PRINCE2 PRINCE2-Agile-Practitioner Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 16
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice PRINCE2 Agile Practitioner Overview
A government digital team has adopted PRINCE2 Agile for a citizen portal project. The steering group wants assurance that the project remains controlled, yet the product owner needs to reprioritise the backlog every two weeks based on user testing feedback. Fixed budget and a regulatory go-live date are non-negotiable. During a sprint review, the product owner proposes replacing the stage plan with a single product backlog reviewed only at the end of each sprint, with no tolerance thresholds set for the overall project. The project manager is asked what should happen before the proposal is accepted. Which action is the BEST response?
Correct Answer: BExplanationPRINCE2 Agile keeps the principle of control through stages and tolerances at the project level, because the fixed budget and regulatory date must still be governed. The product backlog and sprints are the mechanism for adaptive delivery inside those controls rather than a substitute for them. Accepting the proposal removes the thresholds that protect the fixed budget, so it fails the constraints. Replacing the business case with backlog items confuses outputs with benefits, which must still be tracked against the justification for the project. Pushing all tolerance to team level ignores that the board owns project-level risk and the fixed date.
-
2 Question 2 Drag and drop Skills and Processes
A logistics firm is running a PRINCE2 Agile project to replace its warehouse scheduling system. The project manager has identified several practices and must decide which PRINCE2 Agile purpose or behaviour each one primarily supports. Match each practice to the principle or theme it best serves.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Holding a short daily stand-up where team members report progress and impediments to one anotherRecording a risk register entry with owner, probability and impact for a supplier delaySetting a cost tolerance of plus or minus ten percent for the current stageReviewing the business case at each stage boundary against expected benefitsAdaptive delivery through empirical inspection and adaptationTailoring the quality register to remove the product descriptionManaging risk proportionately with visible ownershipManagement by exceptionContinued business justificationCorrect Answer:- Holding a short daily stand-up where team members report progress and impediments to one another → Adaptive delivery through empirical inspection and adaptation
- Recording a risk register entry with owner, probability and impact for a supplier delay → Managing risk proportionately with visible ownership
- Reviewing the business case at each stage boundary against expected benefits → Continued business justification
- Setting a cost tolerance of plus or minus ten percent for the current stage → Management by exception
ExplanationThe daily stand-up is an inspect-and-adapt practice that supports empirical adaptive delivery. Risk entries with named owners and ratings reflect proportionate risk management. The business case review at stage boundaries sustains continued business justification. Stage-level cost tolerances are the mechanism of management by exception, letting the board intervene only when limits are exceeded. The distractor about tailoring the quality register is a real activity but does not map to the four practices given.
-
3 Question 3 Single choice Project Management Solution
An insurance company is delivering a PRINCE2 Agile programme of three projects that share a single platform team. The platform team is pulled into each project's sprint planning, causing repeated context switching and missed commitments. The programme board wants a governance arrangement that keeps the three project managers accountable for their own outcomes while giving the shared team one coherent priority list. Regulatory reporting to the programme board must continue monthly. Which arrangement BEST meets these requirements?
Correct Answer: CExplanationA single prioritised backlog with a designated arbitrating owner gives the platform team one coherent priority list while preserving accountability for each project's outcomes and stage plans. This also supports the monthly programme-board reporting requirement. Merging the projects loses the separate accountability and business cases the board expects. Letting teams alternate by mutual agreement leaves priorities unresolved and is the cause of the current missed commitments. Removing project-level stage plans conflicts with the need for each project manager to remain accountable and with the control expectations of the board.
-
4 Question 4 Order list Skills and Processes
A PRINCE2 Agile project for a regional bank is nearing the end of its first stage. The bank's compliance team requires that the project board approves the transition before the next stage's work begins, and the project manager must ensure the benefits review plan remains valid. Arrange the steps in the order they must be performed at this stage boundary.
Drag the steps into the correct order, or use the arrows.
- Update the business case and confirm it remains viable against expected benefits
- Compile the stage end report showing products delivered, tolerance position and forecast
- Authorise the start of the next stage and release its work to the team
- Hold a stage boundary review with the project board to approve the next stage plan
- Re-baseline the risk register and issue log for the next stage
Correct Answer:- Compile the stage end report showing products delivered, tolerance position and forecast
- Update the business case and confirm it remains viable against expected benefits
- Hold a stage boundary review with the project board to approve the next stage plan
- Re-baseline the risk register and issue log for the next stage
- Authorise the start of the next stage and release its work to the team
ExplanationThe stage end report summarises delivery and tolerance position, which the board needs before deciding anything. The business case must then be updated so the board judges continued viability against current facts. The board holds the review and approves the next stage plan, after which risk and issue records are refreshed to reflect that plan. Only then is the next stage authorised and work released, because compliance requires board approval before any new work begins.
-
5 Question 5 Single choice Certification Validity
A project manager gained PRINCE2 Agile Practitioner certification on a date three years ago and has since delivered two further projects. The certificate is now close to expiry and the employer's learning budget is limited. The project manager wants to keep the credential active without sitting the full foundation course again. Which pathway is the MOST appropriate way to maintain the certification status?
Correct Answer: AExplanationCertification holders maintain status through continuing professional development via the AXELOS membership pathway or through examination renewal options, so the membership route fits a constrained budget. Retaking the Practitioner exam is an available option but is not the only or most budget-conscious route given the stated limit. An employer cannot grant a validity extension, so that option is wrong. Retaking Foundation is not a requirement for maintaining Practitioner status each cycle.
-
6 Question 6 Dropdown Target Audience
A senior project manager at a telecoms firm is preparing a short internal briefing that explains who should pursue PRINCE2 Agile Practitioner certification. The briefing must reflect that candidates need prior PRINCE2 experience and must be able to apply adaptive practices in their own delivery environment. Select the correct value for each blank in the briefing statement.
Choose the correct value for each blank.
Candidates for PRINCE2 Agile Practitioner are typically who already hold the PRINCE2 Foundation qualification and who applying adaptive delivery practices within a PRINCE2 governance structure.Correct Answer:Candidates for PRINCE2 Agile Practitioner are typically project managers and team leaders who already hold the PRINCE2 Foundation qualification and who can demonstrate the ability to applying adaptive delivery practices within a PRINCE2 governance structure.
ExplanationPractitioner candidates are project managers and team leaders who are delivering projects, and they must demonstrate they can apply adaptive practices within PRINCE2 governance. The other options describe roles outside the audience, such as product support staff, auditors or end users. The second set of phrasing options either contradict the purpose of blending agile practice or do not express a capability that the certification assesses.
-
7 Question 7 Multiple choice Project Management Solution
A healthcare provider is adopting PRINCE2 Agile for a patient records upgrade. The board requires a fixed completion date and a set budget, and the clinical governance group requires that patient safety testing is not compromised by delivery pressure. Several teams are working in sprints, and the project manager must ensure the solution remains controlled. Which TWO actions together BEST meet these requirements? (Choose two.)
Correct Answer: B, EExplanationProject-level tolerances with escalation keep the board in control of the fixed date and budget, as PRINCE2 management by exception requires. Embedding clinical safety criteria in the definition of done and reviewing quality at stage boundaries protects patient safety without slowing delivery arbitrarily. Removing safety testing breaches the clinical governance requirement. Letting teams move the fixed date gives away board authority. A rolling plan with no forecast removes the visibility the board needs.
-
8 Question 8 Single choice PRINCE2 Agile Practitioner Overview
A public transport authority is running a PRINCE2 Agile project to deliver a mobile ticketing app. Midway through the project, the team discovers that a key assumption about the payment provider's API has changed, risking a two-week delay. The team lead wants to resolve it within the sprint by reducing the scope of the current increment, but the scope reduction would remove a regulatory requirement. Which response is the BEST first action?
Correct Answer: BExplanationThe change exceeds the team's authority because it threatens a regulatory requirement and a potential tolerance breach. The correct first step is to log it, assess impact on tolerances and the requirement, and escalate to the board for a decision. Dropping the regulatory requirement is unacceptable regardless of later re-addition. Silently extending the sprint hides a tolerance issue from governance. Waiting for the provider to revert is outside the project's control and bypasses the board.
-
9 Question 9 Drag and drop Certification Validity
A Practitioner-level certification holder is reviewing how to keep their credential current across a three-year cycle while working on a regulated public sector programme. Match each renewal consideration to the outcome it primarily supports.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Confirming the three-year validity start date from the original certification recordTracking continuing professional development activity against the membership requirementsUsing the examination renewal option when membership-based activity is not practicalKnowing when renewal falls dueKeeping certification status currentMaintaining status by an alternative pathwayUpdating the programme's risk register with the renewal dateCorrect Answer:- Tracking continuing professional development activity against the membership requirements → Keeping certification status current
- Confirming the three-year validity start date from the original certification record → Knowing when renewal falls due
- Using the examination renewal option when membership-based activity is not practical → Maintaining status by an alternative pathway
ExplanationRecording continuing professional development against membership requirements is what keeps status current. The original certification record establishes when the three-year period ends, so it determines when renewal is due. Examination renewal is the alternative pathway when membership activity is not feasible. The risk register entry is a programme activity with no bearing on the credential's renewal mechanics.
-
10 Question 10 Single choice Skills and Processes
A PRINCE2 Agile project in an energy company has a product owner who wants to change the acceptance criteria for a feature already in a completed sprint. The change would improve usability but would also alter a previously accepted product, affecting the stage plan's product descriptions. The project manager must decide how to handle this within the PRINCE2 Agile controls. What is the MOST appropriate action?
Correct Answer: CExplanationA change to an accepted product alters a product description and possibly the stage plan, so it must go through change control with an impact assessment. Editing only the backlog ignores the link to accepted products. Informal acceptance bypasses the control the stated controls require. Permanent rejection is too rigid, since change is allowed when properly assessed and approved.
-
11 Question 11 Order list Project Management Solution
A retail company is introducing PRINCE2 Agile to coordinate a seasonal stock-management release across four delivery teams. The programme manager needs to set up the arrangement so that priorities are agreed before sprints start. Arrange the steps in the order they should be performed.
