1 Question 1 Single choice Defect Management
A test manager at a payments company runs a defect triage board. A severity-1 defect was found in production that corrupts ledger totals only for transactions in a specific currency. The business has a regulatory obligation to report confirmed data-integrity incidents within 24 hours. The defect tracking system is configured so that a defect can only move to Closed after a retest is passed, and the triage board meets only twice a week. Which action should the test manager take FIRST to balance defect lifecycle discipline with the regulatory deadline?
Correct Answer: AExplanationThe regulatory 24-hour window makes a severity-1 integrity defect an exception to the twice-weekly cycle, so an out-of-cycle triage with release and compliance owners is the right first step. Reclassifying to severity 3 hides the real impact and would misstate the defect's business risk. Waiting for the scheduled board can breach the reporting deadline. Closing the defect before a retest is passed violates the lifecycle rule the tool enforces, so the defect cannot be closed that way anyway.
-
2 Question 2 Multiple choice Defect Management
A test manager is defining defect metrics for a product line that releases monthly. Leadership wants metrics that show whether the defect process is improving rather than merely producing large counts. The test manager must avoid metrics that can be gamed by testers or developers. Which TWO metrics are most suitable for this purpose? (Choose two.)
Correct Answer: C, EExplanationDefect detection percentage compares defects found before release with those escaping to production, which shows whether the test process is effective across releases. Average age of open high-severity defects reflects resolution responsiveness without rewarding volume. Defects per tester invites inflated logging, rejection counts can discourage reporting, and closure totals reward closing easy defects rather than measuring improvement.
-
3 Question 3 Dropdown Improving the Testing Process
A test manager at an insurance firm is assessing testing maturity using TMMi. The assessment team has evidence that test planning and test monitoring are performed for every project, but test design techniques are applied inconsistently and there is no organisation-wide test policy. The manager must report the current maturity level and the level the organisation must reach next. Select the correct value for each blank.
Choose the correct value for each blank.
The organisation is assessed at TMMi level . Its next target level, where a organisation-wide test policy and test strategy must be established, is level .Correct Answer:The organisation is assessed at TMMi level 2. Its next target level, where a organisation-wide test policy and test strategy must be established, is level 3.
ExplanationManaged level 2 requires basic test planning, monitoring and a test policy with testing practices repeatable across projects, and the evidence shows planning and monitoring exist but no organisation-wide policy, so level 2 is the current rating. The next level, defined level 3, is where an organisation-wide test policy and test strategy and standardised test design techniques are established. Choosing level 1 ignores that planning and monitoring are already in place, while levels 4 and 5 require measured and optimised processes far beyond the evidence.
-
4 Question 4 Order list Reviews
A test manager must introduce formal inspections for a safety-critical requirements specification that has been changed significantly after an initial informal walkthrough. The organisation requires that every review follows a documented process and that defects are tracked to closure before sign-off. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Distribute the specification and checklists so reviewers can prepare individually
- Have the author rework the specification to resolve each logged defect
- Have the moderator plan the inspection, select reviewers and define entry and exit criteria
- Hold the inspection meeting where reviewers log and discuss the defects they found during individual preparation
- Verify the rework against the exit criteria and record the review as complete
Correct Answer:- Hold the inspection meeting where reviewers log and discuss the defects they found during individual preparation
- Have the moderator plan the inspection, select reviewers and define entry and exit criteria
- Distribute the specification and checklists so reviewers can prepare individually
- Have the author rework the specification to resolve each logged defect
- Verify the rework against the exit criteria and record the review as complete
ExplanationA formal inspection begins with planning by the moderator, which sets entry and exit criteria and selects reviewers. Distributing the document with checklists allows individual preparation before the meeting. The meeting then logs defects, the author reworks them, and the moderator verifies exit criteria before completing the review. Holding the meeting before preparation would make the discussion unproductive, and sign-off before rework and verification would break the stated traceability requirement.
-
5 Question 5 Single choice People Skills - Team Composition
A test manager is forming a testing team for a new mobile banking application. The team already includes two experienced manual testers and one automation engineer. The application will be built with a new framework the team has never used, and the product owner wants fast feedback on each sprint. The test manager has budget for one additional hire and must also keep the two manual testers engaged, as one has expressed concern about being replaced by automation. Which hire best meets these needs?
