2026 Actual BCS ISEB-PM1 Dumps, Updated Exam Questions for Guaranteed Pass

BCS Foundation Certificate in IS Project Management - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorBCS
Exam codeISEB-PM1
Exam nameBCS Foundation Certificate in IS Project Management
Questions in pack625
Last updatedNovember 22, 2026
Related certificationsProject and Programme Management

Free practice questions with explanations

BCS ISEB-PM1 Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
10
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Projects and Project Work

    A regional logistics company is replacing its legacy warehouse management system. The steering group has asked that the new system be delivered in a way that minimises the risk of disrupting dispatch operations, and that it be possible to revert quickly to the old system if serious faults emerge in the first week after go-live. The legacy system must remain available until the new system has proved itself on live transactions. The project team is considering how to implement the change-over. Which implementation strategy best meets these requirements?

  2. 2 Question 2 Single choice Project Planning

    A software house is planning a customer billing upgrade. The network diagram in the activity-on-node format shows that activity G has an early start of day 14, a duration of 5 days, and a late finish of day 22. Activity H, which depends on G, has a duration of 3 days and an early start equal to the early finish of G. Activity H is not on the critical path. The project manager is asked how much total float H has and whether H can slip without delaying the project end date. Which statement is correct?

  3. 3 Question 3 Order list Monitoring and Control

    A project manager for a mid-sized insurer has discovered that the testing phase of a claims system is running two weeks behind plan, and the stage tolerance has been exceeded. The project board wants the manager to respond using a disciplined control cycle rather than informal adjustments. Arrange the steps in the correct order the project manager should perform them.

    Drag the steps into the correct order, or use the arrows.

    1. Gather progress information from timesheets and the team's progress meeting
    2. Develop corrective action options and assess the impact on the business case
    3. Produce an exception report and submit it to the project board for a decision
    4. Compare the actual progress with the planned progress to identify the variance
    5. Implement the authorised corrective action and continue monitoring achievement
  4. 4 Question 4 Single choice Change Control and Configuration Management

    A public sector agency has baselined the requirements and design for its benefits payment system. During integration testing, a business sponsor requests an additional field for applicant eligibility, which would require changes to the database schema, three interfaces, and the approved user documentation. The contract limits any scope change to a value of 5 percent of the baseline, and the proposed change would exceed this. The project manager must decide the correct first action. What should the project manager do first?

  5. 5 Question 5 Drag and drop Quality

    A medical device firm's software team is preparing for a regulated release of its dosage calculation module. The quality manager wants each quality activity matched to the purpose it serves so that the release gate criteria are clearly defined. Match each quality activity to the category it belongs to.

    Drag each item onto its matching target. On a phone: tap an item, then tap a target.

    Establishing the entry and exit criteria that each stage of development must satisfy
    Carrying out a regression run after a defect fix to confirm that existing functions still work
    Running the module against a set of test cases to find defects in the delivered code
    Checking that a completed design document meets the agreed standard before work proceeds
    Configuration management
    Risk management
    Quality control
    Quality assurance
  6. 6 Question 6 Single choice Estimating

    A consultancy is estimating a new reporting module for a client. The estimator has historical data showing that the team delivers about 9 function points per person-day on comparable work, and the team has just reached a stage where its members are new to the reporting tool. The client asks for a firm estimate of effort for a module the estimator has sized at 540 function points. The estimator recognises that the historical productivity rate may not apply to this team. What is the most appropriate course of action?

  7. 7 Question 7 Dropdown Risk

    A project manager for a bank is maintaining the risk log for an online payments upgrade. A key risk is that the third-party payment gateway may not be certified in time for the planned go-live. The project board has approved a response that the team will accept the residual exposure while keeping a fallback in place. Complete the risk log entry by selecting the correct value for each blank.

    Choose the correct value for each blank.

    Risk response: - the team will accept the residual exposure and prepare a plan to use the existing payment route if the gateway is not certified by the go-live date.
  8. 8 Question 8 Single choice Project Communications and Project Organisation

    A health authority has launched a three-year programme of which one project is a patient records integration. The project board includes a senior responsible owner, a user representative, and a supplier representative. The project manager is concerned that the sponsor is not attending board meetings and that decisions on scope are being made by the user representative alone. The project manager must recommend a correction to the organisation's governance. Which action best addresses the problem?

  9. 9 Question 9 Multiple choice Projects and Project Work

    A property developer is initiating a project to build a customer portal and wants the project initiation documentation to support a sound investment decision and a clear basis for control. The sponsor has asked which features the business case and the planning documents should contain before the project is approved. Which TWO statements about the business case and planning documents are correct? (Choose two.)

  10. 10 Question 10 Order list Project Planning

    A transport authority is planning a scheduling system with a product-based approach. The planning team wants to build the plan from the products down to the activities that create them, so that dependencies are clear and no work is omitted. Arrange the steps in the order the planning team should perform them.

    Drag the steps into the correct order, or use the arrows.

    1. Identify the activities needed to create each product and their dependencies
    2. Draw the activity network and calculate the earliest and latest dates of each activity
    3. Break each product into its component products and record the derived-from relationships
    4. Assign resources to the activities and check for over-allocation using a histogram
    5. Identify the final deliverables and the products that make them up

These are 10 of the 625 questions in the full ISEB-PM1 pack.

Get All 625 Questions

Get all 625 questions & answers

743 Satisfied customers
93.1% Pass rate feedback
85% Said questions matched
97% Found material helpful

Full access options for BCS ISEB-PM1

Self-study

PDF Version

$40.00 $20.00
  • 625 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 625 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the ISEB-PM1 Exam (BCS Foundation Certificate in IS Project Management) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed