Exam Information
Free practice questions with explanations
APICS CPIM Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 16
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Demand
A consumer electronics firm launched a promotional bundle last quarter that inflated sales by roughly 18 percent in two weeks. Its planners now use exponential smoothing with a fixed alpha of 0.3 to forecast next quarter's demand. The forecast for the coming quarter is consistently too high, and the planners are unsure whether the promotion or the smoothing constant is responsible. The marketing team plans two more promotions within the next six months, and the forecast horizon is 12 weeks. The planning manager wants a fix that keeps the model simple and does not require the promotions calendar to be fed into the statistical model. Which action is BEST?
Correct Answer: DExplanationPromotional spikes distort the history that a time-series model learns from, so cleansing the promotional periods out of the baseline is the targeted correction and keeps the model simple. Raising alpha to 0.9 makes the forecast chase the spike even harder, which would worsen the overshoot. A 52-week moving average dilutes the signal and will lag genuine demand changes over a 12-week horizon. A seasonal index addresses a different pattern and would not remove the one-time-style lift caused by promotions that the planners are seeing.
-
2 Question 2 Single choice Detailed Schedules
A plant produces three product families on a single bottleneck CNC machine that runs two shifts per day. The master production schedule has been loaded using finite capacity, but the shop floor reports that the weekly schedule exceeds available machine hours in alternating weeks while leaving idle time in others. Overtime is limited by a labor agreement to 4 hours per week per shift, and a customer contract prohibits moving any order beyond its committed ship week. The production planner must reduce the week-to-week load variation without breaking the contract. Which scheduling action is MOST appropriate?
Correct Answer: CExplanationCapacity leveling in this setting means moving work earlier into underloaded periods while respecting committed ship dates, which is exactly what pulling forward low-priority orders achieves. Pushing orders later breaks the stated ship-date commitment. Inflating lead times changes planned timing for every order without targeting the load imbalance and distorts costing. Moving to infinite loading hides the overload instead of resolving it, which would leave the bottleneck overcommitted.
-
3 Question 3 Single choice Inventory
A distributor of industrial fasteners holds a safety stock of 2,400 units for an item with average weekly demand of 300 units and a weekly demand standard deviation of 90 units. Its service level target is 97 percent (z of about 1.88), and replenishment lead time is 4 weeks with no variability in lead time. Warehouse space is constrained, and the inventory manager must reduce average inventory without lowering the service target. The supplier has offered to cut the lead time to 2 weeks if the distributor commits to a larger, fixed order quantity. Which action is MOST likely to reduce inventory while holding the service level?
Correct Answer: CExplanationSafety stock with variable demand and fixed lead time is z times sigma times the square root of lead time, so a shorter lead time directly reduces the required buffer while holding the 97 percent target. Lowering safety stock to 1,200 units without a basis drops service below target and relies on expediting, which the target does not allow. Increasing order quantity raises cycle stock, which conflicts with the space constraint. Raising the service level increases z and therefore increases safety stock rather than reducing it.
-
4 Question 4 Single choice Quality, Technology and Continuous Improvement
A medical device assembler has seen its first-pass yield fall from 96 percent to 88 percent after moving a torque-sealing operation to a new automated station. Engineers have found that the defects cluster around a single fixture, but the root cause is unclear. The quality manager must produce a corrective action plan that complies with an ISO 13485 audit scheduled in six weeks. The plan must document the problem, the containment, and a verified fix. Which step should be taken FIRST?
Correct Answer: CExplanationA quality system sequence requires containing suspect product and characterizing the problem before any permanent corrective action, and the audit will look for documented containment and a root cause investigation. Redesigning the fixture before the cause is known risks fixing the wrong thing. Reverting to manual work is a process change that bypasses the corrective action requirement. Widening tolerance to hide the defect is a governance violation rather than a fix, and would not survive an ISO 13485 audit.
-
5 Question 5 Single choice Sales and Operations Planning (S&OP)
At a regional food processor, the monthly S&OP meeting consistently ends with sales committing to volumes that operations later declares infeasible. Operations has capacity data for the packaging lines but reports them in machine-hours, while sales plans in cases and marketing plans in promotional events. Finance wants a single integrated plan in dollars before the next cycle, and the company must avoid building a separate planning spreadsheet that duplicates the ERP. The executive sponsor asks for the step that will most directly align the three functions on one plan. Which action should the process owner take NEXT?
