- 64 Actual Exam Questions
- Compatible with all Devices
- Printable Format
- No Download Limits
- 90 Days Free Updates
Get All ISTQB Certified Tester Advanced Level - Test Manager Exam Questions with Validated Answers
| Vendor: | iSQI |
|---|---|
| Exam Code: | CTAL-TM_Syll2012 |
| Exam Name: | ISTQB Certified Tester Advanced Level - Test Manager |
| Exam Questions: | 64 |
| Last Updated: | January 6, 2026 |
| Related Certifications: | ISTQB International Software Testing Qualifications |
| Exam Tags: | Advanced Software DeveloperTechnical Test AnalystTest Engineer |
Looking for a hassle-free way to pass the iSQI ISTQB Certified Tester Advanced Level - Test Manager exam? DumpsProvider provides the most reliable Dumps Questions and Answers, designed by iSQI certified experts to help you succeed in record time. Available in both PDF and Online Practice Test formats, our study materials cover every major exam topic, making it possible for you to pass potentially within just one day!
DumpsProvider is a leading provider of high-quality exam dumps, trusted by professionals worldwide. Our iSQI CTAL-TM_Syll2012 exam questions give you the knowledge and confidence needed to succeed on the first attempt.
Train with our iSQI CTAL-TM_Syll2012 exam practice tests, which simulate the actual exam environment. This real-test experience helps you get familiar with the format and timing of the exam, ensuring you're 100% prepared for exam day.
Your success is our commitment! That's why DumpsProvider offers a 100% money-back guarantee. If you don’t pass the iSQI CTAL-TM_Syll2012 exam, we’ll refund your payment within 24 hours no questions asked.
Don’t waste time with unreliable exam prep resources. Get started with DumpsProvider’s iSQI CTAL-TM_Syll2012 exam dumps today and achieve your certification effortlessly!
Which of the following statements about the STEP test process improvement model is true? K2 1 credit
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:
. Availability of re-usable test systems and documentation from previous, similar projects
2. Unexpected timing of components arrival
3. Stability of the integration test team (no turnover)
4. Many and geographically distributed sub-teams
Which of the following statements is true?
K2 1 credit
You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.
At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.
Which of the following statements is true in this context?
K4 3 credits
Which of the following factors could negatively influence a review?
K2 1 credit
In the next two months some new features will be constantly added to new releases of a project you are working on as Test Manager.
You have identified as one of the main project risks, that the requirements specification will still be incomplete when your team starts the test design and implementation phase.
Some requirements will most likely be completed too late to allow a proper test preparation. You and your test team have already worked on several similar past projects in the same organization.
Which one of the following options would you expect to be the most effective at mitigating this risk?
K4 3 credits