Exam Information
Free practice questions with explanations
US Green Building Council LEED-AP-ID-C Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 15
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Planning and Scoping
A LEED consultant is preparing a LEED v4 Interior Design and Construction project scope for a 40,000 sq ft corporate office fit-out. The client wants to pursue the Interior Design and Construction credit for Daylight but has not yet decided whether to include the existing lobby, which is being retained with no changes. The project team must define the project boundary before modelling and documentation begin. Which action should the consultant take FIRST?
The lobby is outside the leased interior fit-out area and is not being altered by the project. The schedule for the energy and daylight models is tight, and the registration fee is non-refundable once the project is registered.Correct Answer: AExplanationThe project boundary must be set at the start, before modelling, and it should match the space actually being designed and constructed under the project. Because the lobby is retained without change and sits outside the leased fit-out, it belongs outside the boundary and should be documented as excluded. Including it to inflate results is not defensible, and deferring the decision until after simulation would waste modelling effort and risk rework against a tight schedule and non-refundable registration.
-
2 Question 2 Single choice Fieldwork and Evaluation
During construction of a LEED v4 ID+C project, a commissioning consultant must verify that the installed lighting control system meets the specified occupancy sensing and daylight harvesting requirements. The contractor reports that all sensors were installed per drawings. The consultant has limited time on site and a fixed inspection budget. The most sensitive zones are open-plan areas near the glazing, where daylight response is critical to the performance claim.
Which fieldwork approach provides the most reliable evidence of control effectiveness?Correct Answer: AExplanationVerifying control effectiveness requires observing the system respond, so functional testing of sampled sensors in the perimeter zones gives direct evidence of daylight harvesting behaviour. Checklists and data sheets prove intent, not performance, and a panel showing communication confirms connectivity but not correct response. A single midday measurement on a clear day captures only one condition and cannot show the control's response across varied daylight levels.
-
3 Question 3 Single choice Reporting, Recommendations, and Follow-Up
A LEED consultant completes a pre-submission review of an Interior Design and Construction project and identifies that the submitted indoor air quality documentation omits the measured CO2 levels for two occupied floors. The project team has a submission deadline in five days. The client's project manager asks the consultant to simply recommend the team resubmit the full package next quarter so the issue can be handled in the normal review cycle.
What is the most appropriate recommendation?Correct Answer: DExplanationThe consultant should give a specific, actionable recommendation tied to the deadline: supply the actual measured CO2 data with the method used, and verify the correction before submission. Submitting incomplete documentation and waiting for a review query risks an adverse finding. Dropping the credit abandons achievable points without need, and substituting estimated design values for measured data misrepresents performance and fails the documentation requirement.
-
4 Question 4 Single choice Corporate Governance and the Audit Function
A multinational company has its LEED-certified interior projects managed by a regional sustainability team, while the procurement team independently selects finish materials. Recent project submissions have shown inconsistent material declarations, and two projects failed to document Material Ingredient Reporting. The chief operating officer wants a governance structure that reliably prevents these recurrences across all future projects without slowing delivery. Which governance measure is most effective?
The company operates in eleven countries, and each regional team uses its own procurement vendors.Correct Answer: DExplanationEffective governance here means clear accountability and a control point before commitments are made. Assigning an owner for compliance documentation, with shared responsibilities defined with procurement and a verification gate at specification approval, addresses the root cause of inconsistent declarations. Shifting responsibility to a consultant after specification is too late to influence choices, post-occupancy surveys do not address documentation, and full centralisation ignores the stated regional vendor structure and would disrupt delivery.
-
5 Question 5 Multiple choice Planning and Scoping
A LEED consultant is scoping a LEED v4 ID+C project for a tenant fit-out in a multi-tenant building. The client wants the project to be certified quickly and has a limited budget for consultant time. Which TWO planning actions should the consultant take before committing to the credit strategy? (Choose two.)
Correct Answer: B, DExplanationA tenant fit-out can only claim credits over systems and data it controls or can obtain, so confirming lease terms and control over building systems is essential before committing to strategy. Identifying credits that rely on building-level information and securing the owner's data commitment prevents planned points from becoming unachievable. Assuming base building credit, pursuing everything regardless of feasibility, and deferring strategy until after documents are final all waste limited consultant budget and risk unattainable credits.
