Exam Information
Free practice questions with explanations
US Green Building Council LEED-AP-O-M Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 15
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Energy and Atmosphere
A 180,000 sq ft office building is pursuing LEED v4.1 O+M: Existing Buildings. Its energy analyst has 14 months of utility data showing a steady rise in whole-building electricity use after hours, while occupancy sensors indicate the floors are empty from 19:00 to 06:00. The building engineer suspects a plug-load or HVAC scheduling issue. The project must demonstrate an energy performance improvement with the least capital spend, and the team cannot install new submetering before the performance period ends in six weeks. Which action should the team take FIRST to identify the source of the after-hours load?
Correct Answer: CExplanationTrend logs from the building automation system already exist, cost nothing extra, and can show whether air handlers, pumps, or exhaust fans are running on schedules that conflict with occupancy. That directly addresses the suspected HVAC scheduling cause within the six-week window. A full envelope audit is expensive and slow, and envelope losses would not appear as a sharp after-hours electrical rise. Lighting replacement is a capital measure chosen before the source is known. The demand meter would arrive after the performance period and is not needed when trend data is already available.
-
2 Question 2 Single choice Indoor Environmental Quality
A 12-story mixed-use building has a mechanical ventilation system that serves a fitness center where spin classes generate high CO2 concentrations during peak hours. The building has a documented ventilation rate procedure in its facility manual and an existing CO2 sensor in each zone connected to the BAS. Tenants have complained about stuffiness in the early evening. The owner wants a low-cost operational fix that keeps the IEQ credit ongoing compliance without replacing the air handler, which is scheduled for replacement in five years. Which strategy is MOST appropriate?
Correct Answer: AExplanationDemand-controlled ventilation uses the existing zone CO2 sensors to modulate outdoor air in proportion to actual occupant density, which is precisely the operational adjustment needed for an intermittent high-occupancy space. Constant maximum outdoor air wastes energy and conflicts with the building's energy goals. Portable HEPA units address particulates, not CO2 or ventilation rate, so they do not meet the ventilation requirement. Lowering supply air temperature addresses thermal comfort rather than the ventilation effectiveness that the stuffiness complaint reflects.
-
3 Question 3 Single choice LEED Process
A consulting firm is registering a single certification project for an existing 90,000 sq ft campus that includes three separate buildings on one parcel. Building C was leased to a non-profit tenant that occupies 40 percent of its floor area and has no operational control over HVAC or lighting. The owner wants all three buildings certified under one project to simplify documentation. The project team is trying to determine the correct project boundary before beginning any credit work. Which approach is required under LEED v4.1 O+M?
Correct Answer: BExplanationLEED O+M project boundaries are drawn around the spaces and systems the certifying organization controls and manages, and a leased portion that the tenant independently operates is excluded unless the owner can demonstrate operational control. Shared parcel or shared ownership alone does not force a single boundary, and it does not force separate registrations either. Including the full building including tenant-controlled systems would make compliance impossible to document, and separating Building C entirely would be unnecessary when the owner controls the other two buildings.
-
4 Question 4 Single choice Location and Transportation
A 60,000 sq ft office building is seeking an alternative transportation credit under LEED v4.1 O+M. The owner has completed a commuter survey and found that 35 percent of occupants arrive by single-occupancy vehicle, while 22 percent use public transit. The building has 400 occupants and sits within half a mile of a rail station with frequent service. The property manager wants the credit documentation to reflect the most current data and to demonstrate ongoing improvement rather than a single snapshot. Which action BEST meets the requirement?
Correct Answer: AExplanationUnder the O+M transportation approach, current commuter data must be collected from the building's own occupants over the performance period so the mode split reflects real behavior and trends. Design-phase surveys do not reflect operational conditions, and transit agency ridership counts cannot isolate this building's occupants. A bicycle rack alone is an infrastructure measure, not evidence of current transportation patterns, and the credit depends on measured occupant commuting data.
-
5 Question 5 Single choice Materials and Resources
A property manager is planning a tenant-improvement renovation in a 25-year-old retail center. Demolition will produce carpet, ceiling tile, gypsum board, and rigid insulation. The project must reduce construction and demolition waste sent to landfill for LEED O+M purposes, and the contractor has a hauler who charges per ton for mixed debris but offers reduced rates for source-separated loads. The site has limited space for on-site sorting containers. Which waste management approach is MOST appropriate for achieving the diversion goal at the lowest total cost?
