1 Question 1 Single choice Energy and Atmosphere
A 6-story office building in a cold climate is pursuing LEED v4 for Building Design and Construction. The owner wants the energy model to reflect how the building will actually be operated, and the design team has already set heating and cooling setpoints based on the occupancy schedule. During model review, the mechanical engineer notices that the baseline model uses a different envelope than the proposed design, which makes the performance comparison unreliable. The schedule is tight and the design cannot be changed. Which action should the team take FIRST to correct the energy model so that it supports the Energy and Atmosphere credit documentation?
Correct Answer: DExplanationModeling for LEED under the energy performance path requires the baseline to follow ASHRAE 90.1 Appendix G rules, which define the baseline building with envelope, lighting and HVAC characteristics derived from the proposed design in prescribed ways. Rebuilding the baseline correctly fixes the mismatch without altering the design. Increasing glazing changes the actual design to game the result, which is not an acceptable correction. A national average is not a valid comparison basis, and past utility bills describe an existing building rather than the code-defined baseline required for the credit.
-
2 Question 2 Single choice Indoor Environmental Quality
A three-story school renovation is pursuing LEED for Schools. The project team is selecting a ventilation approach for classrooms with operable windows and a mechanical system that is being replaced. The design team plans to meet the outdoor air requirement by relying on the ASHRAE 62.1 ventilation rate procedure. The school district has a strict budget and cannot add significant new ductwork, and the building is located next to a busy highway with elevated particulate levels during morning rush hours. The team must document the ventilation approach for the Indoor Environmental Quality credits. Which strategy BEST satisfies the requirements while respecting the constraints?
Correct Answer: CExplanationMeeting ASHRAE 62.1 with a mechanical supply system that includes filtration matched to the particulate exposure addresses both the outdoor air requirement and the highway pollution constraint, while reusing existing ductwork respects the budget limit. Relying only on operable windows cannot guarantee the required rate during the rush-hour periods when opening windows is undesirable. Exhaust-driven infiltration is uncontrolled and does not deliver code-compliant outdoor air. Filtering only the cafeteria leaves the classrooms, where occupants spend most time, unprotected.
-
3 Question 3 Multiple choice Integrative Strategies
A design team is preparing for an early integrative charrette on a mixed-use project with a tight schedule and a desire to avoid redesign late in the process. Several strategies have been proposed to bring the team together before schematic design is finalized. Which TWO actions best reflect the integrative process as expected by LEED practice? (Choose two.)
Correct Answer: B, EExplanationThe integrative process depends on bringing key disciplines together at the start and analyzing interrelated systems early, when changes are inexpensive and beneficial interactions such as daylighting reducing cooling load can be captured. Deferring modeling and late commissioning remove the feedback loop the integrative process relies on. Independent design followed by a single late conflict resolution is the siloed approach the process is meant to replace.
-
4 Question 4 Single choice LEED Process
A commercial developer is seeking LEED certification for a new retail center and wants to understand how the project will move through the certification process after design. The project has completed its design submittal and the team is preparing the documentation package. The owner asks which step follows the design submittal review and what determines whether the project receives its final rating. Which description is accurate?
Correct Answer: AExplanationIn the LEED process, a project submits for design review and then for construction review, and the final certification level depends on the combined outcomes of these reviews together with the total points achieved. Automatic certification after design review skips a required stage. Self-declaration without third-party verification contradicts the GBCI role in certification. Running reviews simultaneously and letting the lowest credit set the rating is not how point totals or certification levels are calculated.
-
5 Question 5 Single choice Location and Transportation
An urban planner is evaluating two candidate sites for a 120-unit residential development pursuing LEED for Neighborhood Development in a city with an existing transit network. Site One is a greenfield parcel on the urban fringe with no nearby transit. Site Two is a previously developed infill lot two blocks from a bus rapid transit station, but it currently has a surface parking lot that the developer wants to keep in part. The project budget does not allow for extensive new road construction. Which approach BEST aligns with the location and transportation objectives?
Correct Answer: AExplanationInfill sites that are previously developed and near existing transit score highly for location and transportation credits, and the constraint on new road construction makes Site Two more feasible. Reducing the parking footprint rather than keeping the surface lot supports the parking-related objective. A greenfield site with no transit fails the core locational intent even if a shuttle is added, since the shuttle does not replace proximity to infrastructure. Retaining the full surface lot works against the parking footprint goal despite the appealing transit access.
-
6 Question 6 Single choice Materials and Resources
A general contractor is preparing a construction waste management plan for a demolition and rebuild project pursuing LEED v4. The project must divert a significant share of construction and demolition debris from landfill. The site has limited space, and the contractor's usual hauler only accepts mixed loads. The owner has asked the contractor to demonstrate diversion with documented tonnage. Which action is the MOST appropriate to meet the waste diversion requirement?
Correct Answer: AExplanationWaste diversion credits require documented diverted tonnage, and a facility that separates mixed debris allows recovery of materials even when the hauler only accepts mixed loads. Keeping weight tickets for each load produces the auditable record that the credit demands. Purchasing offsets is not a substitute for diversion. On-site burning is prohibited and harmful. Estimating percentages without records fails the documentation requirement for the credit.
-
7 Question 7 Multiple choice Sustainable Sites
A landscape architect is designing stormwater management for a 2-acre commercial site with heavy impervious cover, clay soils with low infiltration rates, and a neighboring property that has experienced flooding from runoff. The client wants to reduce peak runoff and treat pollutants before discharge, using strategies that are compatible with the site's constraints and that support the sustainable sites rainwater management objectives. Which TWO strategies are the MOST appropriate? (Choose two.)
