Exam Information
Free practice questions with explanations
iSQI CTFL_Syll2018 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 10
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Fundamentals of Testing
A payments company is preparing a release of its checkout module. The product owner asks the test lead to explain why exhaustive testing of every input combination is not feasible. The module has 12 input fields, each accepting around 40 valid and invalid values, and the regression cycle must finish within a two-day window before the release freeze. The test lead wants to justify a risk-based approach that focuses effort where failures would cost the most. Which principle should the test lead cite as the basis for this approach?
Correct Answer: AExplanationExhaustive testing of 12 fields with around 40 values each is impossible within two days, and the ISTQB principle that testing shows the presence of defects, not their absence, supports directing effort toward areas where failures have the greatest impact. Defect clustering is a real principle, but it does not justify the cost-driven prioritisation the scenario asks for; it is an input to prioritisation rather than the reason exhaustive testing is infeasible. Early testing is a principle about timing rather than scope, and the absence-of-errors fallacy argues against stopping testing on the basis of zero known defects, so it is the opposite of what the lead needs.
-
2 Question 2 Single choice Managing the Test Activities
A healthcare software vendor is planning a regression test effort for a patient scheduling system. The project has a fixed budget and a firm go-live date. The test manager identifies that the highest product risk lies in the integration with an external insurance eligibility service, which the team does not control and which is scheduled for a vendor upgrade two weeks before go-live. Regulatory rules require that any unplanned change to the eligibility integration be formally assessed before release. Which action should the test manager take FIRST to address this risk within the test plan?
Correct Answer: BExplanationRisk-based test planning starts by identifying and recording product risks and agreeing the response with stakeholders, which here means a contingency such as a dedicated test window after the upgrade. Adding more scheduling test cases does not address a risk located in an external dependency, and extra environment capacity for performance tests answers a different concern. Deferring integration testing entirely would leave the regulated, high-risk area untested before go-live, which conflicts with the firm date and the requirement to assess changes before release.
-
3 Question 3 Single choice Static Testing
A team is preparing an informal review of a 60-page functional specification for a mobile banking feature. Reviewers include a business analyst, a developer, and a tester. The project manager wants defects found early and wants reviewers to examine the document against the original stakeholder requirements, which are held in a separate approved document. The review must be low-overhead and does not need formal approval records. Which review type best fits these needs?
Correct Answer: DExplanationA walkthrough is the informal, low-overhead review type in which the author presents the document and participants ask questions and raise issues, which matches the no-formal-records requirement. A technical review is more formal and involves a documented process, and an inspection adds defined roles, entry and exit criteria and metrics, both beyond what the team wants. A management review focuses on project decisions such as funding rather than detailed defect finding against requirements, so it does not match the stated purpose.
-
4 Question 4 Single choice Test Analysis and Design
A retail company is testing a loyalty discount engine. The business rules state that customers with fewer than 100 points receive no discount, customers with 100 to 499 points receive 5 percent, and customers with 500 points or more receive 10 percent. The tester must select a black-box technique that gives the smallest set of test cases while still exposing boundary errors such as using a strict less-than where less-than-or-equal was intended. Which technique and test set best meet this need?
Correct Answer: BExplanationBoundary value analysis targets the edges between partitions, and values 99, 100, 499 and 500 expose off-by-one and strict versus non-strict comparison errors, which equivalence partitioning with a single representative value per range would miss. Statement coverge is a white-box technique and, with one test per branch, does not check the exact thresholds. Decision table testing is appropriate for combinations of conditions, but the rules here involve a single numeric input, so it adds cases without addressing boundary defects.
-
5 Question 5 Multiple choice Test Tools
A insurance firm is considering introducing test automation for its nightly regression suite of 1,200 API tests. The suite changes frequently because the API is still evolving, the team has two engineers with scripting experience, and the regulator requires auditable test evidence. Management wants a realistic view of the benefits and risks before committing budget. Which TWO statements correctly describe benefits or risks of automating this suite in the circumstances described? (Choose two.)
Correct Answer: B, DExplanationAutomated runs produce consistent, repeatable logs that support auditability, and frequent API change raises the maintenance cost of scripts, which is a genuine risk for a suite that is still evolving. The claim that frequent change removes maintenance is backwards, since changing interfaces typically increase script upkeep. Overnight execution is a real benefit, but the option is framed as a supported conclusion about this specific context and is not the strongest pair with the regulatory point. Automation does not replace exploratory testing, and removing manual testers is an unsupported governance conclusion.
-
6 Question 6 Single choice Testing Throughout the Software Development Lifecycle
A company runs an iterative project with a two-week sprint cadence. A defect was found during system testing that originated in a requirement misunderstanding made during sprint planning. The team has already completed component testing and integration testing for the affected feature. The product owner asks which test level should be strengthened to catch this class of problem earlier in future sprints. Which action best addresses the root cause of the defect as described?
