1 Question 1 Single choice Benefits Realization
A regional transport authority is running a programme to introduce demand-responsive bus routes. The sponsor wants the programme's benefits tracked against the programme's own business case, which currently lists a 15% reduction in journey times as a benefit. Early pilot data shows journey times falling by 15% on routes with dedicated lanes, but the wider network target is unlikely because most routes lack those lanes. The benefits owner for journey times is a service operations director who is not on the programme board. Budget for further measurement is limited and the business case must be reissued within three weeks. Which action should the programme manager take FIRST?
Correct Answer: BExplanationUnder MSP benefits management, the benefit must be defined with a baseline, a measure and a target that the accountable benefits owner accepts, and the business case must reflect realistic expectations. Pilot results from dedicated-lane routes cannot be extrapolated to the whole network, so reporting them as proof of network benefit is misleading. Dropping the benefit discards a valid outcome, and a full independent review is too costly and too slow for a three-week deadline. Restating the benefit by route type with agreed ownership addresses the gap directly and fits the constraints.
-
2 Question 2 Single choice Governance and Control
A national health programme has a Programme Board, a Business Change Group and four projects. Two projects have been reporting green status to the board, but the business change manager has evidence that the outcomes they depend on are not being prepared in operational services. The programme assurance function reports to the Senior Responsible Owner (SRO) and has limited independence. The SRO wants a quick way to restore confidence before the next funding gate, and the board members have asked for no additional reporting burden. Which action BEST strengthens programme governance?
Correct Answer: BExplanationMSP governance relies on assurance that is independent of the delivery team and reports to the board, so that optimistic reporting is challenged rather than repeated. Independent review of interdependencies and benefit readiness exposes the gap between project status and operational readiness. Signed statements from the same project managers add little independent evidence, more meetings add burden without independence, and centralising reporting under the SRO reduces rather than increases challenge. The independent review also respects the board's request to avoid extra routine reporting.
-
3 Question 3 Single choice Problem Solving
A water utility programme is upgrading billing and metering systems. During integration testing, the team finds that a data migration fault affects roughly 4% of customer accounts, and the fault has a cause that is not yet understood. The next stage gate is in six days and the programme's tolerance for schedule slippage is two weeks. A supplier offers a quick workaround that masks the errors in reports but does not correct the migrated data. The issue has been logged as a programme issue. Which action should the programme manager take NEXT?
Correct Answer: BExplanationThe issue exceeds the stage's tolerance and is affecting customer data, so the programme manager must escalate it with an impact assessment and a recommendation rather than resolve it unilaterally. Masking errors in reports hides the fault and does not meet the purpose of the change, so accepting the workaround is wrong. Excluding accounts changes scope without authority, and a full analysis of all data before any decision is too slow and ignores the immediate need for a board decision. Escalation with a recommended investigation path keeps the decision with the right authority.
-
4 Question 4 Single choice Programme Management
A housing agency has launched a programme with three tranches. The programme is being delivered in a fast-moving political environment where the policy objectives are expected to change within the next year. Funding is approved for tranche one only, and tranche two depends on evidence from tranche one. The programme manager is asked to design the programme's delivery approach. Which approach BEST reflects MSP principles for this context?
Correct Answer: BExplanationMSP is built around a vision that guides change, with the transformation delivered in tranches and adjusted as learning and external change occur. Planning tranche one in detail while keeping the later tranches at a higher level, and using evidence to shape them, suits a changing political environment. Fixing the full scope at the start ignores the expected policy change, delaying all planning leaves the programme without direction, and running tranches as independent projects loses the programme-level coordination of benefits and dependencies.
-
5 Question 5 Single choice Resource Management
A manufacturing programme has a shared pool of ten senior process engineers. Three of its four projects need the same specialists in the same quarter. The programme budget is fixed, and agency contractors are available at a much higher daily rate but can only work on routine tasks. One project's critical path depends on a specialist test rig that is only available after a six-week manufacturing outage. The programme manager must allocate the scarce engineers to maximise overall benefit delivery without breaching the fixed budget. What should the programme manager do FIRST?
Correct Answer: BExplanationThe programme manager first needs a prioritised view of resource demand based on benefit contribution and dependencies, then an agreed allocation with the board, because the decision affects multiple projects and the fixed budget. Hiring agency contractors breaches the budget constraint and cannot cover specialist tasks. Arbitrary effort cuts ignore the real demand, and rescheduling the rig outage is outside the programme manager's control and is not a first step.
-
6 Question 6 Single choice Risk and Issue Management
A logistics programme has identified a risk that a key carrier may withdraw from a framework agreement, which would affect service levels for two benefits. The risk owner has rated the probability as medium and impact as high. The programme has a risk appetite statement that is set by the Programme Board. The carrier has given informal signals that it is reviewing its commercial position, but no formal notice has been received. The programme manager wants to ensure the risk is managed proportionately. Which action BEST meets MSP risk management principles?
Correct Answer: BExplanationUnder MSP, risks are managed proactively with defined responses, triggers and owners, and they are assessed against the risk appetite set by the board. Recording contingency options and early warning triggers keeps the programme ready without premature action. Closing the risk because no formal notice exists ignores credible early signals. Converting it to an issue without authority and transferring it through contract changes without consultation both bypass the governance the scenario describes.
