2026 Actual Huawei H19-105_V2.0 Dumps, Updated Exam Questions for Guaranteed Pass

HCSA-Sales-Data Center Facility - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorHuawei
Exam codeH19-105_V2.0
Exam nameHCSA-Sales-Data Center Facility
Questions in pack60
Last updatedNovember 25, 2026
VersionV2.0
Related certificationsHuawei Certified Sales Associate

Free practice questions with explanations

Huawei H19-105_V2.0 Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
15
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Data Center Facility Overview

    A regional bank is building a new Tier III-equivalent data center to host its core banking workloads. The customer requires concurrent maintainability so that any power or cooling path can be taken offline for planned maintenance without shutting down IT loads. The site has a limited budget and the customer rejects any design that doubles the entire power infrastructure at every level. The sales consultant must recommend a power architecture for the UPS and distribution layer. Which recommendation best meets the availability target while respecting the budget constraint?

  2. 2 Question 2 Single choice Power and Cooling Planning

    A telecom operator plans to deploy a high-density AI training cluster in an existing data hall. Each rack will draw about 35 kW, while the hall was designed for 6 kW per rack with air cooling. The operator wants to avoid a full building refit within 90 days and must keep the existing chilled-water loop unchanged. The sales engineer proposes a cooling solution for the hot aisle of the high-density racks. Which proposal is the most appropriate for this constraint?

  3. 3 Question 3 Single choice Environmental Monitoring and Operations

    A government client operates a data center where the facility manager reports intermittent overheating alarms in one cold aisle, but the existing monitoring only tracks average room temperature. The client requires root-cause evidence within a week and has a policy that no new sensors may be mounted inside active server cabinets without a change approval that takes three weeks. The sales team is asked to propose the most effective monitoring enhancement. Which action should be recommended first?

  4. 4 Question 4 Single choice Physical Security and Access Control

    A financial services firm is designing access control for a colocation-style data hall that hosts several tenants. Auditors require that every entry into the caged area be logged with the identity of the individual and that no single staff member can both approve and execute an access request. The site already has a card reader system at the building entrance. Budget allows one additional control layer only at the cage door. The sales consultant must recommend the control that best satisfies both requirements. Which option should be proposed?

  5. 5 Question 5 Multiple choice Fire Protection and Safety

    A healthcare provider is commissioning a data center room that houses critical imaging servers. The room has a suspended ceiling and a raised floor. The provider requires fire suppression that will not damage electronics, must not require the room to be evacuated for every small event, and must comply with its insurer's requirement for early detection. The budget is limited and the sales engineer must select the components to propose. (Choose two.)

  6. 6 Question 6 Multiple choice Network Infrastructure Cabling

    A logistics company is refreshing the structured cabling for a new data center hall that will host 400G spine switches and high-density top-of-rack switches. The design target is a 20-year cable plant lifetime with support for future speed upgrades, and the cabling contractor has proposed low-cost cable types to reduce capital cost. The sales engineer must advise on the media choices that meet the forward-compatibility requirement. (Choose two.)

  7. 7 Question 7 Single choice Data Center Power Efficiency

    A cloud service provider is marketing its new facility to enterprise customers and must present an energy efficiency metric. The customer's procurement team asks for a figure that shows how efficiently the facility delivers power to IT equipment across a full year, rather than a single snapshot. The provider has metered total facility energy and IT equipment energy at the utility feed and at the UPS output. The sales team must select the correct metric to present. Which metric should be proposed?

  8. 8 Question 8 Drag and drop Data Center Facility Operations

    A manufacturing company is reviewing its data center operations contract and must map each operational requirement to the most suitable facility service or practice to propose. The requirements include detecting impending UPS battery failure before an outage, verifying that the standby generator will carry the load during a utility loss, and documenting the facility's capacity and power headroom for planning. Match each requirement to the service or practice that meets it.

    Drag each item onto its matching target. On a phone: tap an item, then tap a target.

    Document available power and cooling headroom for planning
    Detect impending UPS battery failure before an outage occurs
    Verify the standby generator will carry the critical load during a utility loss
    Scheduled battery impedance and capacity testing
    Annual repainting of the generator enclosure
    Periodic full-load generator test with automatic transfer
    Quarterly visual inspection of cabinet door seals
    Capacity management report from DCIM power and cooling data
  9. 9 Question 9 Drag and drop Hardware Lifecycle and Sustainability

    A retail chain is decommissioning an older data center and must recommend how each category of retired equipment should be handled to meet its sustainability and data protection policies. The categories include server drives that held customer payment records, legacy UPS lead-acid batteries, and obsolete network switches that are still functional. Match each category to the disposal approach to propose.

    Drag each item onto its matching target. On a phone: tap an item, then tap a target.

    Functional but obsolete network switches
    Server drives holding customer payment records
    Legacy UPS lead-acid batteries
    Licensed hazardous waste recycling with a take-back agreement
    Certified data sanitisation or physical destruction with a destruction certificate
    Storage on site indefinitely pending a future project
    Certified resale or donation after configuration wipe
    Landfill disposal in general waste bins
  10. 10 Question 10 Order list Facility Planning and Deployment

    A utility company is opening a new data hall and must deliver it on a fixed schedule before a regulatory reporting deadline. The sales project lead must sequence the key facility activities so that the hall is safely energised and accepted. Arrange the steps in the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Perform the level 5 commissioning of the environmental controls and monitoring
    2. Install the cooling units and confirm the chilled-water loop pressure test
    3. Complete the integrated systems test with the UPS and generator under load
    4. Hand over the hall with the operations and maintenance documentation
    5. Commission the power distribution and verify earthing and bonding
  11. 11 Question 11 Order list Facility Change and Incident Response

    A hosting provider experiences a sudden rise in cold-aisle temperature in one row during a hot afternoon. The facility team must respond to protect the IT load while preserving evidence for the root-cause review. Arrange the steps in the order they must be performed.

    Drag the steps into the correct order, or use the arrows.

    1. Reduce the workload or migrate virtual machines away from the hottest racks
    2. Confirm the alarm against the inlet sensors on the affected row
    3. Restore normal setpoints and schedule a root-cause analysis
    4. Check cooling unit status and filter condition on the affected cooling path
    5. Record the temperature readings and actions taken in the incident log
  12. 12 Question 12 Dropdown Power Distribution and Monitoring

    A data center operator must configure a power monitoring interface so that the facility team receives early warning when a PDU branch circuit approaches its safe load limit. The company policy is that alarms should trigger at 80 percent of rated capacity, and the monitoring must be applied to each branch circuit. Complete the configuration statement by selecting the correct value for each blank.

    Choose the correct value for each blank.

    set alarm-threshold percent-of-rated-capacity scope branch-circuit-level
  13. 13 Question 13 Dropdown Data Center Cooling Management

    A colocation operator is adjusting the air handling settings for a hall with mixed-density racks to reduce energy use without creating hot spots. The sales engineer must document the recommended control strategy in the operator's change record. Complete the statement by selecting the correct value for each blank.

    Choose the correct value for each blank.

    Set the cooling control mode to using supply air sensors across the cold aisle
  14. 14 Question 14 Single choice Data Center Standards and Compliance

    A pharmaceutical company is building a validated data center and its quality team requires that facility design documents follow a recognised international standard for availability classification, so that the design can be audited against a published set of criteria. The company wants the classification to describe the redundancy and maintainability of the site's infrastructure. The sales consultant must advise which reference to cite in the proposal. Which should be recommended?

  15. 15 Question 15 Multiple choice Facility Risk and Resilience

    A stock exchange member firm is reviewing the resilience of its data center after a near-miss in which a single feeder failure caused a partial outage. The board requires that the facility can survive a utility feed loss and a single cooling path failure without service interruption, and it has asked the sales team to recommend the measures that address these two risks. The budget excludes building a second data center. (Choose two.)

These are 15 of the 60 questions in the full H19-105_V2.0 pack.

Get All 60 Questions

Get all 60 questions & answers

704 Satisfied customers
93% Pass rate feedback
83.7% Said questions matched
93% Found material helpful

Full access options for Huawei H19-105_V2.0

Self-study

PDF Version

$40.00 $20.00
  • 60 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 60 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the H19-105_V2.0 Exam (HCSA-Sales-Data Center Facility) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed