1 Question 1 Single choice Fundamentals of Availability
A regional bank runs a core transaction platform in a single data centre with a contractual availability target of 99.99 percent per year. Over the last twelve months the facility recorded 4 hours and 20 minutes of unplanned outage, traced to a utility feed failure that the generator bridged imperfectly. The CFO asks the data centre manager whether the outage breached the target. Which statement is correct?
Correct Answer: AExplanationAt 99.99 percent availability the permitted downtime is about 0.01 percent of 8,760 hours, which is roughly 52.6 minutes per year. A 4 hour 20 minute outage far exceeds that budget, so the target was breached. The 8.8 hour figure corresponds to 99.9 percent, a common mistake when shifting one decimal place in the nines table. Planned maintenance exclusions depend on the contract, not a default rule, and the availability budget is measured cumulatively across the year rather than per incident.
-
2 Question 2 Single choice Fire protection methods in the Data Center
A colocation operator is refitting a server hall that holds lithium-ion battery racks and energised IT equipment. The design brief requires that the suppression system clear the hazard without residue, avoid water damage to live electronics, and keep the hall occupiable after discharge within the agent's specified concentration. The operator is comparing a water sprinkler system, a water mist system, an inert gas system and a foam system. Which approach best meets all of the stated requirements?
Correct Answer: DExplanationInert gas agents leave no residue, do not damage electronics, and are designed to be used at concentrations that remain safe for people, which fits the occupiability requirement. Sprinklers and foam both introduce water or liquid that conflicts with the no-water-damage constraint. Water mist uses water droplets that can still cause damage and does not meet the residue-free requirement as well as a clean agent. Foam is also a liquid residue hazard in an energised hall, and its cooling claim is not what the brief is testing.
-
3 Question 3 Single choice Fundamentals of Cabling strategies for Data Centers
A data centre is adding a new row of 40 high-density switches that will each use 48 copper uplinks terminated in a patch panel at the end of the row. The design team wants a layout that keeps the horizontal cable runs under the 90 metre channel limit, minimises congestion in the overhead pathway, and allows a technician to trace and replace a single cable without disturbing adjacent bundles. Which cable layout architecture should the team select?
Correct Answer: AExplanationTop-of-rack with rack-level patch panels keeps each horizontal run short, well under the channel limit, and localises cable changes to a single rack, which supports tracing and replacement without disturbing neighbours. Home-run to a distant main distribution area risks exceeding the 90 metre limit and congests the pathway. A single long bundle makes individual cable replacement impractical, and a perimeter loop adds length and violates the congestion requirement.
-
4 Question 4 Single choice Fundamentals of Cooling I
A mid-sized data centre has a CRAC unit whose evaporator coil is operating with a very low suction pressure and frosting along the coil surface, while the condenser runs hot. The facilities engineer suspects a restriction in the refrigerant circuit. Measurements show the liquid line is cool to the touch at the expansion device, and the discharge pressure is high. Which component is the most likely cause, and what is the correct corrective step?
Correct Answer: BExplanationLow suction pressure with frosting on the evaporator, combined with high discharge pressure and a cool liquid line, points to a restriction in the refrigerant path at the expansion device, which starves the evaporator. Clearing or replacing the restricted expansion device restores flow. An overcharge would raise rather than lower suction pressure. A failed condenser fan would raise discharge pressure but would not explain frosting at the evaporator. A clogged filter reduces airflow and can cause freezing, but it would not produce a cool liquid line with high discharge pressure.
-
5 Question 5 Multiple choice Fundamentals of Cooling II : Humidity in the Data Center
A data centre in a dry climate experiences occasional electrostatic discharge events affecting server boards during winter, while summer humidity sometimes drifts high enough to cause condensation risk on chilled water coils. The operator wants to stabilise moisture levels using control methods that respond to the actual conditions rather than fixed setpoints. Which TWO actions best address both problems? (Choose two.)
Correct Answer: A, CExplanationA dew point control strategy holds the moisture content of room air within a stable band, which addresses both condensation risk at high humidity and static discharge at low humidity. A relative humidity band with a low limit ensures humidification activates when air becomes too dry to prevent electrostatic discharge. Raising supply temperature does not reliably control moisture and can reduce cooling margin. Removing humidification worsens static. A dehumidifier on the chilled water loop is not a valid mechanism, since chilled water is not a room humidity control device.
-
6 Question 6 Order list Fundamentals of Availability
A facilities team has just experienced an unplanned loss of utility power at a data centre. The UPS carried the load, but the generator failed to start automatically and the team must restore normal operation while protecting the critical load and documenting the event for the availability report. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Transfer the critical load to the generator bus and monitor the UPS for stable operation
- Inspect the generator start circuit and record the fault for root cause analysis
- Start the generator manually and verify output voltage and frequency before transfer
- Confirm the UPS is carrying the critical load and estimate remaining battery runtime
- Restore utility power, retransfer the load and log the outage duration for availability reporting
Correct Answer:- Confirm the UPS is carrying the critical load and estimate remaining battery runtime
- Start the generator manually and verify output voltage and frequency before transfer
- Transfer the critical load to the generator bus and monitor the UPS for stable operation
- Inspect the generator start circuit and record the fault for root cause analysis
- Restore utility power, retransfer the load and log the outage duration for availability reporting
ExplanationThe first priority is confirming the UPS is carrying the load and that battery runtime is sufficient, since the critical load depends on it. The generator must then be started manually and verified before any transfer, otherwise the load could be dropped onto an unstable source. Transferring follows verification, and the fault can be investigated once the load is safe. Retransfer to utility and logging the outage closes the event. Logging the outage duration is last because it needs the restoration time.
-
7 Question 7 Drag and drop Fundamentals of Cabling strategies for Data Centers
A data centre operations lead is reviewing cable management practices after a series of intermittent link errors and difficult troubleshooting sessions. Each finding relates to a cable management or maintenance practice that addresses it. Match each finding to the practice that resolves it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Cables routed across floor tiles that block the cold aisle airflow pathUnlabelled copper trunks that take hours to trace during moves and changesFibre patch cords bent tighter than the manufacturer's minimum bend radius near the cabinet doorApply a documented labelling scheme at both ends of every cableRoute cords with radius-controlling guides and respect minimum bend radiusStandardise on a single cable colour for every network zoneRoute cabling in overhead or underfloor pathways away from airflow openingsIncrease patch cord length to reduce strain on connectorsCorrect Answer:- Fibre patch cords bent tighter than the manufacturer's minimum bend radius near the cabinet door → Route cords with radius-controlling guides and respect minimum bend radius
- Unlabelled copper trunks that take hours to trace during moves and changes → Apply a documented labelling scheme at both ends of every cable
- Cables routed across floor tiles that block the cold aisle airflow path → Route cabling in overhead or underfloor pathways away from airflow openings
ExplanationBend radius violations cause signal loss and are controlled by radius guides and disciplined routing that respects minimum bend specifications. Unlabelled cables are solved only by a consistent labelling scheme applied at both ends. Cables blocking airflow are resolved by moving them out of the airflow path into the proper pathway. Longer patch cords do not fix strain and add clutter, and uniform colour does not address traceability or airflow.
-
8 Question 8 Dropdown Fundamentals of Cooling I
A data centre technician is recording the refrigeration cycle states of a precision cooling unit while diagnosing a rising room temperature. The unit's readings show the refrigerant changing phase at each stage of the cycle. Complete the description of the cycle by selecting the correct value for each blank.
Choose the correct value for each blank.
In the evaporator the refrigerant absorbs heat from the room air and undergoes . The compressor raises the pressure of the vapour, which then passes to the condenser where it releases heat and undergoes . The expansion device then reduces the pressure of the liquid before it returns to the evaporator.Correct Answer:In the evaporator the refrigerant absorbs heat from the room air and undergoes evaporation. The compressor raises the pressure of the vapour, which then passes to the condenser where it releases heat and undergoes condensation. The expansion device then reduces the pressure of the liquid before it returns to the evaporator.
ExplanationIn the evaporator the low pressure liquid refrigerant absorbs room heat and boils into vapour, which is evaporation. In the condenser the high pressure vapour releases heat to the outside air and changes back to liquid, which is condensation. Compression describes the compressor's pressure raising, not a phase change in the evaporator, and expansion describes the pressure drop at the expansion device. Sublimation is a solid-to-gas change that does not occur in a vapour compression cycle.
-
9 Question 9 Dropdown Fundamentals of Cooling II : Humidity in the Data Center
A data centre manager is configuring the humidity control points on a computer room air handler after a recent audit flagged both dry-air static risk and condensation risk. The controller shows the relevant parameter fields. Select the correct value for each blank so the control strategy holds the room within its moisture envelope.
Choose the correct value for each blank.
Set the humidity control to so the controller regulates moisture content, and set the humidifier to activate when the measured falls below the lower limit of the envelope.Correct Answer:Set the humidity control to dew point control so the controller regulates moisture content, and set the humidifier to activate when the measured dew point temperature falls below the lower limit of the envelope.
ExplanationDew point control regulates the moisture content of the air independent of temperature, which is the approach that handles both dry static conditions and condensation risk. The humidifier trigger is tied to the measured dew point temperature, since that is the variable the envelope is defined against. Dry bulb temperature alone does not express moisture content, and fan speed and chilled water flow are not humidity measurements. A fixed steam output is not a closed-loop control and does not respond to conditions.
-
10 Question 10 Single choice Fundamentals of Availability
A financial services firm operates a data centre whose cooling plant has been the most frequent cause of unplanned downtime. Management wants to decide where to invest the next budget cycle. The operations team reports that a single 6 hour cooling outage would cost roughly 180,000 USD in lost trading, while a redundant CRAC unit costs 90,000 USD and would prevent most cooling-related outages. The team has also learned that the facility's lease ends in 14 months and a relocation would strand that spend. Which action is the most cost-effective first step?