-
6 Question 6 Single choice Fieldwork and Evaluation
A commissioning agent is evaluating the accuracy of a contractor's construction waste diversion report for a LEED ID+C interior project. The report states 82 percent of waste was diverted from landfill. The agent reviews the hauler weigh tickets and finds that some tickets are for mixed loads hauled to a transfer station, which the report counts as diverted. The agent must decide how to assess the reliability of the reported figure.
What is the most appropriate evaluation step?Correct Answer: CExplanationReliable evaluation means tracing the evidence rather than accepting a headline figure. Mixed loads sent to a transfer station are not automatically diverted, so the agent must confirm the destination and recovery method for each load and recalculate using only verified diversion. A third-party certification of the tracking system does not validate individual tickets, averaging across other projects does not check this project's data, and revising the figure upward to inflate the total is unsupported.
-
7 Question 7 Single choice Reporting, Recommendations, and Follow-Up
A LEED consultant has identified three findings from the pre-submission review of an interior project and must match each finding to the follow-up action that best addresses it.
1. Ventilation calculations use a superseded occupant density value.
2. The low-emitting material documentation lists products without manufacturer certificates.
3. The lighting schedule does not match the approved lighting design drawings.
Targets:
Correct the calculation and rerun the affected ventilation analysis with the verified occupant density.
Obtain and attach the manufacturer certificates for each listed product.
Reconcile the lighting schedule against the approved drawings and issue a revised schedule.
Which mapping is correct?Correct Answer: DExplanationA superseded occupant density invalidates the ventilation calculation, so that analysis must be corrected and rerun. Missing manufacturer certificates for low-emitting materials require obtaining and attaching them as evidence. A lighting schedule that departs from approved drawings must be reconciled against those drawings. The other mappings pair each finding with a remedy that does not fix its specific defect, such as attaching certificates to a calculation problem.
-
8 Question 8 Single choice Planning and Scoping
A LEED consultant is establishing the scope for a project that includes a high-performance conference center within a larger interior fit-out. The owner wants the conference center to be treated as a separate project for scoring purposes, but the mechanical ventilation serving the conference center is shared with the adjacent open office. The consultant must decide how to define the project boundary and resource needs before committing to the modelling plan.
Which approach best meets the requirements?Correct Answer: DExplanationBoundary definition should reflect the owner's intended scope while the modelling plan accounts for the physical reality of a shared ventilation system. Keeping the conference center as its own boundary and modelling how the shared system serves both spaces produces defensible results. Excluding the space to avoid modelling sacrifices a scope element the owner wants, ignoring the shared supply is technically inaccurate, and arbitrary floor-area splitting without recorded airflow lacks a defensible basis.
-
9 Question 9 Order list Fieldwork and Evaluation
A commissioning consultant must verify that the demand-controlled ventilation for a LEED ID+C project operates as designed. The steps below are shuffled. Place them in the correct order for an effective verification. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Confirm sensor calibration and placement at the locations specified in the design.
- Record measured data across varying occupancy conditions.
- Compare measured CO2 response and damper or fan behaviour against the design sequence.
- Document deviations and confirm corrections with a retest.
- Review the design sequence of operations and the approved sensor locations.
Correct Answer:- Review the design sequence of operations and the approved sensor locations.
- Confirm sensor calibration and placement at the locations specified in the design.
- Record measured data across varying occupancy conditions.
- Compare measured CO2 response and damper or fan behaviour against the design sequence.
- Document deviations and confirm corrections with a retest.
ExplanationVerification starts by understanding the intended operation through the design sequence and approved sensor locations, then confirms the sensors are calibrated and correctly placed before relying on their readings. Data is recorded across varying occupancy, compared against the design sequence, and any deviations are documented and retested. Comparing behaviour before recording data, or retesting before documenting deviations, reverses the evidence chain and undermines the conclusion.
-
10 Question 10 Dropdown Corporate Governance and the Audit Function
Which pair of values correctly completes the statement? Choose the correct value for each blank.
Choose the correct value for each blank.
A company's internal audit reviews the sustainability reporting control for LEED documentation. The control requires that a document be reviewed by a second person before submission. The audit finds that the reviewer role is assigned to the same individual who prepares the documents for two projects. To correct this, the audit recommends applying the segregation of duties principle, meaning that must be separated from .Correct Answer:A company's internal audit reviews the sustainability reporting control for LEED documentation. The control requires that a document be reviewed by a second person before submission. The audit finds that the reviewer role is assigned to the same individual who prepares the documents for two projects. To correct this, the audit recommends applying the segregation of duties principle, meaning that preparation of the documentation must be separated from review and approval of the documentation.
