1 Question 1 Single choice Supply
A discrete manufacturer runs a weekly master production schedule (MPS) with a 12-week planning horizon. Its finished product, a pump assembly, has a demand time fence of 4 weeks and a planning time fence of 8 weeks. Sales has just received a firm customer order for 300 units due in week 6, which is not currently in the MPS. The MPS planner must add the order while protecting the existing commitments and keeping the plan feasible for the bill of materials. Which action should the planner take FIRST?
Correct Answer: CExplanationUnder the MPS objective, the planner first checks available-to-promise (ATP) for week 6 to see whether uncommitted MPS quantity exists. Because week 6 falls inside the 8-week planning time fence and within the 4-week demand time fence region, changes must be made deliberately and within the allowed flexibility rather than by directly overriding firm orders. Entering the order directly (A) bypasses the ATP check; moving existing MPS quantity (B) disrupts committed demand; changing subassembly releases (D) does not alter the end-item MPS and breaks the MRP logic that derives those releases.
-
2 Question 2 Single choice Demand
A consumer electronics company uses a forecasting model that has tracked well for two years. In the most recent quarter, forecast error for one product family increased sharply after a competitor launched a lower-priced substitute. The demand planner has data showing a structural shift in the level of demand, not a seasonal pattern. The company's forecast process requires that changes to the statistical baseline be justified and reviewed in the demand review meeting, and the team must keep the forecast responsive without overreacting to a single noisy period. Which action is the BEST response?
Correct Answer: CExplanationThe demand objective emphasises recognising structural change versus noise and incorporating customer and market input through collaborative planning. Because the shift is a level change caused by competitive activity, the baseline should be re-leveled, validated with sales and market intelligence, and governed through demand review. Raising smoothing (A) overreacts to noise and is not targeted at a level shift; a long moving average (B) lags the structural change; a fixed uplift (D) ignores the underlying model and the stated governance requirement.
-
3 Question 3 Single choice Inventory
A regional distributor holds safety stock for 1,200 SKUs. Its service target is a 97 percent cycle service level, and working capital is under pressure from the CFO, who requires a 15 percent reduction in average inventory value within two quarters without reducing service level. Analysis shows that 60 percent of inventory value is in 40 low-volume, highly variable SKUs whose safety stock was set using a single company-wide standard deviation. Which action will MOST effectively meet both constraints?
Correct Answer: BExplanationThe inventory objective is to balance stock levels against customer service using valuation and performance measures. Setting safety stock per SKU from item-level variability keeps the 97 percent service target while right-sizing buffers where the single company-wide standard deviation was distorting values. Lowering service for all SKUs (A) violates the service constraint; removing safety stock and relying on expediting (C) increases cost and breaks service; raising order quantities (D) increases average cycle stock, the opposite of the goal.
-
4 Question 4 Single choice Detailed Schedules
A job shop has three work centres. Work centre 2 is a bottleneck with 85 percent of its time committed to firm orders next week. A new rush order requires 14 hours on work centre 2 and must finish by Thursday. The shop uses finite capacity scheduling for the bottleneck and must not extend the standard shift pattern without a union-approved overtime agreement. Which scheduling action best meets the due date while respecting the constraints?
Correct Answer: BExplanationThe detailed schedules objective covers sequencing and resource allocation. Resequencing on the bottleneck according to priority and slack, combined with lot splitting to overlap operations, uses existing capacity without breaking the shift constraint. The weekend option (A) requires an overtime/agreement the scenario rules out; outsourcing (C) is not justified before checking the schedule; ignoring setup data (D) produces an infeasible schedule and is not a valid control action.
-
5 Question 5 Single choice Distribution
A consumer goods company is redesigning its distribution network. Currently, one central warehouse serves all customers in three regions, with 6-day average delivery lead times to the furthest region. Management wants to cut delivery lead time to 2 days for 90 percent of orders. Constraints include a fixed budget for new facilities, a requirement that no single region's inventory exceeds 20 percent of total stock to limit obsolescence risk, and a need to keep total landed cost per unit from rising. Which approach is the MOST appropriate first step?
Correct Answer: BExplanationThe distribution objective addresses network design. Modelling candidate locations against demand density, transport cost, and service time is the sound first step, and it allows the team to test the budget and the 20 percent inventory cap before committing. Moving all inventory to one region (A) breaks the inventory concentration limit; changing carriers alone (C) does not address the network design goal and may raise cost; more central safety stock (D) does not reduce lead time.
