Exam Information
Free practice questions with explanations
iSQI CTFL-PT_D Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 16
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Fundamentals of Testing
A fintech company releases a mobile banking app every two weeks. The product owner asks the test team to justify testing effort in a sprint review, stating that the team already achieves 100% statement coverage in its automated suite and therefore 'testing is complete.' The regulator requires evidence that the most serious defects affecting customer funds are found before release. Which response best reflects the fundamental principles of testing?
Correct Answer: BExplanationThe key principle is that testing can show the presence of defects but cannot prove their absence. Statement coverage measures which code was executed, not whether the requirements or risks were correctly exercised, so it cannot establish completeness. Focusing evidence on funds-related failures aligns with the regulator's requirement and with the principle of risk-based testing. The option claiming 100% coverage proves absence confuses coverage with correctness. The claim that passing regression proves full correctness ignores the limits of the test set. Exploratory testing after freezing the release candidate delays discovery and conflicts with the goal of finding serious defects before release.
-
2 Question 2 Order list Managing the Test Activities
A retail company must estimate test effort for a new checkout module using a three-point (PERT-style) approach agreed with the test manager. The estimates for the sub-tasks are available from the team but have not yet been combined. Arrange the steps in the order they must be performed.
Drag the steps into the correct order, or use the arrows.
- Calculate the weighted expected effort for each task from the three estimates
- Sum the expected effort values and add a contingency reserve for the schedule
- Obtain optimistic, most likely and pessimistic size estimates for each task
- Record the resulting effort estimate and its assumptions in the test plan
- Identify the test tasks and their work breakdown for the checkout module
Correct Answer:- Identify the test tasks and their work breakdown for the checkout module
- Obtain optimistic, most likely and pessimistic size estimates for each task
- Calculate the weighted expected effort for each task from the three estimates
- Sum the expected effort values and add a contingency reserve for the schedule
- Record the resulting effort estimate and its assumptions in the test plan
ExplanationA three-point estimate needs defined tasks first so that each has optimistic, most likely and pessimistic values to work from. The expected value is then computed for each task with the weighted formula, after which the task values are summed and a contingency is applied. Recording the estimate with its assumptions in the test plan comes last so that it reflects the final figures. Attempting to compute weighted values before the tasks are broken down would leave the inputs undefined, and adding contingency before summing would apply it to the wrong base.
-
3 Question 3 Single choice Static Testing
A healthcare software team is reviewing a 4,000-line module written in C that will run inside a medical device. The team wants to detect possible null-pointer dereferences and uninitialized variable use before any dynamic test execution, using static analysis. The review lead also wants to avoid overwhelming developers with false positives so that real warnings are acted upon. Which action is the best first step?
Correct Answer: AExplanationStatic analysis is performed on code without executing it, and tailoring the enabled checks to the defect classes of concern, such as null dereference and uninitialized variables, keeps the output focused and limits false positives. Reviewing that targeted output first makes the results actionable for developers. Running the full default rule set produces broad noise that the constraint about avoiding overwhelming developers rules out. Replacing the tool with a manual checklist abandons the automated static analysis the team wants. Runtime memory checking is dynamic testing, which the scenario explicitly sets aside in favour of pre-execution analysis.
-
4 Question 4 Multiple choice Test Analysis and Design
A government benefits portal calculates eligibility from income bands and household size. Specifications define three income bands and a household-size rule where households of 1 to 4 members use one threshold and households of 5 or more use another. The team must design black-box test cases with the fewest tests that still cover every equivalence partition and boundary. Which two techniques should be applied? (Choose two.)
Correct Answer: B, CExplanationEquivalence partitioning groups the income bands and household-size ranges into classes, giving one representative per class, while boundary value analysis targets the edges of those classes such as the thresholds and the transition between 4 and 5 members. Together they satisfy the requirement for minimal tests covering partitions and boundaries. Statement and branch coverage are white-box measures that depend on the code structure, which the scenario excludes by requiring black-box design. Error guessing is an experience-based technique that is not derived from the specification, so it does not provide the systematic coverage requested.
-
5 Question 5 Drag and drop Test Tools
A logistics company's test team is selecting tools for a regression programme. Each requirement below must be met by one tool category. Match each requirement to the tool category that best meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Store and version the requirement-to-test traceability and test case documentsDrive the web shipment-booking screens through a browser to verify end-to-end user flowsMeasure response time of the booking API under 500 concurrent virtual usersStatic analysis toolPerformance testing toolTest execution toolConfiguration management toolTest management toolCorrect Answer:- Drive the web shipment-booking screens through a browser to verify end-to-end user flows → Test execution tool
- Store and version the requirement-to-test traceability and test case documents → Test management tool
- Measure response time of the booking API under 500 concurrent virtual users → Performance testing tool
ExplanationBrowser-driven end-to-end flows are the purpose of a test execution tool that replays scripted interactions against the user interface. Traceability and test case storage belong to a test management tool, which records requirements linkage and test artefacts. Measuring response time under concurrent load is the function of a performance testing tool that generates virtual users. Static analysis tools examine code without executing it, so they do not drive browser flows, and configuration management tools control versions of items rather than measuring behaviour under load, so both extras are correctly excluded.