Correct Answer: BExplanationThe core gap is that functions plan in incompatible units, so the integrated plan must reconcile supply and demand in one common measure before the executive decision. A budget ceiling forces demand down without reconciling supply, which is not balancing. A weekly meeting increases frequency without fixing the unit mismatch. Giving marketing sole authority removes cross-functional review, which is the opposite of the integrated consensus S&OP requires.
-
6 Question 6 Single choice Supply
A manufacturer of automotive seats sources foam from a single supplier with a 6-week lead time and has experienced two late deliveries this year. The purchasing manager is negotiating a longer-term agreement. The company's supplier scorecard tracks on-time delivery, quality rejects and price, but the supplier has recently begun shipping early to meet its own targets, which is raising inbound inventory and causing receiving bottlenecks at the plant's single dock. Reducing inventory is a strategic goal, and the company cannot dual-source this material within the next year. Which negotiation term is MOST appropriate to add to the agreement?
Correct Answer: BExplanationThe problem has two sides, late deliveries and early shipments, so the agreement needs a delivery window that penalizes earliness as well as lateness, which controls receiving congestion and inbound inventory. A volume-based price term does not address timing and can encourage more early buying. Consignment stock at the plant would increase on-site inventory, contrary to the stated goal. A late-only penalty leaves the early-shipment behaviour unaddressed and may even encourage it.
-
7 Question 7 Single choice Supply Chains and Strategy
A furniture company is evaluating its supply chain strategy after a strategic review set a goal of growing online direct sales from 10 percent to 35 percent of revenue within two years. The current network uses one central distribution center serving retail stores by truck. Online orders are a mix of small parcels and bulky items, and the executive team worries that the existing KPIs, mainly fill rate for store replenishment and cost per case shipped, do not reflect the new channel. Leadership wants the KPI set to reflect the strategic goal and must avoid a major capital project in year one. Which action BEST aligns the KPIs with the strategy?
Correct Answer: DExplanationA channel strategy is best measured with customer-facing and cost-to-serve KPIs for the new channel, which online cycle time, on-time delivery and cost to serve per channel provide without requiring a capital project. Replacing store fill rate with a pure cost metric would sacrifice service to the existing channel. Leaving KPIs unchanged leaves the strategic goal unmeasured. A zero-inventory target is unrealistic and does not reflect the stated strategy.
-
8 Question 8 Multiple choice Demand
A regional bakery supplier uses a demand forecast that has been consistently biased low for its seasonal holiday products over the last two years. Sales reps report that customers ordered more when reminded of the holiday menu, and the planning team has no access to the customer's point-of-sale data. The planners want to improve the forecast without adding a major new system within the next quarter. Which TWO actions are most appropriate? (Choose two.)
Correct Answer: C, DExplanationMeasuring forecast bias by product family and period reveals persistent error that can be corrected, and structured collaboration with sales captures the promotional knowledge the model lacks without a new system. Extending the horizon to 52 weeks does not correct bias and adds noise. Discarding the holiday history throws away the seasonal signal the planners need. Using last year's actuals without adjustment repeats the same low bias and ignores growth.
-
9 Question 9 Multiple choice Detailed Schedules
A job shop producing custom machined components has a backlog that ranges from 2 to 9 weeks across its work centers. The production controller wants to reduce expediting and improve schedule adherence but has limited time to change the system. The shop runs one shift and has three machining centers that are regularly overloaded. Which TWO actions are most effective for improving the scheduling of this shop? (Choose two.)
Correct Answer: A, DExplanationSequencing the bottleneck queue by earliest due date and releasing work against a capacity-constrained load are standard scheduling practices that cut expediting and protect schedule adherence in an overloaded job shop. Infinite-capacity scheduling is the cause of the overloads, not a remedy. Oversized batches ignore due dates and lengthen queues. Removing setup time from routings falsifies the schedule and does not reduce the actual time spent.
-
10 Question 10 Multiple choice Inventory
A plant maintenance spares crew stocks 4,000 different spare parts, many of which are used fewer than five times per year. Inventory carrying cost is high, and the storeroom has recurring stockouts on the critical 200 parts. The materials manager wants to improve inventory turnover without raising the risk of equipment downtime on critical assets. Which TWO actions are most appropriate? (Choose two.)
Correct Answer: A, BExplanationA criticality and usage classification lets the team reduce stock on low-usage non-critical parts while protecting critical items, and reviewing those slow movers for disposal or return removes dead stock. A uniform percentage cut to safety stock would worsen stockouts on critical parts. Larger order quantities for all spares inflate inventory on parts that barely move. Moving critical spares offsite increases response time and downtime risk on the assets that matter most.
