Exam Information
Free practice questions with explanations
iSQI CTFL-PT Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 17
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Objective 10: Understand the principal performance testing activities.
A retail company is preparing its checkout service for a holiday sales peak. The performance test lead has been asked to plan the testing work for the next release. The team has a two-week window before the code freeze, a shared staging environment that other squads also use on weekdays, and a mandate from the CTO that no production-like test may run against the live payment gateway. The lead must decide which activities to perform first so that the most important risks are addressed before the environment becomes unavailable. Which activity should be performed FIRST?
Correct Answer: CExplanationPerformance testing activities start with understanding the requirements and the expected operational usage so that objectives can be stated in measurable terms. Without objectives, scripts and load profiles have no target to verify against. Running tests first wastes scarce shared staging time because there is nothing to compare results with. Scripting before objectives risks building the wrong scenarios, and monitoring the live payment gateway violates the CTO's explicit prohibition.
-
2 Question 2 Single choice Objective 11: Explain typical categories of performance risks for different architectures.
A bank is migrating its monolithic loan-origination application to a set of microservices communicating over HTTP and a shared message broker. Each service is deployed in a container cluster with autoscaling enabled. The architects are worried that the new design introduces performance risks not present in the monolith. Regulatory requirements prevent any data from leaving the bank's private network, so cloud-hosted third-party load generators cannot be used. Which performance risk category is MOST directly introduced by this architectural change and should be prioritised in the risk assessment?
Correct Answer: CExplanationDecomposing a monolith into microservices shifts work onto the network, so the dominant new performance risk is cumulative latency and reduced throughput from multiple inter-service calls, serialisation and broker hops. The monolith's shared database pool and in-process memory risks existed before the change, and client-side rendering is unaffected by the back-end refactoring. The regulatory constraint on load generators is relevant to test execution but does not alter which architectural risk category is newly introduced.
-
3 Question 3 Multiple choice Objective 12: Analyze a given project to determine the appropriate performance testing activities for each phase of the software lifecycle.
A software house practising DevOps delivers a mobile banking back end every two weeks through a CI/CD pipeline. Developers commit code many times a day. Performance problems have previously been found only in the final pre-release environment, causing costly delays. The project manager wants performance activities placed earlier in the lifecycle without running heavy load tests on every commit, because the build agents have limited capacity. Which TWO activities are the most appropriate to include in the earlier lifecycle phases? (Choose two.)
Correct Answer: C, EExplanationEarly performance activities in a DevOps lifecycle include lightweight automated checks integrated into the pipeline, which give rapid feedback without overloading build agents, and reviews of design decisions that affect performance before code is written. A multi-hour soak test on workstations is impractical and does not fit the commit cadence. Deferring testing to production contradicts the goal of earlier detection, and a single late stress test repeats the problem the project manager is trying to solve.
-
4 Question 4 Single choice Objective 13: Derive performance test objectives from relevant information.
An airline's online booking portal has a service level agreement stating that the search page must respond within 2 seconds for 95 percent of requests during a peak of 3,000 concurrent users. The marketing team has also asked that the system 'feel fast' during promotions. The performance tester has access to the SLA document, the marketing brief, and historical analytics showing that peak traffic is 1,800 concurrent users on normal days. Which objective is the tester MOST appropriate to derive from these sources?
Correct Answer: DExplanationThe SLA provides a measurable, contractual target: 95 percent of search requests under 2 seconds at 3,000 concurrent users, so that is the objective to derive. The marketing wish is not measurable as written and must be translated into quantified criteria. The 1,800-user historical figure describes normal load and does not replace the SLA peak. Finding the first error point is a breaking-point question that goes beyond the stated requirement.
-
5 Question 5 Single choice Objective 14: Outline a performance test plan which considers the performance test objectives for a given project.
A government benefits agency must release a new claims-submission system. The test objectives are: 95 percent of submissions complete within 3 seconds at 500 concurrent users, and no data loss under sustained load for 8 hours. The project has a fixed budget that allows only one shared load-generation environment, and the production-like test environment will only be available for three days in the final week. Which element of the performance test plan best addresses these constraints?