ExplanationSegregation of duties in a documentation control separates the person who creates evidence from the person who reviews and approves it, which is exactly the failure described. Pairing review with storage or budget approval with scheduling does not address the conflict of preparing and reviewing the same document. Separating submission from archiving also misses the core control weakness.
-
11 Question 11 Single choice Reporting, Recommendations, and Follow-Up
A LEED consultant has reported to a client that a project's energy model shows a 14 percent improvement over the baseline. Six weeks later, the design team adds an exterior shading device that reduces cooling loads. The client asks the consultant to note the change in the existing report and carry on. The client's regulatory deadline for the certification package is in three weeks, and the consultant must ensure the reported results remain accurate and traceable.
What is the most appropriate follow-up action?Correct Answer: CExplanationA design change affecting cooling loads changes the modelled outcome, so the energy model must be rerun and the report revised with a version record so the reported figures trace to the actual design. Simply noting the device in a cover letter leaves the result unsupported, adding an estimated percentage to the old figure is not a valid model output, and dropping the energy result abandons a credit the project can still document.
-
12 Question 12 Multiple choice Corporate Governance and the Audit Function
A large organisation is reviewing how its governance framework supports reliable LEED documentation across multiple interior projects. The audit committee notes that project teams report findings directly to individual project managers, with no escalation path. Which TWO governance measures would most improve oversight and accountability? (Choose two.)
Correct Answer: A, EExplanationAn escalation path to an independent oversight role, combined with periodic reporting of discrepancies and tracked corrective actions, creates visible accountability at the governance level. Leaving escalation to individual judgement weakens oversight, removing reviews for smaller projects removes a control that protects accuracy, and combining delivery with independent verification defeats the purpose of verification.
-
13 Question 13 Single choice Fieldwork and Evaluation
A commissioning consultant is testing whether a building automation system's occupancy-based lighting control meets the design requirement that lights shut off within 20 minutes of the last detected movement in unoccupied spaces. The consultant has access to the controller's event log, and a test technician can walk through the space and leave it empty. The project has a tight schedule and the consultant must decide on the most effective test.
Which test provides the strongest evidence of effectiveness?Correct Answer: DExplanationObserving the system respond to real occupancy changes and timing the interval from last movement to lights off gives direct evidence against the 20-minute requirement. A configured timeout shows intent but not behaviour, a green status indicator confirms only connectivity, and staff recollection is anecdotal and does not measure the control's performance.
-
14 Question 14 Single choice Planning and Scoping
A LEED consultant is assessing whether a project meets the regulatory and standards requirements before the scope is approved. The project is located in a jurisdiction that requires a specific ventilation standard, while the LEED credit references a different ventilation standard. The client asks which standard the design must satisfy to be compliant.
What should the consultant advise?Correct Answer: DExplanationA project must satisfy legal requirements in its jurisdiction and also meet the credit it is pursuing, so the consultant should identify the more stringent requirement and document compliance against both. Relying on only the LEED reference ignores binding local law, choosing the cheaper option assumes equivalence that is not stated, and treating credits as optional misreads their documentation requirements.
-
15 Question 15 Dropdown Reporting, Recommendations, and Follow-Up
Which pair of values correctly completes the statement? Choose the correct value for each blank.
Choose the correct value for each blank.
A LEED consultant is writing the follow-up log for a project's open findings. Each finding must be tracked until it is closed with evidence. A finding is considered when the corrective action has been implemented and the evidence has been by the consultant.Correct Answer:A LEED consultant is writing the follow-up log for a project's open findings. Each finding must be tracked until it is closed with evidence. A finding is considered closed when the corrective action has been implemented and the evidence has been verified by the consultant.
ExplanationA finding should be closed only after the corrective action is implemented and the consultant has verified the supporting evidence, which is what makes follow-up meaningful. Archiving a finding or drafting evidence does not establish that the issue was resolved, a proposed correction is not yet closed, and escalating a finding is a routing step rather than a closure.
These are 15 of the 100 questions in the full LEED-AP-ID-C pack.
Get All 100 QuestionsGet all 100 questions & answers
Full access options for US Green Building Council LEED-AP-ID-C
Self-study
PDF Version
- 100 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 100 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 100 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the LEED-AP-ID-C Exam (LEED AP Interior Design + Construction V4) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.