Exam Information
Free practice questions with explanations
CIPS L5M8 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 11
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understand approaches to the planning and management of projects and change initiatives
A regional public-sector procurement unit is launching a three-year e-tendering system replacement. The project board includes the Director of Finance, the Head of Procurement and the IT Director. Early reports show the project is 15% over budget and the sponsor has been absent from two of the last four board meetings. The Project Manager has been reporting progress using only task completion percentages, which the board finds hard to interpret against the business case. The board has 30 days before the next funding tranche is released and must decide whether to continue. Which action should the Project Manager take FIRST to give the board a basis for the funding decision?
Correct Answer: AExplanationWith a funding decision due in 30 days, the board needs evidence tied to the business case, and an exception report that compares forecast cost and benefits against the approved case gives them exactly that. Re-baselining the initiation document would come only after the board decides whether to continue, and a responsibility matrix or a governance escalation addresses ownership rather than the immediate information gap. The sponsor absence matters, but it does not supply the figures the board needs this month.
-
2 Question 2 Single choice Understand approaches to the planning and management of projects and change initiatives
A procurement function is delivering a category-wide sourcing transformation with several parallel workstreams. The programme team is a matrix structure: analysts report to the Head of Category for line management but are assigned to projects by a programme office. Analysts are currently being pulled between two workstreams with conflicting deadlines, and the workstream leads say their work is being delayed without clear authority to resolve the conflict. Governance rules prevent the programme office from altering line reporting lines in the current financial year. Which action is MOST appropriate to resolve the dispute?
Correct Answer: CExplanationThe matrix structure is itself the cause, but the constraint forbids changing reporting lines this year, so the fix must work within the matrix. A documented prioritisation rule with a named escalation owner gives both managers a shared decision mechanism. Converting to a projectised structure breaks the stated governance constraint, and reverting to a functional structure would remove the programme-level coordination the project needs. Hiring contractors adds cost and does not address the shared-resource conflict.
-
3 Question 3 Single choice Understand aspects of projects in organisations
A health authority is procuring a new patient-transport fleet service. The contract will be delivered by a joint venture between a logistics provider and a local SME, and the authority requires that key performance indicators cover safety, quality, cost and delivery. The Procurement Project Manager has drafted a work breakdown structure with twelve top-level elements, several of which overlap with the JV partners' internal workflows. The partners have not yet agreed who will own the vehicle maintenance scope, and the authority's contract manager needs a measurable baseline within six weeks. Which action should the Project Manager take NEXT?
Correct Answer: CExplanationA work breakdown structure only supports measurement when each element has a clear owner, and here the overlap with partner workflows is what leaves the maintenance scope unowned. Mapping each element to an accountable owner within the agreed JV split creates the baseline the contract manager needs inside six weeks. A single flat deliverables list loses the decomposition needed for measurement, deferring KPIs to after go-live breaks the six-week requirement, and transferring scope to the authority contradicts the outsourcing intent.
-
4 Question 4 Single choice Understand aspects of projects in organisations
A manufacturing buyer runs a supplier development project that depends on three tier-two sub-contractors providing critical castings. The project schedule is being compressed to meet a plant shutdown date, and resource loading shows the castings supplier is over-allocated by 40% in the sixth and seventh weeks. The buyer has a contractual right to request schedule changes but has limited budget for expedited freight. Which scheduling action best resolves the over-allocation while protecting the shutdown date?
Correct Answer: DExplanationResource levelling moves activities within their float to smooth demand against available capacity, which is what the over-allocated weeks require, and it keeps the shutdown date because only non-critical orders move. Resource smoothing reduces peaks without changing the end date but cannot resolve a 40% overload that exceeds the float available. A buffer does not reduce load, and removing the castings from the critical chain would hide the very dependency that threatens the shutdown.
-
5 Question 5 Single choice Understand the concept of organisational change and how it can be achieved
A mid-sized retailer's procurement department has operated with decentralised buying for twenty years. A new category strategy is being introduced that centralises spend on forty indirect categories. Staff in regional buying offices have been told the change is minor, but several have already begun withholding supplier data and some have started negotiating new side agreements. The change lead must select a response that addresses the emerging resistance and cynicism without delaying the centralisation timeline by more than one quarter. Which action is MOST appropriate?
Correct Answer: CExplanationThe regional buyers were told the change is minor, which breeds cynicism once they see the scale, so honest reframing paired with involvement addresses the loss stage of the change cycle directly. Involving them in the handover design also reduces resistance while keeping the timeline within a quarter. A directive ignores the loss and doubt driving the data withholding, a six-month pause breaks the timeline constraint, and retention bonuses treat a change-acceptance problem as a pay problem.
-
6 Question 6 Single choice Understand the concept of organisational change and how it can be achieved
A logistics company's procurement function has been through three incremental process changes in two years, each announced as the last. Staff now describe the transformation programme as a cycle with no end point, and engagement scores have fallen sharply. The programme board wants to introduce a fourth initiative, a digital supplier onboarding platform, which must be completed by the end of the financial year. The change lead must decide how to position this initiative. Which approach best addresses the challenge of maintaining change in an environment already showing change fatigue?