Correct Answer: AExplanationThe team lacks experience with the new framework and needs continuous sprint feedback, while one manual tester feels threatened by automation, so a domain-expert exploratory tester who can coach the manual staff and support sprint testing fits all constraints. A second automation engineer in the existing tool duplicates skills and worsens the morale concern. A performance specialist addresses a later, unstated need rather than the sprint feedback requirement. A trainee does not add the testing capability required within the single budgeted hire.
-
6 Question 6 Drag and drop People Skills - Team Composition
A test manager is preparing communication for a distributed test organisation before a major release. Different stakeholders need different information at different levels of detail. Match each communication need to the mechanism that best serves it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Offshore testers who are new to the product and need to understand the release scopeDevelopment team that must fix failing automated checks before the next nightly buildExecutive sponsor who needs a go or no-go recommendation based on residual release riskDetailed monthly percentage breakdown of test cases executed by each testerStructured walkthrough of the test plan and entry criteriaConcise risk-based test status summary with a clear recommendationDirect notification of failing test cases with links to logsCorrect Answer:- Executive sponsor who needs a go or no-go recommendation based on residual release risk → Concise risk-based test status summary with a clear recommendation
- Development team that must fix failing automated checks before the next nightly build → Direct notification of failing test cases with links to logs
- Offshore testers who are new to the product and need to understand the release scope → Structured walkthrough of the test plan and entry criteria
ExplanationExecutives need an executive summary that frames risk and a recommendation rather than volume data. Developers need immediate, actionable failure information linked to logs so they can act before the nightly build. New team members benefit from a structured walkthrough of scope and entry criteria. The monthly execution breakdown is detailed reporting that does not fit any of these needs and would not support the decisions each stakeholder must make.
-
7 Question 7 Single choice Reviews
A test manager is planning a review of a 200-page non-functional requirements document for a government health system. Several stakeholders from different departments must approve the document, and some of them are in different time zones. Past experience shows that unstructured email review produced conflicting comments and missed defects. The organisation requires traceable defect logs and an independent check of the review's results. Which review type is most appropriate?
Correct Answer: AExplanationA formal inspection provides defined roles, checklists, a moderator, and recorded defect logs, which meets the traceability and independent-check requirements, while individual asynchronous preparation accommodates time zones. Informal email review is the approach that already produced conflicting and missed defects. A walkthrough is author-led and does not meet the independence requirement. A technical review limited to developers excludes the stakeholders who must approve the document.
-
8 Question 8 Single choice Test Tools and Automation
A test manager is evaluating a commercial test automation tool for a team of 12 testers who maintain a large regression suite against a web application. Pilot results show that 45 percent of automation effort goes to repairing scripts whenever the UI layout changes, and the application changes weekly. The company's policy forbids storing test data outside the corporate network, and the budget is limited. Which action should the test manager take to address the maintenance problem before scaling the tool?
Correct Answer: BExplanationMaintenance cost driven by UI changes is addressed by separating test logic from UI locators through an abstraction layer such as page objects, with stable locators agreed with developers, and validating the approach in a pilot before scaling. Adding engineers increases cost without reducing the cause. Cloud-hosted storage violates the stated data residency policy. Recording more scripts multiplies the number of scripts that break when the UI changes.
-
9 Question 9 Dropdown Test Tools and Automation
A test manager is configuring an automated regression job so that failing tests are reported without blocking the release pipeline during a period when a known intermittent defect affects the login page. The team uses a command-line test runner that supports selecting tests by tag and marking tests as expected failures. Select the correct value for each blank in the configuration note.
Choose the correct value for each blank.
Tag the login tests with and set the pipeline to run them in a separate stage that does not fail the build, while the defect remains open against the test runner's annotation.Correct Answer:Tag the login tests with known-issue and set the pipeline to run them in a separate stage that does not fail the build, while the defect remains open against the test runner's expected-failure annotation.