Correct Answer: DExplanationA plan that respects both the objectives and the scarce environment schedules the 8-hour endurance run with 500 concurrent users inside the three-day availability window, and includes checks for data loss so the second objective is verified. Running endurance tests on laptops does not represent the production-like environment, so results would not be credible. A 10-minute smoke test cannot verify an 8-hour objective. Testing at 5,000 users changes the objective and wastes the limited window.
-
6 Question 6 Dropdown Objective 15: Create a presentation that enables various stakeholders to understand the rationale behind the planned performance testing.
A performance test lead must brief a steering committee of executives, product owners and developers on why a 12-day performance test phase is planned before a payments launch. The executives ask for a concise rationale they can connect to business outcomes, while developers need the technical basis. Complete the statement that the lead should use to frame the rationale for the executives by selecting the correct value for each blank. The planned testing is justified because the business risk is [1] and the verification approach is [2].
Choose the correct value for each blank.
The planned testing is justified because the business risk is and the verification approach is .Correct Answer:The planned testing is justified because the business risk is customer-facing response times failing agreed targets under peak load and the verification approach is compare measured results against the agreed objectives under representative load.
ExplanationExecutives respond to business framing, so the rationale should tie the phase to the risk that customers experience slow or failing responses under peak demand, and to the verification method of measuring results against agreed objectives under representative load. Hardware specifications, unit test counts and naming conventions are technical details that do not explain why the testing matters to the business. Counting test cases measures activity rather than outcomes, and delaying release until all defects are closed is not a performance-testing rationale.
-
7 Question 7 Single choice Objective 16: Give examples of typical protocols encountered in performance testing.
A performance tester is preparing scripts for a logistics platform. The platform exposes a web portal over HTTPS, a REST API used by a mobile app, and an internal order-routing component that communicates with a legacy warehouse system over a messaging queue using AMQP. The tester is asked to generate load on all three interfaces from a single tool and to replicate the traffic accurately. Which statement correctly identifies the protocols that must be supported?
Correct Answer: CExplanationThe web portal and the REST API both use HTTP or HTTPS as their transport, and the messaging queue uses AMQP, so the tool must support those protocols to reproduce traffic faithfully. The other options assign mail, file transfer, database or network-management protocols to the wrong interfaces, so a tool configured with them would not generate representative load on this platform.
-
8 Question 8 Single choice Objective 17: Understand the concept of transactions in performance testing.
A performance tester is scripting a ticket-purchase journey for a concert platform. The journey consists of: search for events, select a seat, enter payment details, and receive a confirmation page. Each step issues several HTTP requests. Stakeholders want to see the response time that a customer experiences for the complete purchase, and they want a pass/fail result per business step as well. The tool used supports named transaction timers. Which scripting approach is MOST appropriate?
Correct Answer: BExplanationTransactions group related requests so that timing reflects a meaningful business action. Using nested transactions, with step-level transactions inside an end-to-end journey transaction, gives both the customer-experience timing and per-step pass/fail data that stakeholders asked for. A single confirmation transaction hides the earlier steps, per-request transactions lose the journey view, and averaging individual requests does not measure the time a user waits for the whole task.
-
9 Question 9 Order list Objective 18: Create load profiles derived from operational profiles for given performance objectives.
A ticketing company has analysed its production logs and found that during a sale window, 60 percent of traffic is browsing events, 30 percent is adding items to a basket, and 10 percent is completing purchases. Peak throughput of 1,200 purchase-completing transactions per minute must be supported. The tester must build a load profile for the test. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Define a ramp-up period and a steady-state period for the load profile.
- Assign each transaction type a target throughput and configure the load generator to match the mix.
- Derive the total request rate for each activity by applying its percentage of the operational profile.
- Validate the profile by checking that the generated distribution matches the production log percentages.
- Confirm the peak transaction rate from the performance objective and the sale window duration.
Correct Answer:- Confirm the peak transaction rate from the performance objective and the sale window duration.
