Free practice questions with explanations

CIPS L5M8 Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
11
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Understand approaches to the planning and management of projects and change initiatives

    A regional public-sector procurement unit is launching a three-year e-tendering system replacement. The project board includes the Director of Finance, the Head of Procurement and the IT Director. Early reports show the project is 15% over budget and the sponsor has been absent from two of the last four board meetings. The Project Manager has been reporting progress using only task completion percentages, which the board finds hard to interpret against the business case. The board has 30 days before the next funding tranche is released and must decide whether to continue. Which action should the Project Manager take FIRST to give the board a basis for the funding decision?

  2. 2 Question 2 Single choice Understand approaches to the planning and management of projects and change initiatives

    A procurement function is delivering a category-wide sourcing transformation with several parallel workstreams. The programme team is a matrix structure: analysts report to the Head of Category for line management but are assigned to projects by a programme office. Analysts are currently being pulled between two workstreams with conflicting deadlines, and the workstream leads say their work is being delayed without clear authority to resolve the conflict. Governance rules prevent the programme office from altering line reporting lines in the current financial year. Which action is MOST appropriate to resolve the dispute?

  3. 3 Question 3 Single choice Understand aspects of projects in organisations

    A health authority is procuring a new patient-transport fleet service. The contract will be delivered by a joint venture between a logistics provider and a local SME, and the authority requires that key performance indicators cover safety, quality, cost and delivery. The Procurement Project Manager has drafted a work breakdown structure with twelve top-level elements, several of which overlap with the JV partners' internal workflows. The partners have not yet agreed who will own the vehicle maintenance scope, and the authority's contract manager needs a measurable baseline within six weeks. Which action should the Project Manager take NEXT?

  4. 4 Question 4 Single choice Understand aspects of projects in organisations

    A manufacturing buyer runs a supplier development project that depends on three tier-two sub-contractors providing critical castings. The project schedule is being compressed to meet a plant shutdown date, and resource loading shows the castings supplier is over-allocated by 40% in the sixth and seventh weeks. The buyer has a contractual right to request schedule changes but has limited budget for expedited freight. Which scheduling action best resolves the over-allocation while protecting the shutdown date?

  5. 5 Question 5 Single choice Understand the concept of organisational change and how it can be achieved

    A mid-sized retailer's procurement department has operated with decentralised buying for twenty years. A new category strategy is being introduced that centralises spend on forty indirect categories. Staff in regional buying offices have been told the change is minor, but several have already begun withholding supplier data and some have started negotiating new side agreements. The change lead must select a response that addresses the emerging resistance and cynicism without delaying the centralisation timeline by more than one quarter. Which action is MOST appropriate?

  6. 6 Question 6 Single choice Understand the concept of organisational change and how it can be achieved

    A logistics company's procurement function has been through three incremental process changes in two years, each announced as the last. Staff now describe the transformation programme as a cycle with no end point, and engagement scores have fallen sharply. The programme board wants to introduce a fourth initiative, a digital supplier onboarding platform, which must be completed by the end of the financial year. The change lead must decide how to position this initiative. Which approach best addresses the challenge of maintaining change in an environment already showing change fatigue?

  7. 7 Question 7 Single choice Understand the concept of organisational change and how it can be achieved

    A public utility's procurement team has recently changed leadership. The new Director has initiated a review that identifies a widening gap between the team's current capability and the demands of an emerging market for renewable energy contracts. The team's SWOT analysis highlights strong supplier relationships but weak analytical skills, and PEST analysis shows tightening regulatory requirements on supply-chain carbon reporting within eighteen months. The Director wants to categorise the change required before committing resources. Which type of organisational change best describes the required response?

  8. 8 Question 8 Single choice Understand approaches to the planning and management of projects and change initiatives

    A pharmaceutical procurement team is delivering a supplier risk programme. Its risk register currently records twenty-five risks, each rated on likelihood and impact, but the register has not been reviewed since the programme began. A recent supplier insolvency revealed that two risks rated as low had been linked to the affected supplier. The programme sponsor has asked for a method to test how risk events could combine to affect total programme cost, and the finance team requires a probabilistic range rather than a single contingency figure. Which technique should the Project Manager adopt to meet this requirement?

  9. 9 Question 9 Single choice Understand approaches to the planning and management of projects and change initiatives

    A procurement project to introduce category management in a construction firm has a risk register with clear owners for each risk. However, several supply chain risks have been assigned to the Head of Procurement even though the affected sub-contractors are managed by the Operations Director. Two risks have had no review for four months, and the project board has asked for the register to be reformed so that accountability reflects who can actually act. Which action is MOST appropriate?

  10. 10 Question 10 Multiple choice Understand aspects of projects in organisations

    A government department is planning a joint procurement project with two neighbouring authorities to deliver a shared records-management system. The three authorities will share costs, but their governance structures differ and the project must be managed without any single authority taking over the others. The Project Manager is preparing the project structure and must choose the arrangements that best meet these requirements. Which TWO actions should the Project Manager take? (Choose two.)

  11. 11 Question 11 Multiple choice Understand the concept of organisational change and how it can be achieved

    A logistics firm's procurement function is experiencing environmental turbulence following a merger, with a new reporting structure, two competing supplier management systems and uncertainty over which category managers will remain. Several managers have voiced scepticism about the leadership's commitment to the change, and early adopters report being ignored by senior staff. The change lead must select actions to reduce resistance and maintain momentum over the next nine months. Which THREE actions are MOST appropriate? (Choose three.)

These are 11 of the 88 questions in the full L5M8 pack.

Get All 88 Questions

Get all 88 questions & answers

711 Satisfied customers
95.9% Pass rate feedback
84.2% Said questions matched
93% Found material helpful

Full access options for CIPS L5M8

Self-study

PDF Version

$40.00 $20.00
  • 88 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 88 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L5M8 Exam (Project and Change Management) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed