PRINCE2 PRINCE2-Practitioner Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Apply (and tailor) relevant aspects of PRINCE2 processes in context
A regional logistics company is starting up a project to replace its warehouse scheduling system. The sponsor wants a fast start because a contract with the software supplier expires in six weeks. The project manager has drafted a Project Brief but has not yet agreed the tolerances for time and cost with the Project Board, and the board members have not been formally appointed. The corporate PMO requires that no funds are committed beyond the initiation stage without documented approval. Which action best demonstrates correct application of the starting up a project process in this context?
Correct Answer: CExplanationStarting up a project requires that the project management team is appointed and that the Project Brief and tolerances are agreed before the project is formally authorised. Here the PMO rule and the missing appointments mean the sponsor and proposed board must confirm roles and tolerances, which then feed into the Project Brief. Proceeding on a verbal approval breaks the governance requirement, as it leaves no documented authority for commitments. Committing to the supplier before ratification reverses the order of control and exposes funds without approval. Making the project manager the executive collapses a separation of roles that the governance structure is designed to keep.
-
2 Question 2 Single choice Apply (and tailor) relevant aspects of PRINCE2 processes in context
A public-sector agency is running a PRINCE2 project to digitise permit applications. Stage two has ended, and the project manager has produced an End Stage Report showing that the stage finished within tolerance but that a key dependency on an external data provider is now at risk. The Project Board is due to meet to approve the next stage plan. The project manager is considering whether to use the directing a project process to request authorisation for the next stage, or to proceed to the managing a stage boundary process first. Which sequence correctly reflects how the directing a project process supports the project at this point?
Correct Answer: DExplanationDirecting a project places authority with the Project Board, which makes the decision to authorise each stage or exception plan. The managing a stage boundary process prepares the End Stage Report and Next Stage Plan that the board needs. The project manager cannot authorise a stage on their own, which rules out the second option. Work Packages are issued under managing product delivery after a stage is authorised, so approving them after the stage starts reverses the control. Closing the project is not indicated because the stage finished within tolerance and continuation is still viable.
-
3 Question 3 Single choice Apply and tailorrelevant aspects of PRINCE2 themes in context
A national charity is launching a PRINCE2 project to build a donor relationship management platform. The finance director approved a business case based on projected annual fundraising uplift. Eighteen months after go-live, the benefits review shows the uplift is only 40 percent of the forecast, and a new dis-benefit has emerged: volunteer administrators spend extra hours reconciling duplicate donor records. The sponsor wants the project closed on time and within budget. The business case must remain the basis for ongoing benefits tracking. Which action best applies the business case theme in this situation?
Correct Answer: AExplanationThe business case theme requires that benefits, dis-benefits and their measurement remain under review through to and beyond project closure, so the shortfall and the emerging dis-benefit must be recorded and assessed against the investment decision. Closing the project and handing over benefits ignores the requirement that the business case is maintained. Lowering the target to hide the variance falsifies the record and removes the control that the theme exists to provide. Starting a separate project may be a valid response later, but it does not address the reporting and assessment of the original business case.
-
4 Question 4 Single choice Apply and tailorrelevant aspects of PRINCE2 themes in context
A software house is running a PRINCE2 project to deliver a customer portal for a utilities client. The client's communication plan requires that the Project Board receive a monthly progress report, but the client's operations team, which will own the portal, needs weekly updates on user-facing changes. The project manager has three project support staff and a senior supplier who is also the lead developer, which means that the senior supplier is spending much of their time in meetings. The supplier's director has asked for the team structure to be reviewed. Which change best applies the organisation theme while keeping the structure effective?
Correct Answer: CExplanationThe organisation theme requires that the project management team structure and communication management approach fit the project's needs, with roles that are clearly defined. The senior supplier is overloaded with a role that should be distinct from hands-on development, so separating it from delivery work addresses the capacity risk. The operations team's weekly needs are met through a named user representative channel, which keeps the board's monthly cadence intact. Relying on the board to cascade information fails the stated need for weekly updates. Merging executive and senior user roles breaks the principle of a balanced board that represents business, user and supplier interests. Weekly board meetings are an excessive response that does not solve the supplier's workload or the operations team's needs.
