Exam Information
Free practice questions with explanations
Huawei H19-260_V2.0 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 10
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Introduction to Huawei Smart PV C&I Solution
A regional manufacturer with a 1.2 MW rooftop roof area runs two shifts and pays a demand charge based on its peak 15-minute kW draw in the evening. The customer wants the C&I solution to lower its electricity bill without exporting power to the grid, and the site has a 600 kVA transformer with no spare capacity for expansion. The sales engineer proposes adding a battery system to shave the evening peak. Which configuration best meets the customer's goals?
Correct Answer: AExplanationPeak shaving with zero-export control uses the battery to cover evening demand spikes while the PV plant is limited so no power flows back to the grid, which fits both the demand-charge goal and the no-export constraint. Sizing against the measured load profile respects the limited transformer capacity. Leaving export at full transformer rating would push power into the grid, violating the stated no-export requirement. Charging a battery only from the grid ignores the PV asset and the energy savings it provides. Deferring storage until a transformer upgrade fails to address the peak demand charge the customer is paying today.
-
2 Question 2 Single choice Introduction to Huawei Smart PV Plant Solution
A utility-scale developer is designing a 100 MW PV plant in a region with frequent grid voltage dips and a grid operator requirement that the plant support reactive power during faults. The developer also wants to reduce capex on the DC side. The design team is evaluating string-level energy storage against a centralised containerised battery at the point of interconnection. Which design choice best satisfies the plant-level requirements?
Correct Answer: AExplanationA Smart String ESS design places storage close to each string and relies on a plant controller to coordinate active and reactive power so the whole plant meets grid code requirements during voltage dips. This avoids a single large storage asset and keeps DC-side cost manageable. Running inverters at unity power factor removes the reactive support the operator demands. Independent local setpoints without coordination cannot guarantee a plant-level response to the grid operator. Adding a separate static var compensator is outside the stated solution scope and misses the distributed storage goal that drives the design.
-
3 Question 3 Single choice Introduction to Huawei Smart PV Residential Solution
A homeowner in an area with time-of-use tariffs has a 6 kWp rooftop PV system with a hybrid inverter and a 10 kWh battery. The homeowner reports that the battery is discharging to the household during the afternoon, even though the export tariff is high and the household is occupied only in the evening. The installer wants to maximise self-consumption while keeping the battery available for the evening peak tariff window. Which change should the installer make first?
Correct Answer: AExplanationThe hybrid inverter's time-of-use schedule lets the installer define when the battery charges from PV and when it discharges, so afternoon energy is stored for the evening peak rather than consumed early. Enlarging the array does not change how the battery is scheduled and adds cost. Disabling the battery forfeits the evening peak saving that the homeowner wants. Forcing grid charging overnight and full-power discharge all day wastes the battery against the stated tariff structure and goes against the self-consumption goal.
-
4 Question 4 Single choice Introduction to Smart PV Partner Policies Outside China
A sales partner holding a basic certification wants to bid on a commercial PV project that requires the partner to sign the regional end-customer contract and receive the associated partner incentive. The partner's sales manager asks which certification level must be achieved before the partner can take the lead on the contract and claim the higher incentive tier. The partner has passed the product training but has not yet completed the advanced sales certification. What should the sales manager do first?
Correct Answer: AExplanationPartner positioning, certification and incentive eligibility are tied together, so the partner must hold the required certification level in good standing before leading the contract and claiming the higher tier. Product training alone does not establish the certification needed for lead status. Routing the contract directly to the vendor removes the partner's role the partner is trying to secure. Asking for a routine review exemption bypasses governance rather than meeting the certification requirement.
-
5 Question 5 Single choice Partner Quality Management
A partner's SQA reviews a recent utility-scale installation and finds that the partner's inspection checklist was signed off for the string combiner boxes before torque verification was completed on the DC terminals. The project is scheduled for energisation in three days, and the partner's quality system requires that all critical process records be complete before a stage gate is passed. The site manager argues the check is a formality. What is the most appropriate action for the SQA to take next?
Correct Answer: AExplanationA quality system that requires complete process records before a stage gate means the SQA must stop the gate until the torque verification is recorded and verified, and the premature sign-off is a nonconformance to be logged. Deferring the check to commissioning or energisation pushes a critical verification past the point where a loose DC terminal can be corrected cheaply and safely. Relying on monitoring after energisation detects faults only after they have occurred and may involve live equipment.