-
6 Question 6 Single choice Sales and Operations Planning
During a monthly S&OP meeting, the sales team proposes a 20 percent increase in the demand plan for next quarter based on a pipeline review. Operations states that the current production plan can only support a 5 percent increase without adding a second shift, which the finance team has not approved. The S&OP process requires reconciling demand and supply plans into a single agreed plan before the executive meeting. Which action is the MOST appropriate way to reconcile the two positions?
Correct Answer: CExplanationThe S&OP objective covers reconciling demand and supply through a structured process that balances capability with market demand. Testing pipeline assumptions and quantifying alternatives, then agreeing one plan with documented trade-offs, is the correct reconciliation method. Accepting the sales plan blindly (A) and rejecting pipeline evidence outright (B) both fail the reconciliation objective; averaging (D) ignores feasibility, which the process must assess.
-
7 Question 7 Single choice Quality, Technology and Continuous Improvement
A plant's value stream includes an assembly cell where first-pass yield has dropped from 96 percent to 88 percent over three months. The continuous improvement team is considering several responses. The plant is ISO 9001 certified and its quality procedure requires root cause analysis before corrective action is recorded. The team has limited time for the next two weeks. Which action should the team take FIRST?
Correct Answer: CExplanationThe quality objective emphasises structured tools and root cause analysis, which the ISO 9001 procedure in the scenario requires before corrective action. Stratifying defect data and applying Pareto or fishbone analysis identifies the true cause within the two-week limit. Buying equipment (A) and retraining (D) are corrective actions taken before the cause is known; 100 percent inspection (B) detects rather than prevents defects and adds cost without addressing the cause.
-
8 Question 8 Multiple choice Supply
A food manufacturer plans its material requirements. Lead times for a key ingredient vary between 2 and 5 weeks, and the ingredient is used in several finished products. The planner must reduce the risk of material shortages without holding excessive inventory. Which TWO actions best meet these requirements? (Choose two.)
Correct Answer: B, DExplanationThe supply objective covers MRP and supplier relationship management. A time-phased safety lead time derived from observed variability (B) reduces shortage risk without arbitrary over-buffering, and negotiating committed lead times with the supplier (D) reduces the variability at its source. Setting lead time to the maximum (A) inflates inventory and distorts planning; ignoring the supplier minimum order quantity (C) is infeasible; removing the item from MRP (E) breaks the time-phased planning required for a multi-product component.
-
9 Question 9 Multiple choice Demand
A medical device firm forecasts demand for a surgical product sold through hospital tenders. Demand is lumpy, and sales are often announced late. The demand manager must improve forecast accuracy and collaboration without inflating the forecast with unverified upside. Which TWO practices are MOST appropriate? (Choose two.)
Correct Answer: B, CExplanationThe demand objective covers customer input and forecast accuracy. A probability-weighted pipeline (B) incorporates customer and sales input while controlling for unverified upside, and monitoring bias and tracking signal (C) provides a governance measure of forecast quality. Entering bids at full value (A) and using the highest rep estimate (D) inflate the forecast with unverified demand; a fixed alpha of 0.9 (E) produces an overly reactive model for lumpy demand.
-
10 Question 10 Multiple choice Inventory
A retailer's distribution centre holds a fast-moving category where obsolescence risk is high due to frequent seasonal product changes. Finance requires inventory valuation to reflect the true carrying cost, and operations must maintain fill rate targets. Which TWO actions best support these objectives? (Choose two.)
Correct Answer: A, CExplanationThe inventory objective covers strategy, valuation, and cost management. Season-bound order-up-to levels (A) limit exposure to obsolescence while maintaining fill rate, and a full carrying cost that includes capital, storage, insurance, and obsolescence allowance (C) gives a valuation and trade-off basis that reflects reality. Valuing slow stock at historical cost indefinitely (B) misstates value; a monthly review for seasonal items (D) lengthens the response time to change; a 100 percent fill rate for all SKUs (E) is unattainable economically and ignores the trade-off objective.
These are 10 of the 105 questions in the full CPIM-MPR pack.
Get All 105 QuestionsGet all 105 questions & answers
Full access options for APICS CPIM-MPR
Self-study
PDF Version
- 105 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 105 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 105 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CPIM-MPR Exam (Certified in Production and Inventory Management - Master Planning of Resources) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.