PRINCE2 PRINCE2-Agile-Foundation Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understand key concepts relating to PRINCE2
A regional logistics company is running a PRINCE2 project to replace its warehouse management system. The sponsor wants assurance that the project remains justified throughout its life, especially if costs rise or the expected benefits shrink. Which PRINCE2 principle most directly addresses this requirement, and what is the project manager's first action to support it?
Correct Answer: BExplanationContinued business justification is the principle that keeps the project tied to a viable reason to exist, and the Business Case is reviewed at each stage boundary and updated where the justification changes. The sponsor's concern about costs and benefits points directly to that review rather than to tolerance management, which governs deviation within an agreed plan. Manage by exception is about escalating deviations, not confirming the case still stands. Learn from experience matters, but logging lessons does not itself test whether the justification remains valid. Focus on products is important, yet defining a Product Description does not address ongoing justification.
-
2 Question 2 Single choice Understand key concepts relating to projects and PRINCE2 Agile
A software team in a government agency has been asked to deliver a citizen portal in a PRINCE2 Agile environment. The requirements are highly uncertain, the sponsor expects working releases every few weeks, and the board wants a clear definition of the project's temporary nature and unique output. Which statement best describes how the project should be framed?
Correct Answer: BExplanationA project is a temporary organisation created to deliver one or more outputs, and in PRINCE2 Agile the iterative releases are a delivery approach within that temporary structure, not a change to its nature. The portal is a unique output with a clear end point, so the project framing still applies. Treating it as an ongoing service ignores the defined end. Calling it a programme confuses scale with structure, since a programme coordinates several projects. A fixed-scope contract with iteration removed contradicts the stated need for frequent working releases under uncertain requirements.
-
3 Question 3 Single choice Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
A PRINCE2 project in a bank uses a traditional Product Based Planning approach. The team has adopted Scrum for building a new payments module, and the sponsor is concerned that the detailed Project Plan now contradicts the sprint-by-sprint backlog. The steering group still needs control at stage level and forecasts for funding. What is the most appropriate tailoring of the planning theme?
Correct Answer: AExplanationThe planning theme can be tailored so that PRINCE2 retains the high-level plans needed for funding, forecasting and stage control, while the detailed work is planned iteratively through the backlog and sprints. Dropping the Project Plan removes the forecasting the steering group relies on. Forcing a full product breakdown for every sprint recreates the rigidity agile is meant to avoid. Postponing all planning to the end leaves no basis for control or funding at all, which breaks the project's governance needs.
-
4 Question 4 Single choice Understand the agile ways of working, key terms and techniques
A product team is preparing for its first sprint planning session on a new HR platform. The Product Owner has a prioritised Product Backlog of 60 items, but the team has seen previous sprints overrun because stories were picked without a shared view of their size. The Scrum Master wants a technique that lets the team estimate relative effort quickly and consistently without debating hours. Which technique best meets this requirement?
Correct Answer: AExplanationRelative estimation with story points lets the team compare items against each other and reach consensus on size without converting every item into hours, which is why it suits the team's need for quick, consistent sizing. The Agilometer is a tool for judging how agile the project is, not for estimating hours per item. A burndown chart tracks remaining work during the sprint and does not set item sizes. The Lessons Log records past experience, but copying historical hours onto new items ignores the differences between backlog items and does not create the shared relative view the team needs.
-
5 Question 5 Single choice Understand the focus areas in an agile context
A PRINCE2 Agile project for a regional hospital is building a patient scheduling tool. During sprint reviews, stakeholders keep requesting additional features that were not in the agreed release scope. The Product Owner is under pressure to say yes, and the sponsor fears the schedule will slip. The project board has set a tolerance that allows scope changes only within the agreed release goal. Which action best addresses the focus area of value delivery in this context?
Correct Answer: AExplanationAgile focus on value means the team protects the release goal and delivers the highest-value items first, while new requests go into the Product Backlog to be ordered by value for later release. This keeps the agreed release scope intact within the board's tolerance. Adding features straight into the current sprint breaks the release goal and the tolerance. Halting the reviews removes the feedback loop that makes the product valuable. Routing every backlog item through a formal Change Request for individual sponsor decisions creates unnecessary overhead, when the backlog is the designed mechanism for prioritising change.
-
6 Question 6 Single choice Understand key concepts relating to PRINCE2
A mid-sized insurer's project is experiencing a sudden, unforeseen regulatory change that affects two products under development. The project manager has a Risk Register with several standing risks but none that cover this specific event. The project board has delegated a tolerance on cost and time for the current stage. Which PRINCE2 theme and first response best fit this situation?
Correct Answer: AExplanationThe regulatory change is an event that could affect objectives, so the risk theme applies: it should be recorded and assessed, then checked against stage tolerance to decide whether it needs escalation to the board. This keeps the response proportionate and governed. Quality inspection is relevant later but does not first address the uncertain effect on objectives. Restructuring the team is premature before the impact is understood. Raising a Request for Change without assessment skips the logging and evaluation that the risk theme requires.