-
6 Question 6 Multiple choice Safety Management
A partner is preparing to install a 150 kW PV plant with string inverters on a steel-framed building roof. The project team plans to store the modules and inverters on the roof deck for two weeks while crews finish the mounting structure. Site constraints include strong afternoon winds, a DC voltage on the strings that will exceed safe touch limits once modules are connected, and a shortage of qualified electricians on the first day. Which TWO actions best meet the general safety requirements for storage and installation? (Choose two.)
Correct Answer: B, EExplanationStoring equipment in its original packaging, secured against wind and within the stacking limit prevents damage and falls, and keeping DC connection tasks with qualified electricians addresses the shock risk from strings above safe touch voltage. Connecting strings before the mounting work and installation are complete exposes workers to live DC. Leaving modules unpacked overnight invites wind damage and unauthorised access. Using labourers for DC wiring under loose supervision fails the requirement that only qualified personnel handle live circuits.
-
7 Question 7 Single choice Safety Management
A maintenance crew is scheduled to replace a faulty DC isolator on a 1.5 MW PV plant during daylight hours. The strings remain connected to the inverter, and the site supervisor proposes opening the AC breaker only and proceeding immediately to avoid lost generation. The plant's safety procedure requires that the work area be isolated, verified de-energised, and locked out before any work on DC equipment begins. What should the crew do first?
Correct Answer: AExplanationPV strings keep producing DC whenever there is light, so an AC breaker opening does not de-energise the DC side, and the crew must isolate both AC and DC sources, verify with a meter and lock out before touching the isolator. Assuming the inverter stops DC flow once the grid is removed is a dangerous misconception. Insulating tape on a live isolator is not an accepted isolation method. Remote monitoring shutdown does not guarantee the strings are de-energised for the physical work.
-
8 Question 8 Multiple choice Introduction to Huawei Smart PV Plant Solution
A developer is comparing two designs for a 50 MW plant on a site with significant afternoon cloud cover, and a grid code that requires ramp-rate control of active power at the point of interconnection. The developer wants to avoid over-sizing the DC and AC infrastructure. Which THREE design measures best address these requirements? (Choose three.)
Correct Answer: A, B, CExplanationA plant-level controller enforcing a configured ramp-rate limit at the point of interconnection satisfies the grid code directly, and distributed storage absorbs the fast fluctuations caused by passing clouds. Sizing storage and inverters against the measured irradiance and ramp-rate requirement avoids over-building the infrastructure. Oversizing AC cables to full DC capacity inflates cost without solving the ramp problem. Matching the DC-to-AC ratio to module nameplate without regard to irradiance ignores the site profile and risks unnecessary clipping and cost.
-
9 Question 9 Single choice Introduction to Huawei Smart PV Residential Solution
A residential installer is commissioning a 5 kWp hybrid PV system with a 10 kWh battery for a household that has a backup supply requirement during grid outages. During commissioning, the installer discovers that the backup loads switch over correctly but the battery state of charge drops much faster than expected during the outage test. The household's critical loads include a refrigerator and two electric heating appliances that the customer has asked to be kept on during outages. What is the most appropriate change to the installation design?
Correct Answer: AExplanationThe battery is draining quickly because high-power resistive heating loads on the backed-up circuit exceed what the 10 kWh battery can sustain for a useful duration, so moving those appliances off the backed-up circuit matches the load to the design. Adding battery capacity or PV array size does not fix a loads-versus-energy mismatch at outage time. Disabling backup removes the outage protection the customer specifically asked for.
-
10 Question 10 Single choice Partner Quality Management
A partner's SQA is building a plan to improve the quality capability of its installation teams across several regional offices. The partner is subject to a quality management system requirement that each stage gate has documented ownership, and the SQA role is required to provide independent oversight rather than doing the field work itself. Management wants the SQA to be effective in the short term while preserving the independence the quality system requires. What is the most appropriate key task for the SQA to lead first?
Correct Answer: AExplanationDefining checkpoints and stage-gate criteria, then auditing records independently, builds quality capability while keeping the SQA's oversight role separate from execution, which the quality system requires. Taking over installation supervision blurs independence because the SQA would be checking its own work. Approving self-inspection without evidence removes the verification function. Delegating quality records to sales conflicts with the requirement for independent oversight and places records outside the quality function.
These are 10 of the 60 questions in the full H19-260_V2.0 pack.
Get All 60 QuestionsGet all 60 questions & answers
Full access options for Huawei H19-260_V2.0
Self-study
PDF Version
- 60 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 60 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 60 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the H19-260_V2.0 Exam (HCSA-Sales-Smart PV V2.0) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.