Correct Answer: DExplanationSource separation into dedicated streams for materials with established recycling markets, such as gypsum board, carpet, and clean wood, gives the required diversion and lowers hauling cost through the reduced per-ton rates the hauler offers. A single mixed container typically produces lower diversion because contamination reduces recovery, even if a sorting facility is used. Donating only ceiling tile addresses one material and leaves the rest landfilled. Burying debris on site is not a waste diversion method and is generally prohibited.
-
6 Question 6 Single choice Sustainable Sites
A corporate campus is updating its site management plan under a LEED O+M project. The campus has a 4-acre retention pond that receives stormwater runoff from parking lots treated with road salt. The facilities team wants to improve watershed quality and soil health without installing major infrastructure. Monitoring shows elevated chloride levels in the pond during winter months and declining vegetation along its edge. The site must maintain its existing parking capacity and budget constraints. Which operational change BEST addresses the watershed and soil health objective?
Correct Answer: BExplanationReplacing sodium chloride with a lower-chloride or non-chloride deicer, and calibrating application to actual surface conditions, reduces the salt load entering the retention pond and limits soil salinity that damages edge vegetation. Increasing sodium chloride use worsens the problem directly. A concrete liner addresses erosion but not the chemical source, and it does not restore soil health. Removing vegetation eliminates habitat and erosion control without addressing the chloride input.
-
7 Question 7 Single choice Water Efficiency
A 15-acre business park has an irrigation system serving 4 acres of turf and 11 acres of planted beds. The landscape contractor reports that the existing controller runs a fixed schedule regardless of rainfall or soil moisture, and the system uses rotor heads on the turf and drip lines on the beds. Water bills have risen sharply, and the owner must reduce outdoor potable water use for LEED O+M. The owner wants a reduction calculation that reflects the site's actual irrigation demand. Which approach is the MOST accurate way to establish the baseline for the reduction?
Correct Answer: DExplanationHistorical metered irrigation consumption from a dedicated irrigation meter is the defensible baseline because it reflects the actual schedule, system performance, and water use of the existing installation. A flat rainfall calculation ignores the real system and overstates or understates demand. Head count times rated flow assumes continuous operation at maximum, which the controller does not do. Using whole-building consumption would mix irrigation with unrelated uses and misstate the reduction.
-
8 Question 8 Multiple choice Energy and Atmosphere
A 250,000 sq ft hospital outpatient building has a chilled water plant that serves three air handlers. The facilities director has identified that the chillers are cycling frequently at low load during off-peak hours, and that the chilled water supply temperature is held at a fixed setpoint regardless of actual cooling demand. The team must reduce plant energy use within the next year and must not compromise infection-control air change requirements in the clinical areas. Which TWO actions are the MOST appropriate operational strategies to reduce plant energy consumption without violating the clinical requirements? (Choose two.)
Correct Answer: B, DExplanationResetting chilled water supply temperature upward when demand is low, and tying that reset to coil valve position feedback, reduces chiller lift and energy use while keeping every coil able to meet load, which protects the clinical ventilation performance. Lowering outdoor air below the minimum air change rate breaks the clinical requirement. Running all chillers at full capacity increases energy use and does not solve cycling. Shutting off clinical air handlers overnight breaks pressurization and air change requirements in those spaces.
-
9 Question 9 Multiple choice Indoor Environmental Quality
A school district is preparing an O+M indoor air quality management plan for an elementary school built in 1978. The school has a mix of ventilation strategies, including unit ventilators in classrooms with no CO2 sensors and a central air handler serving the gymnasium. Recent cleaning uses a quaternary ammonium product in classrooms and a fragranced aerosol in restrooms. Teachers report headaches during afternoons. The district wants to adopt practices that address ongoing indoor air quality without major capital investment. Which TWO practices are the MOST appropriate to include in the ongoing management program? (Choose two.)