-
7 Question 7 Single choice Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
A PRINCE2 Agile project to modernise a telecom billing system uses fixed-length timeboxes. At the end of a stage the board must approve the move to the next stage, but the team has been working in continuous releases across multiple timeboxes. The project manager needs to keep the stage boundary control while not forcing waterfall gating. Which tailoring of the Controlling a Stage process best meets this need?
Correct Answer: AExplanationStage boundaries can be aligned to a set number of timeboxes so the board keeps its control points, with the working releases providing the evidence the board needs at each boundary. Removing boundaries entirely weakens the governance the board is entitled to. Approving every sprint creates excessive gating that undermines the timebox rhythm. Holding a single review only at closure leaves the board without control during the project, which conflicts with managing by stages.
-
8 Question 8 Single choice Understand the agile ways of working, key terms and techniques
A product team delivering a customer loyalty app holds a daily stand-up but finds that the same impediments are raised repeatedly without being resolved. The Scrum Master notices that team members do not know who owns each impediment. The project manager wants the process to surface blockers quickly and assign them to someone able to act. Which practice should the team adopt?
Correct Answer: AExplanationA visible impediment log with a named owner for each item, reviewed at the daily stand-up, gives the team clear responsibility and a way to track progress on blockers. Putting impediments into the Risk Register delays action until a later review, which defeats the purpose of quick surfacing. Extending the stand-up to an hour undermines its short timebox without adding ownership. Assigning all impediments to the Product Owner misreads the role, since the Product Owner prioritises the backlog rather than resolving every blocker.
-
9 Question 9 Single choice Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
A public transport authority is running a PRINCE2 Agile project to build an electronic ticketing app. Testing has shown that a feature delivered in the last sprint works technically but does not meet the accessibility standard set in the Product Description. The Product Owner wants to accept it because the sprint goal was met. The quality theme requires that products meet their stated quality criteria. What should the project manager do first?
Correct Answer: AExplanationThe quality theme requires that products meet their defined criteria, so the feature should not be accepted as delivered; the gap should be recorded against the criteria and prioritised for rework in the backlog. Accepting it because the sprint goal was met overrides the quality criteria. Changing the criteria to fit the delivered feature lowers standards to suit the outcome, which is not an acceptable response. Escalating only as a risk leaves a known non-conformance unaddressed in the backlog.
-
10 Question 10 Multiple choice Understand key concepts relating to projects and PRINCE2 Agile
A county council is starting a PRINCE2 Agile project to replace its planning permission portal. Several stakeholders disagree on what the project is supposed to deliver. Which TWO statements correctly describe the relationship between the project's outputs and its outcomes? (Choose two.)
Correct Answer: B, CExplanationOutputs are the tangible products the project creates, while outcomes are the changed ways of working that the organisation adopts, and benefits follow from those outcomes over time, so the business case should reference both. Saying the project team is accountable for outcomes at closure ignores that outcomes arise after handover and depend on the business. Treating outputs as sufficient for success ignores whether the intended change happens. Equating outputs and outcomes confuses two distinct concepts that PRINCE2 separates.
-
11 Question 11 Multiple choice Understand the agile ways of working, key terms and techniques
A team building a corporate expenses tool wants to tighten its use of agile techniques. The Product Owner, Scrum Master and developers are deciding which practices fit their current situation, where the backlog is large and changing rapidly. Which THREE statements correctly describe appropriate use of agile techniques here? (Choose three.)
Correct Answer: B, C, DExplanationSprint reviews let stakeholders inspect the increment and feed information back into the backlog, retrospectives drive concrete process improvement, and ordering the backlog by value is the Product Owner's core responsibility. Freezing the backlog conflicts with the need to respond to a rapidly changing backlog, though sprint scope protection is different from freezing the backlog. Assigning individual tasks from the Scrum Master is not how a self-organising Scrum team works, since the team decides how to meet the sprint goal.
-
12 Question 12 Multiple choice Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
A PRINCE2 Agile programme of work for a utility company spans three projects delivering a smart meter rollout. The project managers want to ensure that the tailored management products still support governance and accountability. Which TWO tailoring decisions best preserve the purpose of PRINCE2 management products in this agile context? (Choose two.)
Correct Answer: C, EExplanationKeeping the Business Case with review at stage boundaries preserves the justification purpose, while the Product Backlog carries detailed requirements, and a Lessons Log shared across the programme keeps experience feeding improvement. Removing the Risk Register loses the structured record that governance relies on, even though sprint reviews surface some risks. Replacing the Project Initiation Documentation with a verbal briefing loses the baseline that defines scope, tolerance and governance. Dropping the Highlight Report removes the board's summary of progress, which the daily stand-up does not serve, since it is an internal team meeting rather than a board report.
These are 12 of the 162 questions in the full PRINCE2-Agile-Foundation pack.
Get All 162 QuestionsGet all 162 questions & answers
Full access options for PRINCE2 PRINCE2-Agile-Foundation
Self-study
PDF Version
- 162 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 162 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 162 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PRINCE2-Agile-Foundation Exam (PRINCE2 Agile Foundation V2) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.