added value within these constraints? (Choose two.)
Correct Answer: D, EExplanationValue analysis examines the function the component performs and tests whether unnecessary features can be removed, while value engineering redesigns the item with suppliers to reduce cost while keeping required performance, and both fit the existing timeline when run as focused workshops. Consolidating volume without design review leaves the over-specification untouched and ignores the value question. Choosing the cheapest part breaks the stated performance and reliability constraint. A bulk make-to-stock move addresses lead time but increases holding cost and does not address the over-specification that is driving unit cost.
-
3 Question 3 Dropdown Understand how operational performance of the procurement and supply function can be measured and improved
A central procurement team wants to track how long its purchase-to-pay sourcing cycle takes for orders above a threshold, and how many days each stage adds. The team uses a workflow report that records stage start and end timestamps in a spreadsheet export. Select the correct values to complete the measurement formula, where the cycle time is the difference between the requisition approval date and the contract award date, and the stage duration is the difference between two timestamps for the same record.
Choose the correct value for each blank.
Cycle time (days) = -Correct Answer:Cycle time (days) = contract award date - requisition approval date
ExplanationSourcing cycle time is measured from the point the requirement is authorised to the point the contract is awarded, so the award date is the later timestamp and the approval date is the earlier one. Using the requisition raised date would include internal drafting time that the team has not agreed to count, and using the invoice or goods receipt dates would measure fulfilment and payment rather than sourcing. Supplier onboarding and payment run dates sit outside the sourcing stages entirely. Subtracting in this order yields a positive number of days for each sourced order, which is what the monitoring report needs.
-
4 Question 4 Drag and drop Understand the significance of ethics for procurement and supply
A procurement manager at a construction firm has discovered that a senior project engineer has a family member who owns a shortlisted subcontractor, and has not declared it. The manager must respond in a way that protects the integrity of the tender while following the organisation's code of conduct. Match each required response to the governance action that addresses it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Record the undeclared interest so it is managed going forwardInform those who hold responsibility for ethical compliancePrevent the engineer from taking further part in the tender processEstablish whether the engineer has influenced the shortlist or evaluation scoresAccept a retrospective declaration and close the matter without further actionSuspend the engineer's access and reassign evaluation dutiesReview the evaluation records and scoring audit trailNotify the subcontractor directly of the investigation findingsLog the conflict in the conflict-of-interest registerEscalate the suspected breach to senior managementCorrect Answer:- Establish whether the engineer has influenced the shortlist or evaluation scores → Review the evaluation records and scoring audit trail
- Prevent the engineer from taking further part in the tender process → Suspend the engineer's access and reassign evaluation duties
- Record the undeclared interest so it is managed going forward → Log the conflict in the conflict-of-interest register
- Inform those who hold responsibility for ethical compliance → Escalate the suspected breach to senior management
ExplanationThe first priority is to test whether the undeclared interest affected the outcome, which requires examining the evaluation records and audit trail for influence on scores. Removing the engineer from the process while the matter is open protects the tender, and the interest must be formally recorded so that it is managed for the rest of the project. Suspected breaches of a code of ethics are escalated to senior management as the governance route. Notifying the subcontractor of findings before investigation risks prejudicing the process and breaching confidentiality, and accepting a late declaration with no action would leave the tender integrity unresolved.
-
5 Question 5 Single choice Know tasks associated with each stage of the sourcing process
A public sector body is inviting tenders for a three-year managed print service. Bidders have raised clarification questions about whether the volume forecast is binding, and one bidder has asked privately whether it can submit a lower price if it is told the other bidders' prices. The procurement lead must handle the clarification stage without disadvantaging any bidder, while keeping the process transparent and within the published timetable. What should the procurement lead do?
Correct Answer: AExplanationIn a competitive tender, clarification answers that affect the requirement must go to all bidders at the same time so that no bidder gains an information advantage, and the anonymised publication keeps the process transparent. Disclosing other bidders' prices is a clear breach of confidentiality and would distort competition. Answering privately and withholding the response from other bidders creates an unequal position and is not transparent. Extending the closing date for everyone may be considered, but it is not the first action and does not address the private question itself.
-
6 Question 6 Single choice Know techniques that can achieve added value and its contribution to organisational success
A logistics company compares two suppliers for a fleet of delivery vans. Supplier X has a lower purchase price, while Supplier Y has a higher price but a 60 percent lower expected lifetime maintenance cost and better fuel consumption. The vans will be used for seven years, and the finance director asks procurement to justify the choice in terms of value for money rather than purchase price. Which approach should procurement use to make the comparison?
