A manufacturer sources components through a tier-two supplier in a country where recruitment agencies often charge migrant workers fees that are deducted from wages for the first ten months. During a routine audit, the buyer's team discovers this practice at the tier-two supplier, which is not in direct contract with the manufacturer. The company's supplier code of conduct prohibits bonded labour and requires flow-down to sub-tiers. The sourcing director wants to retain the supplier because it is the only qualified source for a critical part. Which action BEST meets the company's ethical and governance obligations?
Ethical codes that require flow-down mean the buyer must push remediation through the chain, not simply walk away or accept assurances. A documented corrective action plan with verification and conditional continuation addresses the bonded labour risk while managing supply dependency. Ignoring the issue because of no direct contract conflicts with the flow-down requirement. Immediate delisting ignores the stated supply risk and the chance to remediate. A written self-declaration is not independent verification and would fail a governance review.
A public sector body is procuring a five-year managed print service. The specification has been approved and a request for quotation has been issued to eight suppliers. Six responses have been received by the closing date, but two are incomplete: one omits the required environmental data sheet and another has priced an optional lot without the mandatory base lot. The evaluation panel must produce a contract award recommendation under a published evaluation methodology that prohibits post-closing changes to submissions. Which action should the procurement team take NEXT?
Under the stated methodology, submissions are evaluated after closing, and the published rules forbid post-closing changes, so incomplete mandatory elements mean rejection rather than repair. Moving to scoring and recommendation follows the correct stage order. Asking for resubmissions effectively reopens the bid and breaches equal treatment. Negotiating before evaluation reverses the sequence and invites unfairness. Reissuing with a weaker specification changes the requirement mid-process and is not justified by the facts.
A catering company supplies pre-prepared meals to a hospital and is also a buyer of fresh produce from several farms. The produce supplier fails to deliver one day, and the catering company cannot meet its customer's contracted meal deliveries for a ward of 80 patients, which triggers a penalty under the service agreement. The company's supply contract with the farm sets a 48-hour notice requirement for changes to delivery schedules. The operations manager must decide the immediate step that protects the customer delivery. What should the manager do FIRST?
Ingredients must reach patients that day, so the immediate step is an emergency sourcing from an approved alternative and transparent communication with the hospital about the risk. Reducing portions without notice breaches the service agreement and patient trust, so it is not correct. Force majeure is a weak claim for a supplier's ordinary failure and is not the first step. Cancelling the farm contract does not feed the ward that day and is not the immediate priority.
A national retailer compares two bids for supplying refrigerated distribution equipment. Bid X has a purchase price 8 percent lower than Bid Y, but its supplier has a projected energy consumption 15 percent higher over the seven-year asset life, and its maintenance response time is 72 hours against Y's 24 hours. Electricity and maintenance costs are material, and the board has set a target of reducing operating cost per store by 5 percent over the period. The finance director proposes awarding to the lowest purchase price. Which approach BEST supports the organisation's objectives?
Whole life or total cost of ownership analysis is the mechanism that lets the purchase price saving be weighed against higher energy consumption and slower maintenance, which directly affects the operating cost target. Awarding on purchase price ignores the forecast running costs that the board's target depends on. A split award does not answer the cost question and may add complexity. Choosing Bid Y regardless of cost fails to test value for money, since a faster response is not automatically worth any price premium.
A software company delivers a subscription analytics service to enterprise customers, and one customer's integration team reports that data exports are arriving late and incomplete. The company's service agreement guarantees 99.5 percent availability and a delivery of daily exports before 06:00 local time. Support logs show the failures occur only on weekends, when a third-party hosting provider performs scheduled maintenance. The customer account manager must decide the first corrective step that addresses the customer delivery failure while respecting the company's existing outsourcing contract. What should be done FIRST?