Correct Answer: C, DExplanationClay soils with low infiltration rates mean that a conventional infiltration trench needs an underdrain to manage overflow, which makes an underdrained design workable. Bioretention with engineered media and an underdrain provides both peak flow reduction and pollutant treatment on a low-permeability site. Routing runoff straight to the sewer ignores the neighbor's flooding and the treatment requirement. Asphalt increases runoff and reduces the site's ability to manage water. Turf alone provides little treatment or storage for a heavy impervious site.
-
8 Question 8 Single choice Water Efficiency
A facility manager is responsible for a 200-room hotel pursuing LEED for Existing Buildings: Operations and Maintenance. The hotel's water use has risen over the past two years, and the owner wants to lower consumption without compromising guest satisfaction. The engineering team has access to a 12-month interval meter dataset and a list of fixtures that are older and visibly leaking. The owner has a limited capital budget and wants the lowest-cost, highest-impact first step to improve water performance. Which action should the facility manager take FIRST?
Correct Answer: AExplanationInterval meter data reveals where water is being used and when unusual spikes occur, which often points to leaks that are cheap to fix and yield quick savings within the limited budget. Addressing the highest-use and leaking fixtures delivers the best return before any capital investment. Replacing all fixtures ignores that some may be in good condition and wastes capital. Rainwater harvesting is a larger investment that should follow a diagnosis. Reducing cleaning frequency affects guest service without a data-driven basis.
-
9 Question 9 Single choice Energy and Atmosphere
A mid-sized office owner is evaluating refrigerant management for a building that uses packaged rooftop units with an older refrigerant that has a high ozone depletion potential. The owner wants to reduce the building's impact on the atmosphere and is considering a retrofit as part of a broader energy upgrade. The retrofit budget is limited, and the units are near the end of their service life. Which option BEST addresses the ozone depletion concern while aligning with the Energy and Atmosphere objectives?
Correct Answer: AExplanationBecause the units are near end of life and use a high ozone-depleting refrigerant, replacing them with equipment using a zero-ODP, lower-GWP refrigerant addresses the ozone and climate concerns in one step while the capital event is already due. Additives and recharging with another ozone-depleting refrigerant do not remove the underlying problem. A bypass loop does not eliminate the existing refrigerant circuit and adds complexity without resolving the issue.
-
10 Question 10 Single choice Indoor Environmental Quality
A property manager is establishing a green cleaning program for an elementary school pursuing LEED for Schools. The custodial staff currently uses several products that carry strong fragrances and are labeled with hazard warnings. The principal wants a program that protects children with asthma and meets the green cleaning requirements, without reducing the cleaning frequency. The budget supports a single change to product selection and training. Which approach BEST meets the requirements?
Correct Answer: AExplanationA written green cleaning policy paired with third-party certified low-emitting products and staff training addresses indoor air quality and the asthma concern while keeping cleaning frequency and effectiveness intact. Increasing cleaning frequency with the same products raises exposure rather than reducing it. Stronger disinfectants typically increase harmful emissions and do not meet the green cleaning intent. Relying on case-by-case judgment without a policy does not satisfy the program requirement or ensure consistency.
-
11 Question 11 Single choice Project Surroundings and Public Outreach
A developer is preparing a LEED for Homes project in a region where local building codes have recently been updated to require higher insulation levels and stricter air sealing. The design team has been asked to explain how the LEED requirements relate to the local code and to ensure the project does not create a conflict between the two. The architect proposes to pursue LEED credits that exceed code in some areas and to confirm that all code minimums are met. Which statement BEST describes the relationship between LEED and building codes that should guide the design team?
Correct Answer: AExplanationLocal codes set the legal minimum that every project must satisfy, and LEED credits generally reward performance above those baselines, so the design team must meet code first and then earn credits for going further. LEED does not replace codes, so the statement about dropping code compliance is wrong. Allowing LEED to override code with lower values would be unlawful. Treating the two as unrelated ignores how LEED references code baselines in its credit structure.
-
12 Question 12 Single choice LEED Process
A sustainability consultant is advising an owner whose organization is new to green building and is deciding which LEED rating system fits a planned 40,000-square-foot healthcare outpatient clinic that will be renovated from an existing office building. The owner has heard about several rating systems and wants to pick the one that applies to the project type before registration. Which factor should drive the choice of rating system, and what is the correct next step?
Correct Answer: AExplanationLEED rating systems are matched to building type and phase, so the consultant should confirm which system applies to an existing building renovation of this kind before registration. Choosing based on the number of credits or on cost ignores applicability and can lead to an inappropriate registration. Leaving the choice to a permit office confuses code permitting with LEED registration, which is set by the project team.
-
13 Question 13 Multiple choice Water Efficiency
A facility director is preparing a water efficiency plan for a 300,000-square-foot university building with extensive landscaping and a central plant that uses cooling towers. The campus has recently experienced drought restrictions, and the budget is limited. The director wants strategies that reduce potable water use both outdoors and indoors, with measurable performance tracking. Which TWO actions best address the stated goals? (Choose two.)
Correct Answer: B, EExplanationSmart irrigation controllers combined with climate-adapted plantings reduce outdoor demand, which is significant for a campus with extensive landscaping under drought conditions. Submetering major water uses against a baseline gives the measurable tracking the director needs. Higher-flow faucets increase indoor use. Potable makeup water for cooling towers ignores a major efficiency opportunity. Increasing irrigation during restrictions works against both water and regulatory goals.
These are 13 of the 430 questions in the full LEED-Green-Associate pack.
Get All 430 QuestionsGet all 430 questions & answers
Full access options for US Green Building Council LEED-Green-Associate
Self-study
PDF Version
- 430 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 430 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 430 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the LEED-Green-Associate Exam (LEED Green Associate Exam) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.