-
7 Question 7 Single choice Stakeholder Engagement
A city council programme to redevelop a waterfront area involves a sponsor who wants rapid approval, a residents' association that opposes the scheme, a development partner, and local businesses that are split in their views. The programme manager has been told that the residents' association is 'unreasonable' by the sponsor. The next consultation milestone is in eight weeks, and the programme has a legal duty to consider consultation responses. Which action should the programme manager take to BEST engage stakeholders?
Correct Answer: BExplanationMSP stakeholder engagement starts with analysing stakeholders' interests, influence and attitudes, and then tailoring two-way engagement to each group. Given the legal duty to consider consultation responses, genuine dialogue with the residents' association is required, not limited notices. Limiting communication conflicts with that duty, delegating engagement to the development partner compromises neutrality, and framing objections as misinformation damages trust and may not be accurate.
-
8 Question 8 Single choice Tailoring
A government department is adopting MSP for a programme of shared services consolidation. The department already runs a mature portfolio office and uses a strict stage-gate life cycle for all major investments. The programme is short-duration (nine months), has a small team of six, and its benefits are mostly cost reduction that can be measured in the department's finance system. Assurance and governance requirements are set centrally and cannot be waived. Which approach to tailoring the MSP method is MOST appropriate?
Correct Answer: DExplanationMSP is intended to be tailored to context, but mandatory central governance and assurance requirements that cannot be waived must be preserved. Scaling the roles, documents and review frequency to a six-person, nine-month programme with measurable cost benefits is the proportionate response. Applying the full method ignores the scale constraint, removing governance breaches the stated mandatory requirements, and replacing MSP with portfolio standards abandons the method rather than tailoring it.
-
9 Question 9 Order list Benefits Realization
A programme manager needs to establish a benefits realization approach for a new digital citizen services programme. The benefits include reduced call volumes and faster case closure, and both must be measured against a baseline. Place the following steps in the correct order. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Track benefit measures and report progress against the target profile to the Programme Board.
- Define the benefit profile, including when each benefit is expected to be realized.
- Establish the baseline measures for each benefit before any change is delivered.
- Agree the benefit owners and confirm their acceptance of the measures and targets.
Correct Answer:- Define the benefit profile, including when each benefit is expected to be realized.
- Establish the baseline measures for each benefit before any change is delivered.
- Agree the benefit owners and confirm their acceptance of the measures and targets.
- Track benefit measures and report progress against the target profile to the Programme Board.
ExplanationIn MSP benefits management, the benefit profile and timing are defined first, then baselines are established before change so that improvements can be measured. Benefit owners then accept the measures and targets, and only after that is ongoing tracking and reporting to the board meaningful. Defining the profile before baselining is necessary, since the baseline must be set for the measures that the profile identifies. Tracking must come last because it depends on a confirmed baseline and owner acceptance.
-
10 Question 10 Single choice Governance and Control
A programme manager is setting up the programme's governance structure for a transport infrastructure programme. Match each governance element to the role that is primarily responsible for it.
1. Ensuring the programme remains aligned with the business case and approving the programme's tolerances
2. Providing independent challenge on the quality and readiness of programme delivery
3. Day-to-day coordination of programme tranches, dependencies and the programme plan
Targets: Programme Board; Programme Assurance; Programme ManagerCorrect Answer: BExplanationThe Programme Board holds accountability for the business case and approves tolerances, so it owns the alignment and tolerance decision. Programme Assurance provides independent challenge on quality and readiness, so it is the correct match for the second element. The Programme Manager coordinates day-to-day delivery, tranches and dependencies. The other mappings assign accountability or independence to the wrong roles, since assurance must not be the party setting tolerances and the manager is not the board.
-
11 Question 11 Dropdown Problem Solving
Choose the best values for the blanks. Choose the correct value for each blank.
Choose the correct value for each blank.
A programme issue log records that an unresolved supplier dependency has moved past its tolerance and affects two benefits. The programme manager must record the issue so that the Programme Board can make a decision on it. In the issue record, the issue should be assigned to and the recommended escalation route should be .Correct Answer:A programme issue log records that an unresolved supplier dependency has moved past its tolerance and affects two benefits. The programme manager must record the issue so that the Programme Board can make a decision on it. In the issue record, the issue should be assigned to the programme manager with an assigned owner and the recommended escalation route should be escalate to the Programme Board with an impact assessment.
ExplanationAn issue that has exceeded tolerance must be recorded with an appropriate owner and escalated to the board with an impact assessment, which is what allows a decision to be made. Assigning it to the project manager keeps it inside a stage that cannot resolve a programme-level impact. Reclassifying it as a risk ignores that the issue has already occurred, and assigning it to the supplier's account manager removes programme control over the response.
These are 11 of the 75 questions in the full MSP-Practitioner pack.
Get All 75 QuestionsGet all 75 questions & answers
Full access options for PRINCE2 MSP-Practitioner
Self-study
PDF Version
- 75 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 75 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 75 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the MSP-Practitioner Exam (MSP Practitioner, 5th edition Exam) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.