1 Question 1 Single choice Projects and Project Work
A regional logistics company is replacing its legacy warehouse management system. The steering group has asked that the new system be delivered in a way that minimises the risk of disrupting dispatch operations, and that it be possible to revert quickly to the old system if serious faults emerge in the first week after go-live. The legacy system must remain available until the new system has proved itself on live transactions. The project team is considering how to implement the change-over. Which implementation strategy best meets these requirements?
Correct Answer: CExplanationParallel running keeps the legacy system operating alongside the new one on live transactions, which gives the fallback the steering group requires while the new system is proven. Sudden death removes the fallback entirely, and phased rollout without retained fallback at each site does not meet the reversion requirement. A pilot run in a test environment with simulated orders does not prove the system on live transactions, so it fails the proving requirement.
-
2 Question 2 Single choice Project Planning
A software house is planning a customer billing upgrade. The network diagram in the activity-on-node format shows that activity G has an early start of day 14, a duration of 5 days, and a late finish of day 22. Activity H, which depends on G, has a duration of 3 days and an early start equal to the early finish of G. Activity H is not on the critical path. The project manager is asked how much total float H has and whether H can slip without delaying the project end date. Which statement is correct?
Correct Answer: CExplanationFloat is calculated as the difference between the latest finish and the earliest finish of an activity, and an activity that is not on the critical path has positive float that can absorb slippage without moving the end date. Claiming H has no float contradicts its non-critical status. Equating float with duration ignores the constraint imposed by successors' late dates. Tying float to actual completion of G confuses planned float with progress monitoring.
-
3 Question 3 Order list Monitoring and Control
A project manager for a mid-sized insurer has discovered that the testing phase of a claims system is running two weeks behind plan, and the stage tolerance has been exceeded. The project board wants the manager to respond using a disciplined control cycle rather than informal adjustments. Arrange the steps in the correct order the project manager should perform them.
Drag the steps into the correct order, or use the arrows.
- Gather progress information from timesheets and the team's progress meeting
- Develop corrective action options and assess the impact on the business case
- Produce an exception report and submit it to the project board for a decision
- Compare the actual progress with the planned progress to identify the variance
- Implement the authorised corrective action and continue monitoring achievement
Correct Answer:- Compare the actual progress with the planned progress to identify the variance
- Produce an exception report and submit it to the project board for a decision
- Gather progress information from timesheets and the team's progress meeting
- Develop corrective action options and assess the impact on the business case
- Implement the authorised corrective action and continue monitoring achievement
ExplanationThe control cycle begins with collecting progress information, then measuring it against the plan to identify variances. Because the stage tolerance has been breached, an exception report must go to the project board before corrective action can be authorised, and the options must be assessed against the business case first. Implementation and continued monitoring follow the board's decision. Placing the exception report before the variance is identified would report something not yet measured.
-
4 Question 4 Single choice Change Control and Configuration Management
A public sector agency has baselined the requirements and design for its benefits payment system. During integration testing, a business sponsor requests an additional field for applicant eligibility, which would require changes to the database schema, three interfaces, and the approved user documentation. The contract limits any scope change to a value of 5 percent of the baseline, and the proposed change would exceed this. The project manager must decide the correct first action. What should the project manager do first?
Correct Answer: DExplanationA change to an approved baseline must go through the change control procedure, starting with a change request that is evaluated for its impact on the business case, including the contract limit, before the change control board decides. Implementing first bypasses authorisation and breaks configuration control. Outright rejection ignores the legitimate route for change. Updating the baseline unilaterally prevents the board from assessing the change and leaves the baseline uncontrolled.
-
5 Question 5 Drag and drop Quality
A medical device firm's software team is preparing for a regulated release of its dosage calculation module. The quality manager wants each quality activity matched to the purpose it serves so that the release gate criteria are clearly defined. Match each quality activity to the category it belongs to.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Establishing the entry and exit criteria that each stage of development must satisfyCarrying out a regression run after a defect fix to confirm that existing functions still workRunning the module against a set of test cases to find defects in the delivered codeChecking that a completed design document meets the agreed standard before work proceedsConfiguration managementRisk managementQuality controlQuality assuranceCorrect Answer:- Checking that a completed design document meets the agreed standard before work proceeds → Quality assurance
- Running the module against a set of test cases to find defects in the delivered code → Quality control
- Establishing the entry and exit criteria that each stage of development must satisfy → Quality assurance
- Carrying out a regression run after a defect fix to confirm that existing functions still work → Quality control
ExplanationQuality assurance concerns the processes and standards that prevent defects, such as entry and exit requirements and document standards applied before work proceeds. Quality control concerns the examination of the product itself, such as testing and regression runs that detect defects in delivered code. Configuration management and risk management are distinct project disciplines that do not match any of these activities.