Correct Answer: A, BExplanationVerifying that outdoor air dampers reach their design minimum during occupancy directly addresses ventilation rate delivery, which is a core ongoing operational task in an older system without CO2 monitoring. Switching to low-emitting, fragrance-free cleaning products reduces source emissions that may contribute to the afternoon complaints. Installing exhaust fans does not address the ventilation rate requirement and adds capital cost. Sealing windows and recirculating air eliminates outdoor air supply, which worsens indoor air quality. Increasing cleaner application frequency increases chemical exposure without improving ventilation.
-
10 Question 10 Order list LEED Process
A property owner is starting LEED O+M certification for a 300,000 sq ft office building that was last certified as a new construction project a decade ago. The building's operating data and tenant lease terms have changed substantially, and the team must prove compliance for the current performance period. The team has a project administrator, a consultant, and a set of building operating records from the past two years. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Prepare the documentation package and submit the project for review by USGBC
- Collect and review two years of operating records against each prerequisite requirement
- Address any review comments from the certification body and finalize the submittal
- Confirm the project boundary and define the operational control scope for the building
- Register the project on the LEED Online platform under the existing building record
Correct Answer:- Confirm the project boundary and define the operational control scope for the building
- Register the project on the LEED Online platform under the existing building record
- Collect and review two years of operating records against each prerequisite requirement
- Prepare the documentation package and submit the project for review by USGBC
- Address any review comments from the certification body and finalize the submittal
ExplanationThe project boundary must be settled before any data collection, because it determines which spaces and systems the records cover. Registration then establishes the project record in the platform. Only after registration does data collection against prerequisites proceed, followed by assembling the documentation package and submitting for review. Review comments are addressed last, after the initial submittal has been evaluated. Reversing boundary definition with data collection would risk gathering records for the wrong scope.
-
11 Question 11 Order list Energy and Atmosphere
An energy manager at a 120,000 sq ft mixed-use building has identified excessive overnight energy use in the HVAC system and must build a performance improvement plan for LEED O+M. The manager has access to the building automation system trend logs and a 12-month utility bill history, but no interval data from the utility. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Measure post-implementation energy use over a comparable period and compare it to the baseline
- Implement schedule and setpoint corrections in the building automation system
- Document the verified energy performance improvement and update the operations manual
- Establish a baseline energy use profile from utility bills and trend logs for the pre-improvement period
- Identify the operational cause of the overnight load using trend data for air handlers and pumps
Correct Answer:- Establish a baseline energy use profile from utility bills and trend logs for the pre-improvement period
- Identify the operational cause of the overnight load using trend data for air handlers and pumps
- Implement schedule and setpoint corrections in the building automation system
- Measure post-implementation energy use over a comparable period and compare it to the baseline
- Document the verified energy performance improvement and update the operations manual
ExplanationA baseline must be established first, because every improvement claim is measured against it. The cause is then identified from trend data, which justifies which schedules or setpoints to change. Changes are implemented, and only then is post-implementation energy use measured over a comparable period so it can be compared to the baseline. Documentation and manual updates come last, once the improvement is verified. Changing schedules before identifying the cause risks applying the wrong correction and leaves no defensible before-and-after comparison.
-
12 Question 12 Drag and drop Materials and Resources
A facilities manager at a medical office building is reviewing its O+M materials program for a campus that undergoes frequent interior renovations. The team must match each material management requirement to the service or practice that satisfies it. Match each requirement to the service that meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Reduce the quantity of purchased cleaning chemicals with hazardous contentTrack the recycled content and regional sourcing of replacement finishes purchased during renovationDivert gypsum board and carpet from landfill during each tenant renovationInstallation of on-site composting bins for food waste from tenant kitchensChemical inventory reconciliation and substitution with lower-hazard productsAnnual third-party inspection of the building envelope for material failureSupplier documentation review with product manufacturer dataContracted source-separated waste hauling with recycling facility receiptsCorrect Answer:- Track the recycled content and regional sourcing of replacement finishes purchased during renovation → Supplier documentation review with product manufacturer data
- Divert gypsum board and carpet from landfill during each tenant renovation → Contracted source-separated waste hauling with recycling facility receipts
- Reduce the quantity of purchased cleaning chemicals with hazardous content → Chemical inventory reconciliation and substitution with lower-hazard products
ExplanationRecycled content and regional sourcing are established through supplier documentation tied to each product, so a documentation review is the right service. Diversion of gypsum and carpet depends on contracted separate hauling with receipts from recycling facilities that verify the material was not landfilled. Reducing hazardous chemical purchases is achieved by inventory reconciliation and substitution. Food composting and envelope inspection do not address the stated material requirements for renovation waste and product attributes.