Correct Answer: CExplanationValue for money requires looking beyond the purchase price to the total cost of ownership across the asset's life, so the seven-year whole-life cost including fuel and maintenance, discounted to present value, gives a fair comparison. The purchase-price comparison ignores the substantial running costs that the scenario highlights. Delivery counts measure output but not cost, and feature counts measure specification rather than value. Only the whole-life approach reflects the lifetime costs the finance director is asking about.
-
7 Question 7 Order list Understand how operational performance of the procurement and supply function can be measured and improved
A procurement function has identified that its supplier invoice dispute process is causing late payments and complaints from key suppliers, which has become a customer-service issue for the business units it supports. The head of procurement wants to improve performance using a structured approach that starts from measurement and ends with monitored improvement, while limiting disruption to the current payment cycle. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Develop a timed action plan with named owners to address the root causes.
- Implement the agreed actions and track the cycle time and satisfaction measures against targets.
- Analyse the data to identify the root causes of delays in the dispute process.
- Gather customer and supplier satisfaction data and measure current dispute resolution cycle times.
Correct Answer:- Gather customer and supplier satisfaction data and measure current dispute resolution cycle times.
- Analyse the data to identify the root causes of delays in the dispute process.
- Develop a timed action plan with named owners to address the root causes.
- Implement the agreed actions and track the cycle time and satisfaction measures against targets.
ExplanationImprovement must start with evidence, so satisfaction and cycle-time data are gathered before anything else. The data then has to be analysed to find root causes rather than symptoms, because acting on assumptions risks fixing the wrong stage. An action plan with owners and dates turns the findings into commitments, and only then should actions be implemented and monitored against targets. Implementing before analysis or monitoring without an action plan would both fail the structured approach the head of procurement asked for.
-
8 Question 8 Dropdown Know techniques that can achieve added value and its contribution to organisational success
A buyer at a food processing company is reviewing supplier lead times for a critical packaging film used on a continuous production line. The line stops if stock falls below two days' cover. The buyer must calculate the total lead time for the film and the reorder point to avoid line stoppage. Select the correct values for each blank in the calculation note, where total lead time is the internal lead time plus the external lead time, and the reorder point must cover total lead time plus safety stock.
Choose the correct value for each blank.
Total lead time = +Correct Answer:Total lead time = internal lead time + external lead time
ExplanationTotal lead time combines the time the buyer's own organisation takes to process and release an order, which is the internal lead time, with the supplier's time to produce and deliver, the external lead time. The order cycle time and transit time are components or measures within these rather than the two parts of the total, and safety stock is a buffer added to the reorder point, not a lead time component. Using these two values gives the correct total lead time for protecting the line against stoppage.
-
9 Question 9 Single choice Know tasks associated with each stage of the sourcing process
A university is procuring laboratory chemicals under a framework that runs for four years. The framework allows suppliers to update product catalogues during the term. Procurement needs to set up supplier appraisal for shortlisted bidders before award, and wants the appraisal to reveal the risk of supply failure as well as cost and quality capability. Which appraisal action is most appropriate at this stage?
Correct Answer: CExplanationSupplier appraisal before award should test financial stability, accreditations, capacity and continuity, since these reveal supply failure risk that price alone cannot show, and scoring against defined criteria keeps the assessment consistent. Marketing materials are not a reliable basis for appraisal and are not binding. Deferring appraisal until after signature exposes the university to a supplier that cannot perform. Scoring unit prices alone ignores the risk and quality dimensions the scenario requires.
-
10 Question 10 Multiple choice Understand the significance of ethics for procurement and supply
A procurement officer at a public agency is responsible for a contract worth several million pounds. She has been offered tickets to a sporting event by a supplier that is bidding for the next phase of the work, and she is also a member of an evaluation panel for a related tender in which a former colleague is bidding. The agency's code of conduct requires staff to avoid situations where personal interests could affect business judgement. Which TWO actions should the officer take to comply with the code and manage the conflicts properly? (Choose two.)
Correct Answer: D, EExplanationUnder a code of conduct, hospitality offered by a bidder during a live procurement should be declined and recorded in the gifts and hospitality register, so the decision is visible to governance. A former working relationship with a bidder is a potential conflict that must be declared to the panel chair, with the officer stepping aside from scoring the affected bid. Accepting and declaring after the fact still creates the appearance of influence. Remaining on the panel while simply avoiding discussion does not remove the conflict, and sharing criteria privately with a bidder breaches fair-treatment and confidentiality obligations.