Correct Answer: DExplanationThe redundant CRAC unit costs half of the estimated cost of one cooling outage and removes most cooling-related downtime, so it pays back quickly even with a 14 month lease horizon. Relocation studies are a long-lead exercise and do not address the immediate availability gap. Replacing the UPS ignores the stated evidence that cooling is the dominant cause. Deferring spending keeps the exposure at its current level for the full lease term.
-
11 Question 11 Single choice Fundamentals of Cabling strategies for Data Centers
A data centre team must perform cable maintenance on a live row of fibre links that carry production traffic. A technician needs to replace one damaged patch cord without interrupting the other links in the same bundle, and the change must be auditable. Which practice should the team follow?
Correct Answer: BExplanationRecording the port mapping and label before the change, replacing only the damaged cord, then verifying link status and updating records follows a controlled, auditable maintenance practice that avoids disturbing other links. Working from memory risks reconnecting to the wrong port. Unplugging the whole bundle needlessly disrupts production. Splicing a fibre in the field is not a patch cord replacement practice and degrades the link.
-
12 Question 12 Single choice Fundamentals of Cooling II : Humidity in the Data Center
A data centre operator has converted a former office floor into IT space. The converted area uses a legacy air handler with an evaporative humidifier and has no integrated dew point sensor. Operators report frequent humidifier cycling and drifting humidity during low load periods. The equipment vendor states that the humidifier must run at a rate matched to the actual moisture demand, and the air handler's fan runs at fixed speed. Which issue is most likely causing the frequent cycling and what is the correct fix?
Correct Answer: CExplanationFrequent on-off cycling at low load is the signature of short cycling, where equipment starts and stops too often because the controller reacts to small swings. Adding a buffer or staging so equipment runs in longer, steadier periods addresses it. Lowering chilled water temperature does not fix cycling and can cause condensation. Conductive floor tiles address static, not cycling. Enlarging ducts does not correct a control-driven cycling pattern.
-
13 Question 13 Order list Fundamentals of Cooling I
A data centre team is commissioning a new precision cooling unit after installation. The refrigerant circuit has been pressure-tested and the unit is ready for its first charge and performance verification. Arrange the commissioning steps in the correct order so that the circuit is safe, charged correctly and verified before the load is placed on it.
Drag the steps into the correct order, or use the arrows.
- Charge the circuit with the specified refrigerant quantity while the unit is off
- Connect the unit to the building management system and enable alarm monitoring for pressure and temperature
- Evacuate the refrigerant circuit to the specified vacuum level and hold it to confirm there are no leaks
- Energise the unit and start the compressor, then check suction and discharge pressures against design values
- Confirm evaporator airflow and temperature split across the coil before accepting the unit
Correct Answer:- Evacuate the refrigerant circuit to the specified vacuum level and hold it to confirm there are no leaks
- Charge the circuit with the specified refrigerant quantity while the unit is off
- Energise the unit and start the compressor, then check suction and discharge pressures against design values
- Confirm evaporator airflow and temperature split across the coil before accepting the unit
- Connect the unit to the building management system and enable alarm monitoring for pressure and temperature
ExplanationThe circuit must be evacuated and held under vacuum first to confirm integrity before any refrigerant is added. Charging the specified quantity follows with the unit off. Energising and checking operating pressures verifies the charge against design values. Airflow and temperature split are then confirmed on the coil before acceptance. Connecting alarms to the BMS comes last so the monitoring reflects a verified, operating unit.
-
14 Question 14 Drag and drop Fundamentals of Availability
A data centre availability review classifies each incident reported over the past year by its root cause category, so that the team can target improvements. Match each incident to the category that best describes its root cause.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
A technician isolated the wrong PDU branch and dropped a live rack during maintenanceA chiller tripped after a firmware update altered its low-pressure cutout thresholdA storm downed a utility transformer feeding the facilityEquipment failureFire suppression discharge triggered by a faulty detectorHuman errorCooling issue caused by an undersized airflow designNatural disasterCorrect Answer:- A chiller tripped after a firmware update altered its low-pressure cutout threshold → Equipment failure
- A technician isolated the wrong PDU branch and dropped a live rack during maintenance → Human error
- A storm downed a utility transformer feeding the facility → Natural disaster
ExplanationThe chiller tripped on a changed cutout threshold, so the failing component's behaviour is classified as equipment failure. The wrong PDU branch being isolated during work is a human error in operating procedure. The storm damaging the transformer is a natural disaster. The undersized airflow is a cooling issue and the faulty detector triggering suppression is a fire protection fault, so neither matches the three incidents given.
These are 14 of the 40 questions in the full CDCP-001 pack.
Get All 40 QuestionsGet all 40 questions & answers
Full access options for GAQM CDCP-001
Self-study
PDF Version
- 40 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 40 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 40 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CDCP-001 Exam (Certified Data Centre Professional (CDCP)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.