-
13 Question 13 Drag and drop Water Efficiency
A facilities team at a 200,000 sq ft office campus is reducing indoor and outdoor water use under LEED O+M. The team must match each water reduction measure to the outcome it is intended to achieve. Match each measure to the outcome it produces.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Repairing leaks detected by the water submeter during nightly consumption reviewInstalling a soil moisture sensor controller on the turf irrigation zonesReplacing single-flush urinals with high-efficiency models in restroomsSwitching all landscape plantings to high-water-demand turf speciesIrrigation applied only when the root zone needs waterLower indoor water consumption per flush eventIncreasing the pressure setpoint of the domestic water booster pumpElimination of continuous water loss not tied to occupancyCorrect Answer:- Installing a soil moisture sensor controller on the turf irrigation zones → Irrigation applied only when the root zone needs water
- Replacing single-flush urinals with high-efficiency models in restrooms → Lower indoor water consumption per flush event
- Repairing leaks detected by the water submeter during nightly consumption review → Elimination of continuous water loss not tied to occupancy
ExplanationA soil moisture sensor controller reduces outdoor irrigation by applying water only when the soil requires it. High-efficiency urinals lower the volume used per flush, which directly reduces indoor consumption. Repairing detected leaks removes continuous loss that does not correspond to occupancy. Raising booster pump pressure and switching to high-water plantings both increase water use, so they do not match any of the reduction outcomes.
-
14 Question 14 Dropdown Water Efficiency
A facilities engineer at a 40-acre business park is configuring the irrigation controller for a new landscape zone that has drip lines serving shrub beds. The engineer must set the controller so that irrigation runs only in the early morning hours to reduce evaporation and avoid wind drift, with the run frequency kept low to minimize water use. Complete the controller configuration statement by selecting the correct value for each blank.
Choose the correct value for each blank.
Set start time to and set the watering frequency to days per week.Correct Answer:Set start time to 4:00 a.m. and set the watering frequency to Every 3 days per week.
ExplanationEarly morning irrigation around 4:00 a.m. minimizes evaporation and wind drift, which is why the start time is set before dawn. The frequency of every three days reduces total volume compared with daily watering while still supporting shrub beds on drip, which is the lowest interval consistent with the low-frequency goal. Midday and evening starts increase evaporation losses. Daily or every-other-day schedules raise water use beyond what the drip system needs.
-
15 Question 15 Dropdown Indoor Environmental Quality
A property manager at an office building is documenting the ventilation control settings for a demand-controlled ventilation system serving a conference center with variable occupancy. The control logic must respond to measured CO2 rather than run at constant outdoor air, and the manager must document the configuration. Select the correct value for each blank in the sequence description.
Choose the correct value for each blank.
Set the control method to and set the CO2 sensor setpoint for outdoor air increase to ppm above outdoor concentration.Correct Answer:Set the control method to Demand-based CO2 and set the CO2 sensor setpoint for outdoor air increase to 700 ppm above outdoor concentration.
ExplanationDemand-based CO2 control modulates outdoor air in response to measured occupant density, which is what distinguishes it from constant volume or fixed schedule operation. The setpoint of 700 ppm above outdoor concentration is a commonly used threshold for the increase in outdoor air delivery, which provides a working-level response without triggering excessive ventilation at modest occupancy. A 200 or 400 ppm threshold would trigger too readily, while 1000 ppm would allow concentrations higher than typical acceptable limits to persist before any response.
These are 15 of the 168 questions in the full LEED-AP-O-M pack.
Get All 168 QuestionsGet all 168 questions & answers
Full access options for US Green Building Council LEED-AP-O-M
Self-study
PDF Version
- 168 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 168 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 168 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the LEED-AP-O-M Exam (LEED AP Operations + Maintenance) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.