1 Question 1 Single choice Managing the Product
A logistics company runs a hybrid delivery programme. The test manager reports that the defect detection percentage (DDP) for the last release is 62%, while the escaped defect count from production is rising. The programme board wants test progress reported in a way that lets them decide whether to extend the test phase before the warehouse go-live in six weeks. Test execution is 85% complete, but 30% of executed tests were blocked by an unstable interface environment that is not yet fixed. Which reporting approach BEST supports the board's decision?
Correct Answer: BExplanationThe 85% execution figure hides that nearly a third of executed tests were blocked, so the board needs blocked counts and exit criteria status alongside defect trends to judge whether go-live is realistic. Reporting execution alone or DDP alone gives an incomplete picture, and defects per test case does not reveal the environment constraint that actually threatens the date.
-
2 Question 2 Single choice Managing the Product
A team uses a three-point estimation technique for a regression suite. The estimates are optimistic 40 person-days, most likely 60 person-days and pessimistic 110 person-days. The project is an outsourced payment integration with a fixed-price contract, and the vendor has limited historical data for this platform. The test manager must select an estimation approach for the next planning round. Which choice is MOST appropriate?
Correct Answer: DExplanationThe PERT weighting (optimistic + 4 x most likely + pessimistic) divided by six gives roughly 65 person-days, which reflects the wide spread caused by limited historical data. Pairing it with a contingency and a re-estimation trigger suits a fixed-price contract. Committing to the most likely or optimistic value ignores the uncertainty, and an unsupported average hides the assumptions the vendor needs to defend.
-
3 Question 3 Single choice Managing the Product
A retailer's Agile teams log defects in a shared tracker. Testers report that many defects are closed as 'duplicate' or 'not a defect' within a day of being raised, and the product owner says defect counts are misleading in sprint reviews. The test manager must improve defect management in this Agile context without slowing sprint delivery. Which action is the BEST first step?
Correct Answer: DExplanationIn Agile, defect management works best as a lightweight, shared workflow with clear triage roles and closure reasons, which directly reduces misleading duplicate and invalid counts. A weekly change board adds delay that conflicts with sprint pace, dropping defect logging ignores real findings, and mandatory root-cause analysis on every defect creates overhead that slows reporting.
-
4 Question 4 Single choice Managing the Team
A test manager leads a team of six testers for a warehouse management system. Two senior testers are strong in exploratory testing but weak in automation, while a newly hired tester has strong automation skills but limited knowledge of the logistics domain. The programme needs better automated regression coverage within three months, and the team has no budget for external training. Which approach BEST develops the team's skills within these constraints?
Correct Answer: DExplanationPairing and cross-shadowing are on-the-job development approaches that use the team's existing strengths without new spending, which fits the no-budget constraint. Outsourcing removes the skill-building benefit, paid training conflicts with the budget limit, and solo work leaves the new hire without domain knowledge and the seniors without automation skills.
-
5 Question 5 Single choice Managing the Team
A test manager must assess candidates for a senior test analyst role on a safety-related rail signalling project. The team already has strong technical testers but lacks people who can explain test results to non-technical stakeholders and negotiate scope with the project sponsor. The manager wants a skill assessment method that will reliably show whether candidates can do this. Which assessment technique is MOST suitable?
Correct Answer: DExplanationA structured role-play with a scoring rubric directly observes the communication and negotiation skills that are missing from the team, so it gives reliable evidence for the gap. The written test and the automation practical measure technical skills the team already has, and reviewing certifications and experience is indirect evidence that does not show the competency being sought.
-
6 Question 6 Single choice Managing the Team
A test manager is reviewing motivation in a test team that has been working overtime for three months to meet a regulatory deadline. Surveys show that testers are satisfied with their salaries and working conditions but feel their contributions go unrecognised and that they have no path to grow their skills. Which action BEST addresses the motivating factors without relying on the hygiene factors that are already adequate?
Correct Answer: DExplanationRecognition and opportunities for growth and responsibility are motivating factors, and the survey shows the team already has adequate hygiene factors such as pay and conditions. Further pay increases or environmental improvements address hygiene factors that are not the problem, and removing overtime alone does not provide the recognition or advancement the testers say is missing.
-
7 Question 7 Single choice Managing the Team
A financial services company is deciding how to justify its testing budget to executives. The test manager has data showing that the cost of prevention activities such as test planning and reviews is 18,000 per release, appraisal activities such as test execution are 42,000, internal failure costs such as rework from defects found in test are 55,000, and external failure costs such as production incidents and customer credits are 120,000. Which statement correctly classifies these costs under the cost-of-quality model?
