Exam Information
Free practice questions with explanations
AutoDesk BIM_MGT_101 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 13
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Collaboration process
A structural consultant in Germany must send a federated Revit-based model to an external facade subcontractor who does not have access to the project CDE. The project's BIM Execution Plan requires that the subcontractor sees only the facade-related elements, that no editable native files leave the organisation, and that the sharing is traceable. The consultant's team lead proposes exporting the full coordinated model to a single DWF package. Which action best meets these requirements?
Correct Answer: DExplanationPublishing a filtered DWFx limited to the facade categories removes the unrelated model content before it leaves the organisation, and sharing it through the CDE's controlled external access keeps the transfer traceable. Emailing the full DWF exposes everything the requirement says must stay internal. Hiding worksets in an RVT still ships the full native model with its data, which violates the no-editable-files rule. Granting a full project account gives the subcontractor access to the whole central file, far beyond the facade scope.
-
2 Question 2 Single choice Collaboration process
Two architectural models in a campus project were linked to a structural model and the structural team reports that the architect's building is 4 m away from where it appears in the coordinated view. The architect insists that the building was correctly placed relative to the site survey. Both models use Project Base Point and Survey Point coordinates. The architect's file was recently shifted and the structural file has its Project Base Point set to the original location. Which action correctly reconciles the geolocation?
Correct Answer: CExplanationThe offset comes from inconsistent shared coordinates, so the correct fix is to bring both models into the same shared coordinate system by aligning the Project Base Point and confirming the Survey Point. Adjusting only the True North angle changes orientation, not position. Auto origin-to-origin ignores shared coordinates and would still place the building relative to the wrong internal origin. Changing project units is a scale problem and would not produce a clean 4 m positional offset.
-
3 Question 3 Single choice Collaboration process
A design team on a hospital project runs clash detection in Navisworks every Friday against a clash matrix that separates hard clashes from clearance clashes for MEP versus structure. The project manager wants the reports regenerated so that only MEP-to-structure hard clashes on levels 3 and 4 appear, with clearance clashes excluded, and the results grouped by the responsible discipline for resolution allocation. Which configuration best delivers this focused report?
Correct Answer: CExplanationClash Detective lets you define each clash test with a type, and a focused report is built by adding selection-set criteria that restrict the test to the required levels and categories. Grouping results by the Assigned To field then supports allocation of resolution responsibility. Running both test types and deleting rows afterwards produces an unreliable, unrepeatable report. Changing tolerance does not remove clearance tests from the matrix. Duplicate clash identifies coincident geometry, not MEP-to-structure hard conflicts.
-
4 Question 4 Single choice Corporate standards and documentation
A BIM manager is establishing model health thresholds for a company that delivers large Revit projects across several time zones. Recent audits show that some models with many warnings still pass the review, while others are rejected for minor issues. The company wants a threshold that flags risk rather than counting every warning equally, and must be measurable with the tools already in use by the modelling teams. Which threshold approach best meets this goal?
Correct Answer: BExplanationA ratio normalised to model size, with weighting that reflects severity, produces a threshold that is comparable across projects and ties to real risk. Warnings reported by Revit can be reviewed and tracked per model, so the measure is practical. A flat count penalises large models unfairly and ignores severity. Requiring zero warnings is rarely achievable and Purge Unused only removes unused families and types, not warnings. File size is a weak proxy and does not reflect modelling errors.
-
5 Question 5 Single choice Corporate standards and documentation
A firm is building a multidisciplinary template for a series of healthcare projects. Its graphic standard requires that all section views use a view template that hides grids, shows level datums only on the left, and applies a specific line weight to structural framing. Several junior modellers keep applying the view properties manually, so the output varies across sheets. The BIM manager wants the standard enforced inside the template with minimal ongoing maintenance. Which action should be taken?
Correct Answer: AExplanationRevit view templates store visibility, graphic overrides and line settings, and assigning them to views in the template ensures every new section carries the standard. Locking the assignment prevents modellers from overriding it. A reference sheet relies on manual compliance, which is the problem being solved. Section views are not families, and placing them as families is not a valid method. Browser sorting changes organisation only and has no effect on line weights.
-
6 Question 6 Single choice Corporate standards and documentation
A BIM coordinator is preparing the BIM Execution Plan for a public infrastructure bridge project. The client requires a Master Information Delivery Plan (MIDP) that is consistent with the contract and aligned with the information delivery cycle. The contract uses an AIA-style delivery schedule, but the design team is considering an existing Task Information Delivery Plan (TIDP) from a previous project. The coordinator must choose how the plans relate and which template to base the BEP on. Which approach is correct?
Correct Answer: BExplanationThe MIDP is the consolidated plan built from the task-level TIDPs, so the BEP template should follow the contractual delivery structure and each team's TIDP should feed into it. Copying a previous project's TIDP unchanged ignores the contract's delivery requirements. Replacing the MIDP with separate TIDPs removes the consolidated view the client needs. A milestone-only MIDP lacks the task-level deliverables that define the information cycle.
-
7 Question 7 Multiple choice Corporate standards and documentation
A BIM manager is evaluating a new clash-detection and model-coordination tool for a firm that works on large mixed-use projects. The firm needs a consistent, repeatable process for approving tools, and must confirm that the tool supports its shared coordinate workflow and a project data standard. Which TWO actions should be part of the evaluation process? (Choose two.)