-
6 Question 6 Single choice Estimating
A consultancy is estimating a new reporting module for a client. The estimator has historical data showing that the team delivers about 9 function points per person-day on comparable work, and the team has just reached a stage where its members are new to the reporting tool. The client asks for a firm estimate of effort for a module the estimator has sized at 540 function points. The estimator recognises that the historical productivity rate may not apply to this team. What is the most appropriate course of action?
Correct Answer: BExplanationProductivity rates derived from past data must reflect factors such as staff experience, so when the team lacks familiarity with the tool, the rate should be adjusted before it is applied to the size driver. Using the unadjusted historical rate ignores a known factor affecting productivity. Choosing a figure the client will accept is not an estimating method. Abandoning the size-based approach discards a usable basis merely because the rate needs adjusting.
-
7 Question 7 Dropdown Risk
A project manager for a bank is maintaining the risk log for an online payments upgrade. A key risk is that the third-party payment gateway may not be certified in time for the planned go-live. The project board has approved a response that the team will accept the residual exposure while keeping a fallback in place. Complete the risk log entry by selecting the correct value for each blank.
Choose the correct value for each blank.
Risk response: - the team will accept the residual exposure and prepare a plan to use the existing payment route if the gateway is not certified by the go-live date.Correct Answer:Risk response: Acceptance - the team will accept the residual exposure and prepare a contingency plan to use the existing payment route if the gateway is not certified by the go-live date.
ExplanationAccepting a risk means retaining its exposure without further action, and it is paired with a contingency plan that is triggered if the risk event occurs, such as falling back to the existing route. Transfer would pass the exposure to another party, such as an insurer or supplier, which is not described. Prevention and reduction both involve actions taken to lower probability or impact, which the team has explicitly chosen not to pursue. A rolling or baseline plan is not a risk response, and escalation is a reporting route rather than a planned fallback.
-
8 Question 8 Single choice Project Communications and Project Organisation
A health authority has launched a three-year programme of which one project is a patient records integration. The project board includes a senior responsible owner, a user representative, and a supplier representative. The project manager is concerned that the sponsor is not attending board meetings and that decisions on scope are being made by the user representative alone. The project manager must recommend a correction to the organisation's governance. Which action best addresses the problem?
Correct Answer: BExplanationThe project sponsor is the source of authority for the project, and the project board must have the right membership with defined roles so that scope decisions are made by those with authority. Documenting membership and responsibilities closes the gap that allowed the user representative to decide alone. Removing the user representative removes an important stakeholder voice rather than fixing the sponsor problem. Rescheduling meetings does not address the accountability gap. The project support office provides administrative and control support, not decision authority over scope.
-
9 Question 9 Multiple choice Projects and Project Work
A property developer is initiating a project to build a customer portal and wants the project initiation documentation to support a sound investment decision and a clear basis for control. The sponsor has asked which features the business case and the planning documents should contain before the project is approved. Which TWO statements about the business case and planning documents are correct? (Choose two.)
Correct Answer: A, BExplanationA business case justifies the investment by setting out expected costs and benefits and comparing alternatives, and discounted cash flows are used within it to reflect the time value of money. The project initiation document does not replace stage plans, which provide detailed control at stage level. Candidates are not required to perform discounted cash flow calculations. A quality plan is a planning document prepared before the project's work begins, not after closure.
-
10 Question 10 Order list Project Planning
A transport authority is planning a scheduling system with a product-based approach. The planning team wants to build the plan from the products down to the activities that create them, so that dependencies are clear and no work is omitted. Arrange the steps in the order the planning team should perform them.
Drag the steps into the correct order, or use the arrows.
- Identify the activities needed to create each product and their dependencies
- Draw the activity network and calculate the earliest and latest dates of each activity
- Break each product into its component products and record the derived-from relationships
- Assign resources to the activities and check for over-allocation using a histogram
- Identify the final deliverables and the products that make them up
Correct Answer:- Identify the final deliverables and the products that make them up
- Break each product into its component products and record the derived-from relationships
- Identify the activities needed to create each product and their dependencies
- Draw the activity network and calculate the earliest and latest dates of each activity
- Assign resources to the activities and check for over-allocation using a histogram
ExplanationThe product-based approach starts from the final deliverables, decomposes them into component products with their relationships, and then identifies the activities that create each product. The activity network is drawn from those activities, with earliest and latest dates calculated on it. Resource allocation and smoothing or levelling come last, once the schedule is known. Starting from activities would risk omitting products and their relationships.
These are 10 of the 625 questions in the full ISEB-PM1 pack.
Get All 625 QuestionsGet all 625 questions & answers
Full access options for BCS ISEB-PM1
Self-study
PDF Version
- 625 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 625 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 625 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the ISEB-PM1 Exam (BCS Foundation Certificate in IS Project Management) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.