-
5 Question 5 Single choice Apply the PRINCE2 principles in context
A pharmaceutical company is running a PRINCE2 project to update its clinical trial data system. The project team has been working for four months on a plan that a regulator's audit team now says is outdated, since a new data privacy requirement has been published. The project manager argues that the team has already spent significant effort and the change is not in the original scope, so the project should continue with the current design and address the privacy requirement in a later release. The Project Board has asked for advice on how the principles apply. Which principle is most directly relevant to the decision, and what is the correct course of action?
Correct Answer: BExplanationThe continued business justification principle requires that the project is reviewed throughout its life to confirm that it remains desirable, viable and achievable. A new regulatory requirement can change that judgement, so the board must reassess and decide whether to adapt the plan. Recording a lesson does not address the current decision, and continuing unchanged ignores a material change. Managing by exception is about the board's involvement, not about whether the business case still holds, and waiting for a tolerance breach would delay a known risk. Deferring the requirement to a later release is a plan decision the board should make after reassessing justification.
-
6 Question 6 Single choice Apply the PRINCE2 principles in context
A retail bank is running a PRINCE2 project to replace its mobile app. Halfway through the project, a senior director asks the team to add a biometric login feature that the business case did not include. The project manager agrees informally and asks the developers to start, without raising a change request, arguing that the feature is small and will be a quick win. Two weeks later, the testing team reports that the feature affects the authentication module and delays a regulatory test window. Which principle has been most directly breached, and what should the project manager have done first?
Correct Answer: DExplanationThe tailor to suit the project environment principle allows the approach to be adapted, but it does not remove the control that change must be assessed and approved within the agreed governance, so the sensible step is to adjust the change control process rather than bypass it. Here the project manager should have raised the change request for assessment before any work began. Stage management is relevant to planning but does not require a new plan for a small feature that the board can approve through change control. A Product Description would be useful but does not address the decision about whether the change is accepted. Managing by exception concerns escalation triggers and would not justify starting unapproved work.
-
7 Question 7 Single choice Apply (and tailor) relevant aspects of PRINCE2 processes in context
A university IT department is running a PRINCE2 project to migrate student records to a cloud platform. The project manager has been asked to review the directing a project process because the Project Board has recently met only once during the initiation stage and has not issued any formal decisions since. The board members say they are busy and prefer to be informed by email. The project manager is considering how to tailor the process to suit the environment. Which approach is most effective and fit for purpose?
Correct Answer: AExplanationDirecting a project is a required process, and its purpose is to ensure that the board keeps authority over the project. Tailoring is allowed, but the authority for stage authorisation, change decisions and closure must be retained, so the approach must still give the board formal decision points. Agreeing scheduled short reviews with a documented decision method meets the board's constraints while keeping control. Accepting informal email decisions without formal authorisation weakens accountability and creates an audit gap. Removing directing a project breaks the process model, and transferring the board's decisions to the project manager removes the governance the process exists to provide.
-
8 Question 8 Single choice Apply and tailorrelevant aspects of PRINCE2 themes in context
A manufacturing firm is running a PRINCE2 project to implement a new production planning system across three factories. The business case was approved on the basis of reducing inventory costs by a stated amount. The benefits review plan states that inventory data will be collected monthly from the existing finance system. Three months after go-live, the finance system is replaced by a new ERP, and the old data feed is switched off without anyone updating the benefits review plan. The project manager now cannot measure the inventory benefit. Which action best applies the business case theme?
Correct Answer: AExplanationThe business case theme requires that benefits are measurable and that the benefits review plan remains valid, so when the data source changes, the plan must be updated, agreed with the board and checked for continued measurability. Assuming the benefit is achieved confuses delivery with benefit realisation. Replacing the benefit with throughput changes what the business case promised without authority. Removing the benefit to make reporting easier falsifies the record and misrepresents performance against the approved justification.
