Exam Information
Free practice questions with explanations
PRINCE2 PRINCE2-Foundation Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understand key concepts relating to projects and PRINCE2
A regional logistics company is launching a six-month initiative to introduce a new warehouse tracking system. The sponsor insists the project must be called a PRINCE2 project in its governance reporting. The project has a clearly defined scope, a fixed budget of 400,000 pounds, a single delivery date, and a cross-functional team drawn from operations and IT. Eight months into the programme, a steering group suggests the initiative is effectively a series of ongoing operational improvements with no end date, because the warehouse team will continually refine the system after handover. The project manager must decide how to respond to the suggestion while keeping the project within the PRINCE2 framework. Which characteristic of the initiative most directly determines whether it qualifies as a project under PRINCE2?
Correct Answer: BExplanationUnder PRINCE2 a project is a temporary organisation created for the purpose of delivering one or more business products according to a pre-agreed business case. The defining feature is temporariness with a clear start and end, so ongoing refinement after handover is operational work rather than project work. A cross-functional team is common in projects but does not define one, so it is not the decisive test. A fixed budget is a control parameter that many operational activities also have, so it cannot establish project status. A steering group is a governance arrangement that may exist in many organisations regardless of whether work is a project.
-
2 Question 2 Single choice Understand how the PRINCE2 principles underpin the PRINCE2 method
A public health agency is running a project to deploy a new vaccination booking platform. The project board has agreed a business case based on reducing waiting times by 30 percent. During the initiation stage, the project manager discovers that the original cost-benefit assumptions were based on an outdated population forecast, and the revised estimate shows the benefit may fall to 12 percent, while cost is rising. The project manager wants to honour the principle that ensures the project remains desirable and viable throughout its life. The board is considering whether to continue, pause, or stop. Which action best applies the principle that governs this decision?
Correct Answer: AExplanationThe continued business justification principle requires that the project is, and remains, desirable, viable and achievable, so the business case must be reviewed at key points and the board must confirm justification before committing further resource. Treating the signed-off case as untouchable breaks this principle. Delegating the decision to a team manager ignores that the project board owns the business case. Cutting scope without revisiting benefits is a tempting partial fix, but it does not establish whether the project should continue at all.
-
3 Question 3 Single choice Understand the PRINCE2 themes and how they are applied throughout the project
A manufacturing firm is running a PRINCE2 project to replace its legacy production scheduling software. The project's benefits review plan identifies a target of 15 percent reduction in machine downtime, measured twelve months after go-live. During the project, the team delivers a new scheduling module on time, and the project manager reports this as a benefit achieved. The senior user challenges this claim, noting that no operational change has yet occurred and the downtime measure has not been recorded. The finance director wants a precise description of the item just delivered so the investment can be tracked correctly. Which statement correctly classifies the new scheduling module and explains how it should be recorded?
Correct Answer: AExplanationAn output is a specific product delivered by the project, such as the scheduling module, and it is measured in terms of delivery. A benefit is the measurable improvement in performance that an organisation experiences, here the downtime reduction, which can only be confirmed after operational use. Describing the module as a benefit conflates the two concepts, which is exactly the error the senior user raises. An outcome is the change in working practice that results from using outputs, which is not what has been delivered at this point. A dis-benefit is an unwanted negative consequence and has no connection to the module's delivery.
-
4 Question 4 Multiple choice Understand the PRINCE2 themes and how they are applied throughout the project
A financial services company has commissioned a PRINCE2 project to build a customer self-service portal. The project board has three key concerns: keeping the project aligned with changing regulatory requirements, ensuring the senior supplier's delivery team can handle a sudden change request from the customer, and making sure the customer's operational representative is involved in acceptance decisions. The project manager is reviewing the role allocation within the organisation theme. (Choose two.)
Correct Answer: A, DExplanationThe senior user represents the interests of those who will use the outputs and is responsible for ensuring they meet user needs, including agreeing acceptance criteria. The change authority is a delegated body with authority to approve changes within limits set by the project board, and assigning it to the senior supplier is a legitimate arrangement for technical changes that do not exceed tolerance. Combining project assurance with the senior supplier is prohibited, because assurance must be independent of the people it monitors. The executive remains accountable for the business case and should not delegate day-to-day change approval. Post-closure operational performance belongs to the operating organisation, not the senior user role on the project.