Correct Answer: A, EExplanationA standard evaluation process relies on a controlled pilot with defined acceptance criteria and checks that the tool handles the firm's own shared coordinates and data formats. Vendor marketing and feature counts are not evidence of fitness for purpose. Installing everywhere before testing skips validation. Assuming compatibility because of a common vendor is not a valid assumption without testing against the actual file and coordinate requirements.
-
8 Question 8 Single choice Data management
A Revit model used by a hospital design team shows a sudden increase in the file size of the central model, and several users report that Sync with Central fails with a generic error. The team lead finds that a warning in the journal file references a corrupt family that was loaded from an old library. The project's policy requires preserving the full version history and avoiding loss of any user's unsynchronised work. Which action should be taken FIRST?
Correct Answer: DExplanationThe journal file identifies the failing operation and family, and confirming a clean prior version protects the project history before any repair is attempted. Deleting the family from the central file removes users' ability to recover unsynchronised work and skips the diagnosis step. Saving a local copy as a new central breaks the link to the shared history. Compact Central File is a housekeeping operation that does not repair a corrupt family and should not be used as a first step during failures.
-
9 Question 9 Single choice Data management
A consultant is required to deliver an ISO 19650-compliant model file for a metro station project. The file names currently use a mix of internal project codes and the client's naming standard requires the originator code, project code, volume, level, type, role and classification fields separated by hyphens. The team has already produced a sheet of 40 files, all named inconsistently. The task is to bring them into compliance without breaking the links between files in the model set. Which approach best meets the requirement?
Correct Answer: BExplanationRenaming within the controlled environment and then updating the external references keeps the model set intact and produces compliant file names. Renaming in Explorer breaks links unless each link is re-pointed, and it bypasses the CDE's record of revisions. Metadata alone does not satisfy a file-naming requirement. Shortcuts do not meet the naming standard and are not accepted deliverables.
-
10 Question 10 Single choice Data management
A BIM manager is closing out a university building project. The contract requires archiving of the native models, the CDE record, and all issued documentation, with the models kept accessible and unaltered for the client for ten years. The team also has local copies of the central models on several workstations and a set of external references pointing to files in an old project folder. Which closeout action best meets the requirements?
Correct Answer: BExplanationA proper closeout archives the authoritative central model together with the CDE record and issued deliverables, after detaching local copies and checking external references so the archive is self-contained. Keeping only PDFs loses the native data the client requires. Leaving local copies creates version conflicts. An IFC file alone does not preserve the native model and project record required by the contract.
-
11 Question 11 Single choice Project needs assessment
A specialist contractor is joining a delivery team on a commercial project that uses Autodesk Forma for early massing and environmental analysis and Revit for detailed design. The project lead must assess whether the contractor's team can participate in the BIM process as planned. The contractor's staff are experienced in other CAD tools, have limited Revit skills, and the project schedule is tight with a milestone for the first clash review in three weeks. Which action is the BEST next step to plan the team's involvement?
Correct Answer: BExplanationAssessing capability, capacity and training requirements before the milestone allows the project lead to plan targeted training that fits the schedule. Learning on the job during a clash review risks poor data quality and missed issues. A separate CAD model and PDF submission would break the shared model workflow. Deferring involvement removes the contractor from a process they must support and does not solve the capability gap.
-
12 Question 12 Multiple choice Project needs assessment
A BIM manager is writing the risk management section of a project BIM Execution Plan for a hospital project delivered by four design firms and a contractor. Concerns include unauthorised access to sensitive facility plans, team members working from outdated models, and miscommunication about which model is authoritative. The client requires that access be restricted to named roles and that model use limits be stated. Which TWO elements should be included in the risk management system? (Choose two.)
Correct Answer: B, EExplanationNamed-role access control with permission levels addresses unauthorised access, and stated model-use limits address misuse of design-intent models for other purposes. Allowing unrestricted offline editing creates version conflicts. Relying on individual judgement invites the miscommunication the plan is meant to prevent. Removing quality control increases risk rather than reducing it.
-
13 Question 13 Single choice Project needs assessment
A BIM manager is developing the BIM goals and uses for a mixed-use development with a fixed budget and a client who wants quantity-based cost estimates at concept stage. The design team is limited to one modelling tool and the BEP must avoid introducing tools that the team cannot support. The concept-stage model will be reviewed by the cost consultant in four weeks. Which goal and use combination best reflects a realistic, supportable scope?
Correct Answer: DExplanationEarly cost estimation from quantities is a goal the client needs at concept stage, and it can be supported with the single tool and a defined model scope by the four-week review. The energy and structural uses require tools and expertise the team does not have and are outside the stated scope. A fully detailed construction model and 4D sequencing are not appropriate for concept stage. Asset tagging for handover is premature and would consume effort before design is approved.
These are 13 of the 57 questions in the full BIM_MGT_101 pack.
Get All 57 QuestionsGet all 57 questions & answers
Full access options for AutoDesk BIM_MGT_101
Self-study
PDF Version
- 57 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 57 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 57 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the BIM_MGT_101 Exam (Autodesk Certified Professional in BIM Management for Building Design) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.