-
11 Question 11 Order list Quality, Technology and Continuous Improvement
A packaging plant has adopted a continuous improvement program after a series of unplanned line stoppages reduced overall equipment effectiveness to 61 percent. The improvement team must address the losses in a disciplined way that supports a sustainable gain and can be audited. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Identify the top loss contributors with a Pareto analysis of the classified data
- Perform a root cause analysis on the largest loss, such as the bottleneck filler jam
- Implement and validate the countermeasure, then update the standard work and monitor OEE
- Establish a control plan with an OEE target and a review cadence for the improved process
- Measure the current OEE and classify the stoppage and speed losses by category using line data
Correct Answer:- Measure the current OEE and classify the stoppage and speed losses by category using line data
- Identify the top loss contributors with a Pareto analysis of the classified data
- Perform a root cause analysis on the largest loss, such as the bottleneck filler jam
- Implement and validate the countermeasure, then update the standard work and monitor OEE
- Establish a control plan with an OEE target and a review cadence for the improved process
ExplanationThe disciplined sequence begins with measuring OEE and classifying losses from line data, then uses a Pareto analysis to find the biggest contributors. Root cause analysis follows on the top loss before any countermeasure. The countermeasure must be implemented and validated before standard work is updated, and the control plan then sustains the gain. Reversing the Pareto and root cause steps would target a loss without evidence of its size, and writing a control plan before validation would lock in an unproven fix.
-
12 Question 12 Order list Supply
A consumer goods company is replacing its manual supplier selection with a structured sourcing process for a critical packaging film used across three plants. The category manager must run the process so the decision is defensible to the board and the supplier contract reflects the findings. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Issue a request for proposal to a shortlist of qualified suppliers with a common data template
- Evaluate proposals against weighted criteria including total landed cost, quality and capacity
- Conduct supplier audits and run a pilot order with the preferred supplier before award
- Negotiate and award the contract with performance metrics aligned to the evaluation criteria
- Define the specification and total cost requirements for the packaging film category
Correct Answer:- Define the specification and total cost requirements for the packaging film category
- Issue a request for proposal to a shortlist of qualified suppliers with a common data template
- Evaluate proposals against weighted criteria including total landed cost, quality and capacity
- Conduct supplier audits and run a pilot order with the preferred supplier before award
- Negotiate and award the contract with performance metrics aligned to the evaluation criteria
ExplanationA defensible sourcing process starts by defining the requirements, including total cost, so bidders are compared on the same basis. The RFP is then issued to a qualified shortlist, followed by weighted evaluation of the returned proposals. Audits and a pilot precede award so that capacity and quality claims are verified, and the contract is negotiated last, reflecting the criteria used. Awarding before the pilot would commit the company before verifying the supplier's claims.
-
13 Question 13 Drag and drop Supply Chains and Strategy
A mid-sized electronics manufacturer has identified four supply chain risks from a recent review: a single-source microcontroller supplier in a politically unstable region, a dependency on one ocean port for inbound components, currency exposure on purchases billed in a foreign currency, and a rising risk of counterfeit components entering through an unapproved broker. The risk committee wants each risk matched to the mitigation that most directly addresses its source. Match each risk to its mitigation.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Single-source microcontroller supplier in a politically unstable regionDependency on one ocean port for inbound componentsCounterfeit components entering through an unapproved brokerCurrency exposure on purchases billed in a foreign currencyIncrease finished goods inventory across all product linesEstablish alternate routing through a second port in the contract logistics termsQualify a second source and hold a strategic buffer of the componentMove all purchasing to spot market buying to reduce long-term commitmentsUse forward contracts or a hedging program to fix the exchange rateRestrict purchasing to an approved supplier list with authenticated component certificatesCorrect Answer:- Single-source microcontroller supplier in a politically unstable region → Qualify a second source and hold a strategic buffer of the component
- Dependency on one ocean port for inbound components → Establish alternate routing through a second port in the contract logistics terms
- Currency exposure on purchases billed in a foreign currency → Use forward contracts or a hedging program to fix the exchange rate
- Counterfeit components entering through an unapproved broker → Restrict purchasing to an approved supplier list with authenticated component certificates
ExplanationEach mitigation addresses the cause of its risk: a qualified second source and buffer reduce single-source dependency, alternate routing removes single-port exposure, hedging fixes the exchange rate, and an approved supplier list with authenticated certificates controls counterfeit entry. Spot-market buying increases supply uncertainty and does not address any of these risks. Blanket finished goods inventory is a costly response that does not target the component sources at all.