Correct Answer: CExplanationThe defect began as a requirement misunderstanding, so the root cause sits in planning, and reviewing acceptance criteria with business and testers during sprint planning catches such errors before code is written, which aligns with the shift-left principle. Unit tests check code against the developer's understanding and would not reveal a misread requirement. User acceptance testing and extended system testing both happen after the defect has already been built into the product, so they detect the problem later and at higher cost.
-
7 Question 7 Order list Managing the Test Activities
A test team has finished executing a regression cycle for a logistics application and must now complete the defect handling and reporting steps for the failed tests. The defect management process requires that each defect is recorded before it is reported and that its status is kept current throughout its life. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Triage the defects with the stakeholders and assign each one a priority and severity.
- Retest the fixed defects and close those that pass, reopening any that still fail.
- Update the defect status and report the defect counts to the test manager in the test progress report.
- Log each confirmed failure as a defect with steps to reproduce, expected and actual results, and environment details.
Correct Answer:- Log each confirmed failure as a defect with steps to reproduce, expected and actual results, and environment details.
- Triage the defects with the stakeholders and assign each one a priority and severity.
- Retest the fixed defects and close those that pass, reopening any that still fail.
- Update the defect status and report the defect counts to the test manager in the test progress report.
ExplanationDefects must first be logged with reproducible detail, then triaged so priority and severity are set, then fixed and retested, and only then closed, with status reported throughout. Reporting progress depends on the current defect statuses, so it sits at the end of the sequence. Retesting cannot precede triage and the fix, and closing cannot precede retest, so the sequence follows the defect life cycle logically.
-
8 Question 8 Drag and drop Test Analysis and Design
A team is designing tests for a new online booking workflow and wants to choose the most suitable technique for each testing situation. The team must cover the internal logic of a pricing algorithm, check a form against user needs, reuse tester intuition about likely failures in a legacy module, and examine the behaviour of a fare calculation with many combinations of conditions. Match each situation to the technique that best fits it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Verifying that every branch of the pricing algorithm's internal logic is exercisedChecking the booking form's behaviour against the documented user story and its acceptance criteriaTesting fare rules that combine several conditions to produce different outcomesUsing tester knowledge of defect-prone areas in an undocumented legacy modulePerformance testingBlack-box testingWhite-box testingStatic analysisExperience-based testingDecision table testingCorrect Answer:- Verifying that every branch of the pricing algorithm's internal logic is exercised → White-box testing
- Checking the booking form's behaviour against the documented user story and its acceptance criteria → Black-box testing
- Using tester knowledge of defect-prone areas in an undocumented legacy module → Experience-based testing
- Testing fare rules that combine several conditions to produce different outcomes → Decision table testing
ExplanationWhite-box testing targets internal structure such as branches of the pricing logic, black-box testing checks behaviour against requirements, experience-based testing uses tester knowledge where documentation is lacking, and decision table testing handles combinations of conditions. Static analysis examines code without executing it and does not fit a request about design technique selection, while performance testing addresses speed and load, not any of the four situations described.
-
9 Question 9 Dropdown Testing Throughout the Software Development Lifecycle
A team is documenting its approach to testing changes in a production payroll system that has been in use for six years. A small correction was made to a tax calculation module, and the team must confirm that existing behaviour elsewhere has not been affected. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
Testing performed after a change to an existing system, to confirm that the change has not adversely affected unchanged parts, is known as testing, and it is typically supported by a test suite that is re-run after each change.Correct Answer:Testing performed after a change to an existing system, to confirm that the change has not adversely affected unchanged parts, is known as regression testing, and it is typically supported by a regression test suite that is re-run after each change.
ExplanationTesting that checks unchanged functionality after a modification is regression testing, and the reusable set of tests that is re-run for this purpose is a regression test suite. Confirmation testing is used to verify that a specific defect fix works, not to check unchanged areas, and maintenance testing is the broader category of testing changes to live systems, so it does not name the specific activity described. A smoke suite is a shallow check of build stability rather than a broad re-run after each change.
-
10 Question 10 Single choice Fundamentals of Testing
A software house is reviewing the skills required of its testers before recruiting for a new project. The project involves a safety-related control module, and the test manager wants candidates who can understand the system from the user's point of view, communicate defects clearly to developers and business stakeholders, and think critically about requirements that are ambiguous. The role will not include writing production code. Which combination of skills best matches the requirements for this tester role?
Correct Answer: BExplanationThe role calls for communication with developers and stakeholders, critical evaluation of ambiguous requirements, and a user-focused view, which together describe the core skills expected of a tester. Production architecture and programming expertise are development skills the role explicitly excludes. Database and network administration are infrastructure skills outside the tester's core remit here, and budget allocation belongs to project management rather than the tester role described.
These are 10 of the 365 questions in the full CTFL_Syll2018 pack.
Get All 365 QuestionsGet all 365 questions & answers
Full access options for iSQI CTFL_Syll2018
Self-study
PDF Version
- 365 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 365 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 365 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CTFL_Syll2018 Exam (ISTQB Certified Tester Foundation Level) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.