-
6 Question 6 Dropdown Testing Throughout the Software Development Lifecycle
A team practising DevOps runs unit, integration and acceptance tests in a pipeline. The pipeline must stop and report failure when the unit test stage fails, and it must run the acceptance stage only after integration succeeds. Complete the pipeline stage definition by selecting the correct value for each blank.
Choose the correct value for each blank.
stages: needs: on_failure:Correct Answer:stages: unit-tests needs: integration-tests on_failure: stop-pipeline
ExplanationIn a DevOps pipeline, dependencies between stages determine ordering, and a failing stage that should block progression must halt the run so defects do not reach later environments. The acceptance stage needs integration to have succeeded, so integration-tests is the dependency to declare. The stage that begins the sequence is the one whose failure must stop the pipeline, which is the unit test stage named as the first stage. Continuing or skipping after a failure would let defective builds proceed, and retrying indefinitely does not resolve a genuine defect.
-
7 Question 7 Single choice Testing Throughout the Software Development Lifecycle
A team using Scrum delivers an increment every sprint for a logistics platform. Automated regression tests take 6 hours and run only nightly, so defects introduced on a given day are often discovered the following morning, by which time developers have moved on. The team wants to shorten feedback without weakening coverage, and the test suite cannot be redesigned in the sprint. Which action is the best choice?
Correct Answer: BExplanationRunning a fast, risk-selected subset on every commit gives developers feedback while the change is still fresh, and the full nightly suite preserves coverage, which matches the constraint of not weakening coverage. Moving testing to a late phase reproduces the delay the team wants to remove and conflicts with iterative delivery. Removing automation sacrifices repeatable regression coverage and would not scale across sprints. Increasing parallelism is a valid optimisation, but the scenario rules out any change that would not reduce feedback time enough, and the stem asks for the best choice rather than the option that only halves runtime while still feeding back overnight.
-
8 Question 8 Order list Test Analysis and Design
A team is applying a decision table to test a loan approval rule that depends on credit score band, employment status and loan amount, with an approve or refer outcome. The business analyst has supplied the conditions and actions. Arrange the steps in the order they must be performed.
Drag the steps into the correct order, or use the arrows.
- Enumerate all combinations of condition values to form the rule columns
- List every condition and its possible values from the loan approval specification
- Execute the test cases and compare the actual outcome with the expected action
- Determine the expected action for each rule and remove infeasible combinations
- Derive one test case per remaining rule and assign concrete input values
Correct Answer:- List every condition and its possible values from the loan approval specification
- Enumerate all combinations of condition values to form the rule columns
- Determine the expected action for each rule and remove infeasible combinations
- Derive one test case per remaining rule and assign concrete input values
- Execute the test cases and compare the actual outcome with the expected action
ExplanationA decision table is built by first identifying the conditions and their values, then forming the combinations that make up the rule columns. Each column's expected action is determined and infeasible combinations are removed before deriving test cases with concrete inputs. Execution and comparison come last. Deriving test inputs before the rules are complete would leave gaps in coverage, and attempting to determine actions before combinations exist has no defined basis.
-
9 Question 9 Single choice Managing the Test Activities
A test manager at an insurance company must report test progress for a claims system release. Test execution is 60% complete, but 35 of the 120 planned test cases remain blocked by a defect in a dependent service that the development team has not scheduled to fix. The steering group wants to know whether the release is on track and which information to include in the status report. Which content best supports an informed release decision?
Correct Answer: CExplanationA useful status report shows the counts of executed, passed, failed and blocked tests, identifies the blocking defect and its effect on release risk, which is what the steering group needs for an informed decision. The percentage complete alone hides the 35 blocked cases, and assuming the remaining tests are only regression is an unsupported claim. Total defect counts without linkage to test coverage do not indicate release readiness, and per-test effort hours answer a different question about productivity rather than readiness.
-
10 Question 10 Multiple choice Fundamentals of Testing
A university ran a pilot test of a student enrolment system before its launch. The project board asks why the test team spends time on early reviews of requirements instead of waiting until the system is built. Which two statements describe the benefits of early testing activities that the team should give? (Choose two.)
Correct Answer: B, DExplanationDefects introduced in requirements typically cost less to fix when caught early, because the correction is limited to documents rather than code, rework and retesting. Early test design also checks that requirements are testable, which exposes vagueness before development starts. The claim that early testing guarantees no defects is false, since testing cannot prove absence. Removing later test execution is incorrect, because system and acceptance testing still verify the integrated product. Reviewing requirements early does reveal ambiguities, but the scenario's emphasis on test activities rather than reviews of the requirements themselves makes testability the more directly tested benefit here.
-
11 Question 11 Dropdown Test Tools
A performance test team at an e-commerce company runs a load test with a tool that uses a command-line runner. The runner must execute a scenario file with 200 virtual users for a 10-minute duration and write results to a report folder. Complete the command by selecting the correct value for each blank.