Correct Answer: CExplanationFraming the platform as closed and contained, with fixed scope, a defined end date and explicit closure criteria, gives staff a visible finish line that the previous cycle lacked. Positioning it as open-ended would reinforce the perception of endless change, and combining initiatives into one simultaneous programme would increase the load. Postponing breaks the financial-year deadline, which the board has set as a constraint.
-
7 Question 7 Single choice Understand the concept of organisational change and how it can be achieved
A public utility's procurement team has recently changed leadership. The new Director has initiated a review that identifies a widening gap between the team's current capability and the demands of an emerging market for renewable energy contracts. The team's SWOT analysis highlights strong supplier relationships but weak analytical skills, and PEST analysis shows tightening regulatory requirements on supply-chain carbon reporting within eighteen months. The Director wants to categorise the change required before committing resources. Which type of organisational change best describes the required response?
Correct Answer: AExplanationThe SWOT and PEST findings point to adjustments to existing processes and skills within the current purpose, which is adaption rather than wholesale change. Evolution implies gradual, self-directed development that the eighteen-month regulatory deadline does not allow, and reconstruction or revolution imply a change of purpose or structure that the evidence does not support. Strong supplier relationships are an asset that adaption preserves.
-
8 Question 8 Single choice Understand approaches to the planning and management of projects and change initiatives
A pharmaceutical procurement team is delivering a supplier risk programme. Its risk register currently records twenty-five risks, each rated on likelihood and impact, but the register has not been reviewed since the programme began. A recent supplier insolvency revealed that two risks rated as low had been linked to the affected supplier. The programme sponsor has asked for a method to test how risk events could combine to affect total programme cost, and the finance team requires a probabilistic range rather than a single contingency figure. Which technique should the Project Manager adopt to meet this requirement?
Correct Answer: DExplanationMonte Carlo simulation samples uncertain inputs across many iterations to produce a probability distribution of total cost, which meets the finance team's need for a range and captures interactions between risks. Pareto analysis ranks risks but produces no distribution, a decision tree yields a single expected value that the finance team has ruled out, and a one-at-a-time sensitivity table misses the combined effects the sponsor asked about.
-
9 Question 9 Single choice Understand approaches to the planning and management of projects and change initiatives
A procurement project to introduce category management in a construction firm has a risk register with clear owners for each risk. However, several supply chain risks have been assigned to the Head of Procurement even though the affected sub-contractors are managed by the Operations Director. Two risks have had no review for four months, and the project board has asked for the register to be reformed so that accountability reflects who can actually act. Which action is MOST appropriate?
Correct Answer: DExplanationRisk accountability should sit with the person who can influence the event, so reassigning supply chain risks to the manager who controls the sub-contractor relationship matches ownership to ability to act, and recording the rationale keeps the register auditable. Removing the risks hides exposure from the project, collective board ownership dilutes accountability, and adding a secondary contact leaves the wrong owner in place.
-
10 Question 10 Multiple choice Understand aspects of projects in organisations
A government department is planning a joint procurement project with two neighbouring authorities to deliver a shared records-management system. The three authorities will share costs, but their governance structures differ and the project must be managed without any single authority taking over the others. The Project Manager is preparing the project structure and must choose the arrangements that best meet these requirements. Which TWO actions should the Project Manager take? (Choose two.)
Correct Answer: A, DExplanationAn equal-voting steering group with rotating chairing matches the requirement that no single authority takes over, and a consortium agreement defining cost shares, decision rights and disputes before award fixes the arrangement that a consortium or joint venture depends on. A lead-contractor model breaks the no-takeover requirement, independent sub-contracting fragments the system, and deferring cost sharing leaves the funding unresolved during delivery.
-
11 Question 11 Multiple choice Understand the concept of organisational change and how it can be achieved
A logistics firm's procurement function is experiencing environmental turbulence following a merger, with a new reporting structure, two competing supplier management systems and uncertainty over which category managers will remain. Several managers have voiced scepticism about the leadership's commitment to the change, and early adopters report being ignored by senior staff. The change lead must select actions to reduce resistance and maintain momentum over the next nine months. Which THREE actions are MOST appropriate? (Choose three.)
Correct Answer: A, C, DExplanationA committed decision timeline reduces the uncertainty driving turbulence, a formal challenge review turns scepticism into recorded and answered concerns, and visible recognition of early adopters sustains momentum and counters the sense that their efforts are ignored. Delaying communication fuels the speculation already present, and replacing sceptical managers is a people decision that ignores their knowledge and risks further disengagement during the merger.
These are 11 of the 88 questions in the full L5M8 pack.
Get All 88 QuestionsGet all 88 questions & answers
Full access options for CIPS L5M8
Self-study
PDF Version
- 88 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 88 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 88 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L5M8 Exam (Project and Change Management) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.