-
5 Question 5 Single choice Understand the PRINCE2 processes and how they are carried out throughout the project
A government department has approved a project to modernise its benefits payment system. The project board has accepted the project brief, and the project manager is now preparing for the initiation of the project. The board expects a documented baseline that establishes how the project will be governed, managed and assured before significant spend starts. A senior colleague suggests that the project manager should start controlling the first stage immediately, arguing that the detailed planning can be completed later. The project manager needs to identify which process must be completed before work on the first stage begins, and what it produces. Which action is correct?
Correct Answer: DExplanationInitiating a project is the process that creates the project initiation documentation, which establishes the baseline for governance, management and assurance before the first stage begins. Starting controlling a stage before initiation leaves the project without an agreed baseline, which the senior colleague's suggestion ignores. Starting up a project is preceding work that produces the project brief and confirms viability, but it does not establish the baseline needed for the first stage. Directing a project runs throughout the project and is not the process that produces the baseline, and managing a stage boundary occurs at the end of a stage rather than before it begins.
-
6 Question 6 Single choice Understand key concepts relating to projects and PRINCE2
A national railway operator is delivering a PRINCE2 project to install a new signalling control centre. The project manager presents the progress report, which describes six aspects of performance: time, cost, scope, quality, risk and benefit. The project board notes that the team has delivered the control centre hardware early and under budget, but a quality test revealed that the failover system falls short of the specification. The project manager is asked which aspect is affected and how the gap should be managed within the performance framework. Which response best reflects how PRINCE2 expects performance to be managed?
Correct Answer: BExplanationPRINCE2 requires managing six aspects of performance, and a quality shortfall can affect scope, benefit and the business case, so it must be assessed in that wider context. If the deviation exceeds tolerance, it must be escalated as an exception report to the project board. Recording quality in isolation ignores how the gap affects the business case. Ignoring the gap because time and cost are within tolerance fails to manage all six aspects. Cutting the budget because hardware came in under cost misreads the situation, since the problem is quality rather than cost.
-
7 Question 7 Single choice Understand how the PRINCE2 principles underpin the PRINCE2 method
A regional council is running a PRINCE2 project to develop a digital permit application service. The project has a six-stage plan, and the project board has delegated authority to the project manager to manage each stage within agreed tolerances. During stage three, the project manager discovers that the integration with the council's legacy records system will take an extra three weeks, which pushes the stage end date beyond the stage tolerance agreed by the board. The project manager has a good relationship with the team and believes the delay can be absorbed by reallocating developers from stage four. The council's standard governance requires that significant deviations are escalated promptly. Which action best applies the principle that governs this situation?
Correct Answer: DExplanationThe manage by exception principle means the project manager manages within tolerance but must escalate to the project board when a forecast or actual deviation exceeds the tolerance, and the board decides how to respond. Absorbing the delay by reallocating work hides the deviation and makes a board decision without authority, even if it looks efficient. Delegating rescheduling to the team manager has the same problem, because the board, not the team manager, controls stage tolerance. Waiting for the stage closure report delays escalation beyond when the forecast breach was known, which is contrary to prompt escalation.
-
8 Question 8 Multiple choice Understand the PRINCE2 processes and how they are carried out throughout the project
A housing association is running a PRINCE2 project to replace its tenant maintenance request system. The project is in its final stage. The project manager is planning the closing a project process and wants to confirm that all required actions are completed before the project board is asked to approve closure. The sponsor is concerned that the project must not close before outstanding issues are dealt with and lessons are captured for future projects. (Choose three.)
Correct Answer: A, C, DExplanationClosing a project requires confirming that products have been handed over and accepted, with records completed, so operational ownership is clear. Follow-on actions and open issues must be passed on, which ensures nothing is lost when the project ends. The end project report compares the final outcome with the original objectives and business case and captures lessons, supporting the learn from experience principle. Reassigning team members before acceptance is premature and disconnects resources from unfinished work. Restarting the project brief is not part of closure, because the brief belongs to starting up and rewriting it at the end contradicts the process purpose.
-
9 Question 9 Single choice Understand the PRINCE2 processes and how they are carried out throughout the project
A water utility is running a PRINCE2 project to upgrade its treatment plant monitoring software. The project is in stage two, with a stage plan approved by the project board. The project manager has been managing product delivery and reporting progress through checkpoint reports. Midway through the stage, the team discovers that a supplier-provided sensor interface cannot meet the performance specification, and the project manager must decide how to respond within the stage. The project manager is considering whether to act inside the current stage or to request a new stage plan. The process that governs control within the stage must be used to monitor, report and respond to such deviations. Which process should the project manager be operating when this situation is handled, and what is its key objective?
Correct Answer: BExplanationControlling a stage is the process the project manager operates during a stage, with the objective of assessing progress, monitoring deliverables, reporting and responding to issues through checkpoint reports and exception reporting. Managing a stage boundary takes place at the end of a stage and is about planning the next stage, so it is not the right process mid-stage. Directing a project spans the whole project and is the board's process, not the project manager's day-to-day control. Managing product delivery is performed by team managers and the supplier, and while it is involved in the delivery, the control over the stage and its deviations belongs to controlling a stage.
-
10 Question 10 Single choice Understand the PRINCE2 processes and how they are carried out throughout the project
A large retailer is running a PRINCE2 project to replace its point-of-sale terminals across 400 stores. The project board has approved the project and the project manager is about to close the current stage. The stage has finished on schedule, but the team has discovered that two of the planned products, the store training materials and the updated returns policy, are not complete and will need additional effort. The project manager must decide whether to proceed to the next stage plan immediately or first manage the stage boundary. The project board requires an informed decision before the next stage commits budget. Which action best meets the purpose of managing a stage boundary in this situation?
Correct Answer: BExplanationManaging a stage boundary exists so the project board can make an informed decision before committing to the next stage, which means producing a stage end report, an updated forecast and a revised plan, then obtaining approval to proceed. Starting the next stage before the boundary is managed bypasses the board's decision and can commit budget without authority. Keeping the stage open until everything is delivered delays the boundary and ignores that the stage has already ended on schedule. Routing the decision to the change authority is inappropriate, because the change authority handles changes, not stage approval, which belongs to the project board.
-
11 Question 11 Single choice Understand how the PRINCE2 principles underpin the PRINCE2 method
A telecommunications firm is delivering a PRINCE2 project to replace its customer billing engine. The project manager is preparing the project initiation documentation and must document how the project will be tailored. The firm operates in a heavily regulated market, and the project is part of a wider transformation programme. The project board wants to avoid unnecessary bureaucracy on a project that is smaller than typical enterprise projects, but the regulator requires audit trails for changes to billing logic. The project manager considers reducing the number of stages, removing the quality review technique, and reducing the frequency of checkpoint reports. Which of these tailoring decisions is correct, and where must the decision be recorded?
Correct Answer: DExplanationTailoring is about adjusting how PRINCE2 is applied to suit the project's size, complexity, risk and environment, but it must never remove what the regulator or the organisation requires. Change control with an audit trail must remain, while checkpoint frequency and stage count can reasonably be tailored. These decisions must be documented in the project initiation documentation so that the board, the regulator and the team can see the agreed approach from the outset. The project brief precedes tailoring decisions and is not where they are recorded. Removing change control to reduce bureaucracy would break the regulatory audit requirement, and daily stand-up notes are not a controlled place for governance decisions.
-
12 Question 12 Single choice Understand the PRINCE2 processes and how they are carried out throughout the project
A logistics company is delivering a PRINCE2 project to introduce automated route planning software. The project has been directed by the project board, which has just approved the initiation documentation and the first stage plan. The project manager is now starting the controlling a stage process for stage one. The project manager must decide how the work will be authorised to start, and the team manager will be responsible for producing the software modules. The project manager wants to ensure work only begins once the correct authority and information exist. Which action must happen before the team begins managing product delivery for the first work package?
Correct Answer: AExplanationWork begins when the project manager authorises it by issuing a work package to a team manager, which states the products to be delivered, quality expectations, tolerance and the agreed reporting arrangements. This is the formal link between controlling a stage and managing product delivery. The project brief is a starting-up product written before initiation, so it is not written by the board at this point. The change authority deals with change requests and does not release funding through business case approval. The project closure report belongs to the end of the project, so it cannot authorise the first stage's delivery work.
These are 12 of the 476 questions in the full PRINCE2-Foundation pack.
Get All 476 QuestionsGet all 476 questions & answers
Full access options for PRINCE2 PRINCE2-Foundation
Self-study
PDF Version
- 476 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 476 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 476 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PRINCE2-Foundation Exam (PRINCE 2 Project Management Foundation (Version 7)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.