Drag the steps into the correct order, or use the arrows.
- Confirm sprint goals and capacity with each team before the sprint starts
- Run each sprint, reporting progress against the agreed priorities at the review
- Agree the programme-level priorities and the single owner who will arbitrate them across teams
- Derive a prioritised backlog for each team from the agreed programme priorities
Correct Answer:- Agree the programme-level priorities and the single owner who will arbitrate them across teams
- Derive a prioritised backlog for each team from the agreed programme priorities
- Confirm sprint goals and capacity with each team before the sprint starts
- Run each sprint, reporting progress against the agreed priorities at the review
ExplanationProgramme-level priorities and an arbitrating owner must be agreed first, since everything else depends on them. Team backlogs are then derived from those priorities. Sprint goals and capacity are confirmed before the sprint begins, and the sprint is only run once that commitment exists. Reporting against priorities happens during and after the sprint, so it cannot come first.
-
12 Question 12 Single choice PRINCE2 Agile Practitioner Overview
A financial services firm's PRINCE2 Agile project team has been asked by its governance committee to demonstrate that the project remains on track to deliver its benefits, not just its outputs. The team has been reporting only on sprint velocity and backlog burn-down. The sponsor wants evidence linking delivery to the expected benefits. Which change to the team's reporting BEST meets this requirement?
Correct Answer: AExplanationLinking completed increments to the business case's expected benefits and tracking those measures over time gives the committee evidence about benefits rather than outputs. More velocity data still reports delivery, not benefits. A list of user stories is an output listing with no benefit linkage. Removing the business case conflicts with continued business justification, which must be maintained throughout.
-
13 Question 13 Dropdown Skills and Processes
A project manager at a manufacturing company is documenting a standard practice for how a sprint review feeds into project control. The document must reflect that the review inspects delivered increments and that any decisions affecting project tolerances go to the project board. Select the correct value for each blank.
Choose the correct value for each blank.
At each sprint review, the team the delivered increment, and any proposed change that would breach a project is escalated to the project board for a decision.Correct Answer:At each sprint review, the team inspects the delivered increment, and any proposed change that would breach a project tolerance is escalated to the project board for a management decision.
ExplanationThe sprint review inspects the delivered increment, which is the empirical check that drives adaptation. Breaches of project tolerance must reach the board, so tolerance is the correct term. The decision then sits with the board as a management decision rather than being made unilaterally or silently. The distractors describe concealment or irrelevant items, which would break the controls the document is meant to describe.
-
14 Question 14 Single choice Target Audience
A county council is selecting staff to take part in a PRINCE2 Agile Practitioner course. Candidates include a recently qualified business analyst with no project responsibility, a project coordinator who schedules meetings but does not own deliverables, a project manager who leads a delivery team and owns stage outcomes, and a finance officer who approves invoices. The council wants the course to suit people who will apply the approach to live projects. Which candidate is the BEST fit for the Practitioner audience?
Correct Answer: CExplanationThe Practitioner audience is project managers and team leaders who deliver projects and make governance and tolerance decisions in live work. The project manager who owns stage outcomes fits that profile directly. The business analyst lacks project responsibility, the coordinator does not own deliverables, and the finance officer approves spending without leading delivery, so each falls short of the intended applied role.
-
15 Question 15 Multiple choice Certification Validity
A PRINCE2 Agile Practitioner holder is planning how to keep their credential active over the next three-year cycle while working on a defence contract with strict record-keeping. Which TWO actions together BEST support maintaining certification status in line with the renewal requirements? (Choose two.)
Correct Answer: D, EExplanationA dated record of continuing professional development activity linked to the membership pathway is the mechanism that maintains status. Keeping the original certification date on file lets the holder calculate when the three-year validity period ends and renewal falls due. Annual Foundation retakes are not required. Employer processes do not renew personal certification. Waiting until expiry and seeking retroactive reinstatement is not a renewal method the framework provides.
-
16 Question 16 Single choice Project Management Solution
A construction company is delivering a PRINCE2 Agile project that must hand over a building management system before a fixed opening date. The supplier proposes a fixed-price contract, while the internal team has a flexible scope within agreed tolerances. A dispute arises when the supplier wants the scope fixed upfront and the internal team wants to keep backlog items open for adaptation. The project board must decide how the project will be governed under this arrangement. What is the MOST appropriate approach?
Correct Answer: CExplanationKeeping the backlog adaptable within agreed tolerances while aligning the supplier's terms to the same stage and tolerance structure reconciles the fixed opening date with adaptive delivery. Fixing all scope upfront removes the adaptation that the internal team needs and risks handover failure. Letting the supplier set priorities independently gives away governance control. Dropping the fixed date conflicts with the stated hard constraint on the opening date.
These are 16 of the 50 questions in the full PRINCE2-Agile-Practitioner pack.
Get All 50 QuestionsGet all 50 questions & answers
Full access options for PRINCE2 PRINCE2-Agile-Practitioner
Self-study
PDF Version
- 50 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 50 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 50 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PRINCE2-Agile-Practitioner Exam (PRINCE2 Agile Practitioner Project Management) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.