Correct Answer: AExplanationUnder the cost-of-quality model, prevention covers planning and reviews, appraisal covers checking activities such as test execution, internal failure covers defects found before release, and external failure covers defects found by customers after release. The distractors mix categories by confusing who performs the work or what the activity is for, rather than applying the defined boundaries.
-
8 Question 8 Single choice Managing the Team
A test manager must justify spending 25,000 on a combinatorial test design tool for a claims processing system. Historical data shows that a defect escaping to production costs about 15,000 on average to resolve, and the tool is expected to prevent roughly four escapes per year. The tool requires 5,000 annual licence cost. The sponsor asks for the added value of testing expressed as the net benefit of the first year. Which calculation BEST answers this request?
Correct Answer: DExplanationFour prevented escapes at 15,000 each give 60,000 of expected savings, and the first-year cost is the 25,000 purchase plus the 5,000 licence, so the net benefit is 30,000. The other options either omit the licence cost, use a single escape where four are expected, or present a ratio that does not answer the net-benefit question the sponsor asked.
-
9 Question 9 Single choice Managing the Test Activities
A test manager is planning testing for a hybrid programme that combines a waterfall-style hardware integration phase with Agile software sprints for a warehouse robotics system. The sponsor wants a single master test plan but the teams work on different cadences. Which planning approach is MOST appropriate?
Correct Answer: DExplanationA hybrid programme benefits from a master strategy that sets common exit criteria and reporting, while allowing team-level plans to adapt iteratively in the sprints. A single detailed up-front plan cannot accommodate the Agile cadence, unrelated plans leave no consolidated view for the sponsor, and deferring planning delays risk-based decisions that should be made early.
-
10 Question 10 Multiple choice Managing the Test Activities
A test manager is analysing a payroll system release that is being tested at system and acceptance levels by different teams. The system test team reports that many failures are environment-related, and the acceptance team reports that business users cannot yet confirm expected results because they were not involved in defining the acceptance criteria. Which TWO actions are the MOST appropriate test management responses? (Choose two.)
Correct Answer: B, CExplanationInvolving business stakeholders early in agreeing acceptance criteria addresses the gap in confirming expected results, and separating environment failures from product defects gives an accurate picture of test progress and quality. Merging the test levels removes the independence the programme relies on, stopping acceptance until all defects are closed delays business involvement unnecessarily, and removing expected results makes outcomes subjective and unverifiable.
-
11 Question 11 Multiple choice Managing the Test Activities
A test manager is reviewing test monitoring and control for a claims system with a fixed release date in ten weeks. The current metrics show that 40% of planned test cases are executed, 12 high-priority defects are open, and the planned exit criteria are unmet for two of six risk areas. Which THREE control actions are the MOST appropriate responses to these monitoring results? (Choose three.)
Correct Answer: C, D, EExplanationTest control responds to monitoring results by re-prioritising execution around risk, escalating decisions that exceed the test team's authority, and re-planning scope against risk when time is limited. Reducing defect reports hides information and undermines control, and adding untrained testers at the last minute creates onboarding overhead that slows progress rather than speeding it up.
-
12 Question 12 Single choice Managing the Test Activities
A test manager is preparing test completion activities for a logistics platform after its final release. Testing is stopping because the programme budget is exhausted, not because all exit criteria are met. Several medium-severity defects remain open and two planned test areas were never executed. Which action is MOST important to include in the test completion report?
Correct Answer: DExplanationWhen testing stops because budget is exhausted, the completion report must state the reasons, unmet exit criteria and residual risks so stakeholders can make an informed release decision, and lessons learned support future planning. Presenting all cases as complete would misrepresent the situation, while performance ratings and framework design do not belong in the completion report.
-
13 Question 13 Single choice Managing the Test Activities
A test manager is planning risk-based testing for a new inventory management module. A risk workshop identifies a payment-related function with high business impact but low likelihood of failure, and a reporting screen with low impact but a history of frequent defects. The budget allows execution of about 60% of the planned test cases. Which test prioritisation decision is MOST consistent with risk-based testing?
Correct Answer: CExplanationRisk-based testing rates risk by combining likelihood and impact, so the reporting screen's frequent defect history can outweigh the payment function's low likelihood even though the payment impact is high, depending on the combined rating. Impact alone ignores likelihood, equal coverage ignores risk entirely, and restricting testing to new functions ignores risk in existing areas affected by change.
These are 13 of the 52 questions in the full TM3 pack.
Get All 52 QuestionsGet all 52 questions & answers
Full access options for BCS TM3
Self-study
PDF Version
- 52 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 52 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 52 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the TM3 Exam (ISTQB Certified Tester Advanced Level - Test Management v3.0) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.