- Derive the total request rate for each activity by applying its percentage of the operational profile.
- Define a ramp-up period and a steady-state period for the load profile.
- Assign each transaction type a target throughput and configure the load generator to match the mix.
- Validate the profile by checking that the generated distribution matches the production log percentages.
ExplanationThe load profile starts from the performance objective, which fixes the peak rate. The operational profile percentages are then applied to derive per-activity rates, the ramp and steady-state timing are defined, the mix is configured in the load generator, and finally the generated distribution is checked against the logs. Configuring the generator before deriving rates or validating the mix would leave the profile without a basis or verification.
-
10 Question 10 Single choice Objective 19: Analyze throughput and concurrency when developing performance tests.
A fintech team is testing an API that processes payment requests. Each request takes on average 0.5 seconds to complete, including server processing and network time. The performance objective requires the system to sustain 400 completed requests per second at steady state. The team's load generator is configured with a fixed pool of virtual users, and each virtual user waits for a response before issuing its next request, with no think time. Which number of concurrent virtual users is required to achieve the target throughput, applying Little's Law?
Correct Answer: AExplanationLittle's Law states that average concurrency equals throughput multiplied by average time in system, so 400 requests per second at 0.5 seconds each requires 200 concurrent virtual users. The 800 figure inverts the relationship incorrectly, 400 assumes an unrealistic one request per second per user, and 50 divides the wrong quantities. Note that the stated 0.5-second response time is taken as the cycle time when there is no think time.
-
11 Question 11 Drag and drop Objective 20: Understand the basic structure of a performance test script.
A performance engineer is reviewing a colleague's script for a hotel booking API. The script must reproduce realistic user sessions, handle values that change per session, and measure what the business cares about. Match each script element to its purpose in the script structure.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Named timer wrapped around the complete search-and-book journeyParameterised list of hotel identifiers fed into each iterationPause inserted between two user actions to imitate reading timeLogin request whose returned session token is reused in later requestsResult aggregation across runsThink timeCorrelation of dynamic valuesLoad injector allocationTransaction boundaryData parameterisationCorrect Answer:- Login request whose returned session token is reused in later requests → Correlation of dynamic values
- Pause inserted between two user actions to imitate reading time → Think time
- Named timer wrapped around the complete search-and-book journey → Transaction boundary
- Parameterised list of hotel identifiers fed into each iteration → Data parameterisation
ExplanationA script's structure separates request logic from the dynamic handling and timing elements. Correlation captures values such as session tokens so later requests succeed, think time models realistic user pauses, transactions define measurement boundaries, and parameterisation varies input data across virtual users. Load injector allocation and result aggregation belong to test execution and analysis rather than to script structure.
-
12 Question 12 Single choice Objective 21: Implement performance test scripts consistent with the plan and load profiles.
A performance tester has been given a plan that requires a checkout scenario to run at 60 percent of virtual users performing a search, 30 percent adding to cart, and 10 percent completing checkout. The tester has implemented three separate scripts, each running at 100 percent of the load, and then launched them together so that the total number of virtual users is equal to the sum. The test lead rejects the results. What is the MOST accurate reason the result is invalid?
Correct Answer: BExplanationEach script was run at its full population, so the combined run does not follow the planned 60/30/10 distribution, and the total load is inflated beyond the plan. Scripts can run concurrently when the scheduler allocates the planned proportion to each. Concurrent execution is not inherently erroneous, and removing parameterisation or transactions would reduce the validity of measurement rather than correct the mix.
-
13 Question 13 Multiple choice Objective 22: Understand the activities involved in preparing for performance test execution.
A performance test team is about to start a load test of an online insurance quoting system. The system is deployed in a staging environment that is shared with a functional testing team. Two days earlier, the functional team deployed a new build, and the environment has not been checked for configuration changes since. The lead wants to ensure that the results will be valid and that the environment is ready before execution starts. Which TWO preparation activities are the most important to complete? (Choose two.)
Correct Answer: C, DExplanationValid results depend on a known environment state, so the configuration must be checked against the plan after the recent deployment, and the test window must be protected from competing activity on the shared environment. Disabling monitoring removes the data needed to analyse results, starting with an empty database changes the performance profile unrealistically, and exceeding the target load alters the test objective rather than preparing for it.
-
14 Question 14 Single choice Objective 23: Understand the principal activities in running performance test scripts.
A performance test is running against a ticket reservation system. Twenty minutes into a planned 60-minute steady-state run, the test monitor shows that the load generator's CPU is at 98 percent, while the application servers are at 40 percent CPU. Response times recorded by the tool have started rising sharply, and the throughput has dropped below the planned rate. The test is still running and the test manager asks what should happen next. What is the MOST appropriate action?
Correct Answer: BExplanationA saturated load generator means the measured response times and throughput reflect the injector rather than the system under test, so the results are not valid. The correct response is to stop, record what was observed, and confirm whether the injector is the bottleneck before re-running. Continuing would produce misleading data, increasing load worsens the injector problem, and restarting application servers addresses the wrong component.
-
15 Question 15 Dropdown Objective 24: Analyze and report performance test results and implications.
A performance analyst is preparing a results summary for a travel booking system after a load test. The test measured response times for 4,000 requests across a 30-minute run. The analyst must describe the response time distribution accurately, because the stakeholder SLA is expressed as a percentile target rather than an average. Complete the statement by selecting the correct value for each blank. The SLA requires that [1] of requests complete within [2] seconds, so the analyst should report the [3] percentile.
Choose the correct value for each blank.
The SLA requires that of requests complete within seconds, so the analyst should report the percentile.Correct Answer:The SLA requires that 95 percent of requests complete within 2 seconds, so the analyst should report the 95th percentile.
ExplanationThe SLA is written as a percentile target, so the analyst must report the 95th percentile against the 2-second limit rather than the average or maximum. The average can hide a long tail of slow requests and the maximum is dominated by outliers, so neither can confirm compliance with a percentile objective. Using the 50 percent figure or the minimum would not reflect the stated requirement.
-
16 Question 16 Single choice Objective 25: Understand how tools support performance testing.
A performance team is deciding how to use its load testing tool during a multi-week engagement. The tool can generate load, record scripts, and produce graphs. The team also has an existing application performance monitoring platform that collects server-side CPU, memory and database metrics. The team's manager asks how the two tools should share responsibilities so that bottlenecks can be attributed correctly. Which arrangement BEST reflects how such tools support performance testing?
Correct Answer: CExplanationLoad generation tools produce the synthetic load and measure what the client experiences, while monitoring tools observe server-side resources. Correlating the two on a common timeline lets testers attribute a response time increase to a particular resource. Reversing the roles misplaces the functions, running both as load generators doubles the traffic and confuses results, and making testers generate load manually is impractical and unrepeatable.
-
17 Question 17 Single choice Objective 26: Evaluate the suitability of performance testing tools in a given project scenario.
A health-technology company must select a performance testing tool for a patient-records API. The constraints are: the API is built on HTTP and must be tested with both REST and a legacy SOAP interface, all test data is classified as confidential and cannot leave the company's private network, the budget is limited, and the team's engineers are experienced in Java but not in other scripting languages. Two candidate tools are a cloud-only SaaS load generator with a visual scripting interface, and an open-source tool hosted on-premises that uses Java-based scripting. Which evaluation conclusion is MOST justified?
Correct Answer: AExplanationThe confidentiality classification of test data rules out a cloud-only generator that would transmit it outside the private network, so the on-premises tool is the defensible choice, and its Java-based scripting matches the team's skills within the budget. The SaaS option violates the stated constraint, the claim that test data is exempt contradicts the classification given, and abandoning testing is not a justified conclusion when a suitable tool exists.
These are 17 of the 40 questions in the full CTFL-PT pack.
Get All 40 QuestionsGet all 40 questions & answers
Full access options for iSQI CTFL-PT
Self-study
PDF Version
- 40 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 40 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 40 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CTFL-PT Exam (ISTQB Certified Tester Foundation Level - Performance Testing) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.