Choose the correct value for each blank.
loadrunner run --users --durationCorrect Answer:loadrunner run checkout.scenario --users 200 --duration 10m
ExplanationThe runner takes the scenario file as its first argument, the number of virtual users is set to 200 as the scenario requires, and the duration uses the minute suffix to represent 10 minutes. Passing a report or log file in place of the scenario would give the runner no workload definition. Twenty or two thousand users do not match the requirement. Seconds or hours would give the wrong duration, and 600ms represents a sub-second value rather than ten minutes.
-
12 Question 12 Single choice Test Analysis and Design
A team testing a travel booking website uses exploratory testing with session charters after formal test design. Management questions whether this is an acceptable use of the team's time when the requirements are fully documented. The team has limited time for a release that includes a new payment flow with several unanticipated interactions. Which justification for exploratory testing is most accurate?
Correct Answer: AExplanationExploratory testing is an experience-based approach in which design, execution and learning happen concurrently, so testers can follow up on unexpected behaviour that scripted cases do not anticipate, such as unplanned payment flow interactions. It complements rather than replaces documented test design. Claiming it replaces design overstates its role, and it is not a coverage-measurement method. Saying it is most useful when requirements are complete misreads its strength, which is value when behaviour is uncertain or under-specified.
-
13 Question 13 Single choice Test Tools
A software house is implementing a test automation framework for a web application that the team wants to maintain over several years. The tool must support keyword-driven tests written by business analysts and must keep scripts maintainable when user-interface locators change. The budget does not allow licensing an expensive commercial product. Which decision best meets these constraints?
Correct Answer: BExplanationA keyword-driven framework lets analysts write tests using high-level keywords while locators are stored centrally, so a change to a user-interface element requires updating only the repository rather than every script, which satisfies both maintainability and accessibility for non-programmers. Recorded scripts break when locators change and are hard to maintain. Static analysis of style does not address locator maintenance or support analyst-written tests. Hard-coded locators scatter changes across all scripts, which conflicts with the maintainability requirement.
-
14 Question 14 Drag and drop Static Testing
A review team is preparing for three different static testing activities on a payroll module specification and its code. Each activity below must be matched to the review type that best fits its purpose. Match each activity to the review type that best meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Lead a structured inspection with defined roles, entry criteria and recorded defect metrics for the moduleWalk through the specification with stakeholders to gain understanding and collect informal commentsHave the author present the code to peers to share knowledge and detect obvious issuesWalkthroughDynamic analysisFormal inspectionScripted executionInformal reviewCorrect Answer:- Walk through the specification with stakeholders to gain understanding and collect informal comments → Informal review
- Lead a structured inspection with defined roles, entry criteria and recorded defect metrics for the module → Formal inspection
- Have the author present the code to peers to share knowledge and detect obvious issues → Walkthrough
ExplanationA walkthrough is led by the author to inform peers and find issues informally, which fits the presenting-to-peers activity. Formal inspection uses defined roles, entry criteria and recorded metrics, matching the structured inspection described. An informal review is the lightest activity, with minimal process, and fits the informal stakeholder discussion. Dynamic analysis and scripted execution both require running the code, which static review does not do, so they are correctly excluded from the targets.
-
15 Question 15 Single choice Testing Throughout the Software Development Lifecycle
A company is migrating a legacy monolith to microservices in incremental releases. The release manager wants to confirm that changes to one service do not break integrations with others, but the integration environment is shared and costly to reset, and the teams deploy several times a day. Which testing approach best meets the constraints?
Correct Answer: DExplanationConsumer-driven contract tests verify each service's interactions with its consumers within each pipeline, catching integration breakage early without requiring the costly shared environment to be reset for every deployment, which suits frequent releases. Quarterly end-to-end testing is too infrequent for several deployments a day. Isolated unit tests cannot detect integration changes, and relying on production monitoring defers detection to users. Duplicating the full production environment for every team is prohibitively expensive, which the cost constraint rules out.
-
16 Question 16 Single choice Managing the Test Activities
A test lead estimates effort for a mobile app regression cycle using past metrics. The team historically completes about 18 test cases per tester per day, with planning-based estimation showing 240 cases to execute. A second estimate uses the work breakdown with three tester-days per functional area across 8 areas. Management wants the more defensible estimate for budget approval, and the team has no reliable data on this specific build. Which estimating approach should the lead choose?
Correct Answer: CExplanationHistorical productivity data is a proven basis for estimation when it comes from comparable cycles, and the stated history of 18 cases per tester per day with 240 cases provides a quantified, defensible figure. The work breakdown relies on an unvalidated assumption of three tester-days per area with no data for this build, which is weaker support for approval. Averaging does not improve accuracy when one input is poorly grounded, and deferring the estimate fails the budget approval requirement.
These are 16 of the 40 questions in the full CTFL-PT_D pack.
Get All 40 QuestionsGet all 40 questions & answers
Full access options for iSQI CTFL-PT_D
Self-study
PDF Version
- 40 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 40 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 40 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CTFL-PT_D Exam (ISTQB Certified Tester Foundation Level - Specialist Performance Testing) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.