-
9 Question 9 Multiple choice Apply (and tailor) relevant aspects of PRINCE2 processes in context
A healthcare provider is running a PRINCE2 project to introduce electronic prescribing across its hospital network. The project manager is reviewing the controlling a stage process after a month of delivery, and notes that the team is producing several products without reference to the stage plan, that work package authorisation is informal, and that the highlight reports are not reaching the Project Board on time. Which TWO actions would best make the controlling a stage process effective and fit for purpose in this context? (Choose two.)
Correct Answer: A, DExplanationControlling a stage depends on authorising work through formal Work Packages that define what is to be produced and to what standard, and on monitoring progress against the stage plan so that deviations are seen early. Stopping highlight reports removes the very information the board needs to exercise control. Letting team members set their own products and deadlines disconnects the work from the plan and from accountability. Replacing the stage plan with a high-level schedule removes the baseline against which control is measured.
-
10 Question 10 Multiple choice Apply (and tailor) relevant aspects of PRINCE2 processes in context
A county council is running a PRINCE2 project to replace its citizen contact centre telephony. The project is in its initiation stage and the project manager is preparing the starting up a project process. The council's governance board has asked that the project be ready for formal authorisation, and the project manager must decide which outputs and actions are required before the project can move to the directing a project process. Which THREE actions are needed before the project is ready for the directing a project process? (Choose three.)
Correct Answer: B, C, DExplanationStarting up a project prepares the ground for directing: the project management team is confirmed, the Project Brief with an outline business case and initial tolerances is produced, and the project approach and initial Project Initiation Documentation are established. Producing a detailed product flow for every product is part of later planning and is not a prerequisite for authorisation. Starting design work before the project is authorised means delivery is occurring without the approval that directing requires.
-
11 Question 11 Multiple choice Apply and tailorrelevant aspects of PRINCE2 themes in context
A logistics firm is running a PRINCE2 project to introduce an automated route-planning tool. The business case lists three benefits: lower fuel costs, faster delivery times and improved driver satisfaction. The project manager is preparing the benefits review plan and wants to confirm that each benefit is measurable and that dis-benefits are accounted for. Which TWO of the following are the most appropriate steps for the benefits management approach in this context? (Choose two.)
Correct Answer: C, DExplanationA benefits management approach requires each benefit to have a defined measure, baseline, target and assessment timing, and dis-benefits must be identified and tracked alongside benefits. Assessing driver satisfaction from a single pre-introduction survey provides no measure of change after introduction. Assuming fuel savings occur without measurement gives the board no evidence. Removing a benefit because it is hard to measure reduces the business case without a valid decision. The correct steps are to define measurable benefits with their baselines and targets, and to plan for dis-benefits with measures.
-
12 Question 12 Multiple choice Apply and tailorrelevant aspects of PRINCE2 themes in context
A government department is running a PRINCE2 project across three regional offices to introduce a new case management system. The project team includes staff from each region, a central IT function and an external supplier. Communication has broken down, with regional users unaware of changes to training dates, and the supplier reporting that the Project Board decisions do not reach the delivery team in time. The project manager is reviewing the organisation theme. Which TWO actions would best improve the communication management approach and the team structure? (Choose two.)
Correct Answer: C, DExplanationA defined communication management approach with a matrix of audiences, content, channels and owners addresses the missed information flows, and named regional representatives give each office a clear route for information. Routing everything through the project manager creates a bottleneck and cuts regional users off from the supplier. Informal networks have already failed in this scenario. Publishing all board minutes to the whole department ignores the need to share information appropriately with defined audiences.
These are 12 of the 293 questions in the full PRINCE2-Practitioner pack.
Get All 293 QuestionsGet all 293 questions & answers
Full access options for PRINCE2 PRINCE2-Practitioner
Self-study
PDF Version
- 293 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 293 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 293 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PRINCE2-Practitioner Exam (PRINCE2 Project Management Practitioner (Version 7)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.