-
14 Question 14 Drag and drop Demand
A specialty chemicals firm operates a formal demand planning process across its product lines and wants each demand-related technique matched to the purpose it serves in the planning cycle. The VP of supply chain has asked the team to confirm each pairing before it is adopted in the process documentation. Match each technique to its purpose.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Forecast accuracy tracking using mean absolute percentage errorCollaborative planning with key distributorsCustomer segmentation by service requirementDemand sensing using point-of-sale signalsShortening the response time to recent changes in actual customer buyingAssigning differentiated service levels and planning priorities to customer groupsSetting the maximum production capacity of each plantSharing promotional and inventory data to refine the shared demand viewMeasuring how closely past forecasts matched actual demandCalculating the economic order quantity for raw materialsCorrect Answer:- Forecast accuracy tracking using mean absolute percentage error → Measuring how closely past forecasts matched actual demand
- Collaborative planning with key distributors → Sharing promotional and inventory data to refine the shared demand view
- Demand sensing using point-of-sale signals → Shortening the response time to recent changes in actual customer buying
- Customer segmentation by service requirement → Assigning differentiated service levels and planning priorities to customer groups
ExplanationMAPE is a forecast accuracy measure used to evaluate past forecasts, and collaborative planning exchanges promotional and inventory information to refine the shared forecast. Demand sensing uses near-real-time signals to respond faster to actual buying changes, and segmentation assigns different service and priority levels to customer groups. Economic order quantity and plant capacity are supply-side calculations that do not serve any of the demand purposes listed.
-
15 Question 15 Dropdown Inventory
A distribution center is reviewing the parameters of its continuous review inventory policy for a fast-moving consumer item. The inventory analyst must record the policy settings in the planning system's reorder configuration so that the reorder point covers demand during lead time plus safety stock. Complete the reorder configuration statement by selecting the correct value for each blank. The item sells 120 units per week with a 3-week replenishment lead time and a safety stock of 150 units, and the policy is a reorder point (ROP) with a fixed order quantity.
Choose the correct value for each blank.
Reorder point = (average weekly demand x lead time in weeks) + safety stock = ( x ) + 150 = 510 units. The policy triggers a replenishment order when inventory position falls to .Correct Answer:Reorder point = (average weekly demand x lead time in weeks) + safety stock = (120 x 3) + 150 = 510 units. The policy triggers a replenishment order when inventory position falls to Reorder point.
ExplanationThe reorder point equals average weekly demand times lead time plus safety stock, so 120 units per week times 3 weeks gives 360 units, and adding 150 units of safety stock gives 510 units. The trigger in a continuous review policy is the reorder point itself. The other options misapply the lead time or demand, or name a quantity that is not the trigger, so they would produce an incorrect configuration.
-
16 Question 16 Dropdown Sales and Operations Planning (S&OP)
A consumer appliance company is preparing the monthly S&OP supply-demand balancing worksheet for its three product families. The S&OP coordinator must record the balancing figures so that the executive team can see the gap between demand and capacity in a single, common unit. Complete the statement by selecting the correct value for each blank. Family A has forecast demand of 4,800 units and planned capacity of 5,200 units, and the coordinator measures the surplus as capacity less demand in units.
Choose the correct value for each blank.
Family A supply-demand balance = planned capacity forecast demand = 5,200 4,800 = units of surplus capacity. The S&OP review must reconcile this balance in the unit before the executive decision.Correct Answer:Family A supply-demand balance = planned capacity minus forecast demand = 5,200 minus 4,800 = 400 units of surplus capacity. The S&OP review must reconcile this balance in the common unit before the executive decision.
ExplanationSurplus capacity is capacity minus demand, so 5,200 minus 4,800 gives 400 units of surplus, and the S&OP review must reconcile supply and demand in a common unit as the planning principle requires. The 200 figure results from miscalculating the subtraction, while 800 and 1,000 do not follow from either input. Using a single unit that is not common, such as machine-hours, would repeat the unit mismatch the process is meant to eliminate.
These are 16 of the 588 questions in the full CPIM pack.
Get All 588 QuestionsGet all 588 questions & answers
Full access options for APICS CPIM
Self-study
PDF Version
- 588 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 588 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 588 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CPIM Exam (Certified in Production and Inventory Management) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.