The root cause sits in the upstream supplier's maintenance window, so the first step is to verify the hosting provider's schedule and obligations and then make the customer-facing export reliable, for example by rescheduling. Changing the customer commitment would be a concession that the service does not need, and switching providers before diagnosing is premature and costly. Blaming the customer without evidence breaches the duty to deliver the service as agreed.
A manufacturer is measuring the effect of its procurement function on profitability. Over three years, it has renegotiated contracts for steel and packaging, and reported savings of 4 percent on its annual spend of 60 million. However, the finance team notes that cost of goods sold has risen by only 1.5 percent of revenue, and a new supplier quality issue has increased scrap costs by 900,000 a year. The CEO asks the procurement director to present the most accurate measure of procurement's contribution to profit. What should the director present?
Presenting the net benefit after the scrap cost increase gives a truthful account of procurement's effect on profit, since the quality problem is a consequence of supply decisions. The gross saving overstates the contribution by ignoring the new cost. The total spend describes influence, not impact. A contract count measures activity rather than financial effect.
A hospital trust is sourcing a three-year framework for surgical gloves. Demand varies seasonally, the trust wants to avoid excess stock, and suppliers must meet quality standards before award. Which THREE actions are appropriate within the pre-award and award stages of this sourcing process? (Choose three.)
A prequalification questionnaire screens suppliers before tenders are invited, and a specification with measurable quality requirements is needed before quotations are requested. A framework with call-off orders matches the seasonal demand and avoids excess stock. A single fixed three-year order ignores the variable demand and stock constraint. Awarding to the first respondent bypasses the assessment of quotations entirely.
A regional hospital outsources its laundry service to an external contractor under a three-year service contract. Collections happen twice weekly, and the contract states that any delivery more than 24 hours late attracts a service credit. In month four, the contractor misses two consecutive collections, citing a driver shortage, and the hospital's linen stock drops to a level that threatens theatre scheduling. The procurement officer must decide what to do first to protect continuity of supply while preserving the contractual position. Which action should be taken FIRST?
The hospital needs continuity now but must keep its contractual rights intact, so a formal notice of non-performance that references the service levels and asks for a recovery plan is the right first step, paired with interim supply. Immediate termination skips the notice and remedy process and could expose the hospital to a wrongful termination claim. Silently deducting credits does not address the operational risk to theatre scheduling. Insourcing requires recruitment and cannot protect supply in the short term, so it is not a first action.
A distribution centre issues a blanket purchase order to a packaging supplier for corrugated boxes, with call-off releases raised by warehouse staff as stock falls below reorder points. Over one quarter, the supplier's delivery notes frequently reference call-off numbers that do not appear in the system, and several deliveries have arrived without an associated release. Finance cannot match these invoices and the blanket order's remaining value is unclear. Which action BEST restores effective administration of this arrangement?
Blanket orders depend on call-off releases being raised, referenced on delivery notes and tracked against the remaining balance, so reconciling the balance and enforcing release numbers restores control at the root. Cancelling the blanket order abandons a valid arrangement and multiplies transactions. Paying unmatched invoices bypasses the control. Increasing the blanket value hides the administrative failure rather than correcting it.
A university has a devolved purchasing model in which faculties buy laboratory consumables directly from approved suppliers. Over two years, the central procurement team has found that 30 percent of consumables spend is with suppliers outside the framework, pricing varies by up to 40 percent for identical items across faculties, and several faculties have exceeded annual budgets without warning. The vice-chancellor wants savings without removing academic autonomy over research choices. Which structure change BEST addresses these issues?
A lead buying model lets central procurement aggregate demand and secure frameworks for common items, which addresses price variation and off-framework spend, while devolved authority preserves academic choice for specialist items. Full centralisation would remove the autonomy the vice-chancellor wants to keep. Removing the approved list would worsen maverick spend and price control. Relying on after-the-fact reviews leaves the budget overspend problem unresolved.
Get all 156 questions & answers
Full access options for CIPS L2M1
Self-study
PDF Version
- 156 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 156 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 156 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L2M1 Exam (Introducing Procurement and Supply) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.