-
11 Question 11 Drag and drop Know techniques that can achieve added value and its contribution to organisational success
A procurement team is reviewing four proposed purchases for a manufacturing plant. Each purchase has a distinct requirement that must be met to apply the five rights of procurement. Match each requirement to the right that it satisfies.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Items must be fit for their intended function and meet the agreed specificationPurchases must be delivered to the correct production site and storage locationSupplies must reach the plant at the time the line requires themParts must arrive at the production line in the quantity the schedule specifiesRight placeRight qualityRight priceRight quantityRight timeRight supplierCorrect Answer:- Parts must arrive at the production line in the quantity the schedule specifies → Right quantity
- Supplies must reach the plant at the time the line requires them → Right time
- Items must be fit for their intended function and meet the agreed specification → Right quality
- Purchases must be delivered to the correct production site and storage location → Right place
ExplanationThe five rights of procurement are right quality, right quantity, right time, right place and right price, and each requirement in the scenario maps onto one of them. Quantity covers the amount the schedule specifies, time covers the moment the line needs it, quality covers fitness for purpose and specification, and place covers the delivery location. Right price and right supplier are the remaining options, but neither is described by the four requirements, so they serve as distractors that have no matching item.
-
12 Question 12 Single choice Understand how operational performance of the procurement and supply function can be measured and improved
A procurement department has a budget of 2.4 million for the year. At mid-year, actual spend is 1.3 million, while the forecast at the same point was 1.1 million. Analysis shows that a planned consolidation of office supplies was delayed, while spend on emergency maintenance rose sharply due to an ageing asset. The finance director wants the variance explained and a mitigation proposed that does not rely on cutting essential maintenance. Which response is most appropriate?
Correct Answer: CExplanationThe correct response splits the variance into timing effects, such as the delayed supplies consolidation, and genuine cost increases, such as emergency maintenance, because each needs a different response. Bringing the consolidation forward and planning asset renewal addresses the causes and reduces future emergency spend without cutting essential maintenance, as the finance director requested. A flat percentage cut ignores the causes and would harm essential activity. Freezing maintenance orders is unsafe and rejected by the constraint, and asking suppliers to delay invoices misstates spend and breaches good practice.
-
13 Question 13 Single choice Know techniques that can achieve added value and its contribution to organisational success
A hospital procures a high-volume disposable item and is considering whether to award a single national contract to one large supplier, which would give the lowest unit cost through economies of scale, or to split the requirement between two regional suppliers with higher unit prices. Clinical staff have reported that the national product has recurring quality issues with packaging integrity. The hospital's priorities are patient safety and sustained supply. Which decision best balances economies of scale against quality?
Correct Answer: DExplanationEconomies of scale can lower unit cost, but where quality is a patient-safety requirement the savings must not be taken at the expense of quality, and splitting the supply with defined acceptance testing gives assurance without relying on the scale supplier alone. Awarding on scale savings ignores the reported packaging failures. Continuing without testing dismisses the reports without verification. Rejecting batches after the fact still exposes the hospital to supply disruption and quality risk and does not address the root reliability issue, which is why the single-supplier option fails the stated constraints.
-
14 Question 14 Order list Understand the significance of ethics for procurement and supply
A procurement professional has discovered evidence that a supplier's sales representative offered a cash incentive to a member of staff in exchange for favourable treatment in an ongoing tender. The organisation's code of ethics requires suspected bribery to be handled in a controlled way that preserves evidence, protects the tender, and escalates to the correct level. The professional has the authority to report but not to investigate personnel matters. Arrange the steps in the order they must be performed.
Drag the steps into the correct order, or use the arrows.
- Escalate the suspected breach to senior management and the ethics or compliance function.
- Record the incident in the organisation's ethics log and cooperate with the agreed investigation.
- Suspend the staff member's involvement in the tender and restrict the supplier's access to tender information.
- Preserve the evidence, including emails and records of the offer, without altering them.
Correct Answer:- Preserve the evidence, including emails and records of the offer, without altering them.
- Suspend the staff member's involvement in the tender and restrict the supplier's access to tender information.
- Escalate the suspected breach to senior management and the ethics or compliance function.
- Record the incident in the organisation's ethics log and cooperate with the agreed investigation.
ExplanationEvidence must be preserved first, before anything can alter or lose it, and only then should involvement in the tender be restricted to protect the process. Escalation to senior management and the compliance function comes next, since the professional lacks authority to investigate personnel matters and the matter must be handled at the appropriate level. Recording in the ethics log and cooperating with the agreed investigation follows the formal escalation. Restricting the staff member before preserving evidence risks losing records, and recording or investigating before escalation would bypass the governance route.
These are 14 of the 90 questions in the full L3M2 pack.
Get All 90 QuestionsGet all 90 questions & answers
Full access options for CIPS L3M2
Self-study
PDF Version
- 90 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 90 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 90 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L3M2 Exam (Ethical Procurement and Supply) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.