ExplanationTagging the affected tests with a known-issue tag lets the pipeline isolate them into a separate stage that does not block the build, and an expected-failure annotation records the open defect without masking it as a pass. Smoke and regression tags describe test purpose rather than known problems. Skip hides the tests entirely so the defect is no longer visible, retry only reruns them, and timeout is unrelated to recording a known failure.
-
10 Question 10 Single choice Testing Process
A test manager at a logistics company is adapting the testing process for a new subscription product that will be delivered through two-week sprints. The product owner wants risk-based testing so that testing effort is focused on the areas most likely to affect revenue. The current process applies the same full regression suite to every release regardless of what changed. Which step should the test manager take FIRST?
Correct Answer: DExplanationRisk-based testing starts with identifying and ranking risks, meaning the likelihood and impact of failure on revenue-critical features, so a risk workshop with the product owner and technical staff must come first. Removing the regression suite without a risk basis discards coverage without justification. Adding testers keeps the process unchanged and ignores the stated goal. Moving testing after the sprint conflicts with the two-week feedback cycle.
-
11 Question 11 Order list Testing Process
A test manager is aligning the test process for an organisation that has moved from a waterfall model to Scrum. The manager must define how testing fits into each sprint. Arrange the steps in the correct order in which they should be introduced during a sprint.
Drag the steps into the correct order, or use the arrows.
- Run the regression and exploratory tests against the sprint increment
- Report test results and residual risks at the sprint review
- Design and automate tests for the selected stories as they are developed
- Agree the sprint acceptance criteria with the product owner during sprint planning
- Assess the sprint's test process and record improvements in the retrospective
Correct Answer:- Agree the sprint acceptance criteria with the product owner during sprint planning
- Design and automate tests for the selected stories as they are developed
- Run the regression and exploratory tests against the sprint increment
- Report test results and residual risks at the sprint review
- Assess the sprint's test process and record improvements in the retrospective
ExplanationTesting in Scrum begins with agreeing acceptance criteria during sprint planning so that testers know what must be verified. Test design and automation proceed alongside development of the selected stories. Regression and exploratory testing then run against the increment before the sprint review, where results and residual risks are reported. The retrospective is where process improvements are recorded, so it closes the sequence.
-
12 Question 12 Multiple choice Testing Process
A test manager is optimising the testing process for a financial reporting system that must satisfy audit requirements and a fixed quarterly release date. The current process has high test execution cost and frequent late defects. Which TWO actions best align testing with organisational goals while respecting the audit and timeline constraints? (Choose two.)
Correct Answer: C, DExplanationEarly static analysis and requirement reviews move defect detection upstream, reducing the cost of late defects, and using the audit-required traceability to prioritise tests by criticality optimises effort without breaking audit obligations. Removing the traceability matrix violates the stated audit requirement. Dropping non-functional testing ignores a quality area that should be scoped rather than eliminated. Concentrating all execution into a final window increases the risk of late defects.
-
13 Question 13 Single choice Improving the Testing Process
A test manager at a retail company wants to improve the testing process using TPI Next. The assessment finds that most test cases are designed by the same two senior testers, and the company wants to reduce the risk of key-person dependency before a planned expansion to three new product lines. Management also requires that improvements be introduced in controlled steps with measurable outcomes. Which improvement action is most appropriate as the next step?
Correct Answer: DExplanationTPI Next improvements are introduced in controlled steps with measurable outcomes, so piloting a standard design technique and checklist in one product line, measuring the result, and then extending it addresses key-person dependency in a controlled way. A simultaneous company-wide automation rollout breaks the controlled-step requirement. Copying requirements verbatim is not test design and does not reduce dependency on design skill. Assigning the same two testers to all lines deepens the key-person risk the manager is trying to reduce.
These are 13 of the 64 questions in the full CTAL-TM_Syll2012 pack.
Get All 64 QuestionsGet all 64 questions & answers
Full access options for iSQI CTAL-TM_Syll2012
Self-study
PDF Version
- 64 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 64 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 64 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CTAL-TM_Syll2012 Exam (ISTQB Certified Tester Advanced Level - Test Manager) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.