1 Question 1 Single choice 1 Introduction to IT Service Management
A regional logistics company has run its IT service desk for six years with monthly satisfaction surveys that show stable but mediocre scores. The IT director wants to demonstrate the value of service management to the finance committee, which questions every discretionary spend. The company has no formal service catalogue, incident data is spread across three tools, and the finance committee will only approve a further investment if the case links IT services to business outcomes. Which approach is the BEST way to describe the value of service management to the committee?
Correct Answer: CExplanationService management creates value by enabling customer outcomes and by making the cost and quality of services visible in terms the business understands. Linking fragmented incident and request data to business processes gives the committee the traceability it needs to judge investment. Fewer tickets is not reliably a sign of health, since users may simply stop reporting issues. Certification is a means of assurance rather than an automatic satisfaction gain, and tooling alone does not deliver value without process and service design behind it.
-
2 Question 2 Single choice 2 Service Management System (SMS)
A bank's IT department is preparing its service management system for an ISO/IEC 20000-1 readiness review. The regulator has recently issued guidance that outsourced cloud hosting suppliers must meet the same availability commitments as in-house services. The IT department has documented its objectives, but they mention only internal efficiency targets. The readiness assessor notes that the organisation has not yet analysed how the regulator's expectations and the outsourced suppliers' obligations affect the management system. Which action should the organisation take FIRST to address this gap?
Correct Answer: AExplanationISO/IEC 20000-1 requires the organisation to understand itself and its context, including interested parties and their requirements, before the SMS can be designed or its objectives set. Identifying the regulator and cloud suppliers and recording how they affect scope is the logical starting point, and objectives, continuity plans and ownership should follow from that analysis. Revising objectives first would set targets without understanding the requirements behind them. Rewriting continuity plans and appointing an owner are downstream actions that depend on the scope being defined.
-
3 Question 3 Single choice 3 The Operation of the Service Management System
A telecom provider has an incident backlog that grew over the last quarter. Analysis shows that 60 percent of incidents are repeats of the same underlying fault in the billing platform, and the service desk resolves each one by restarting a batch job. Management wants to reduce the recurrence of these incidents permanently while keeping incident resolution times within the agreed service levels. Which process should be used to address the root cause of these recurring incidents?
Correct Answer: DExplanationProblem Management exists to find the root cause of one or more incidents and to manage workarounds and permanent fixes, which here means analysing the billing fault and raising a change to correct it. Service Request Management handles standard user requests rather than faults, so it would formalise the workaround without removing the cause. Capacity and Demand Management address resource and volume issues, but the trigger described is a fault that recurs regardless of load.
-
4 Question 4 Single choice 1 Introduction to IT Service Management
A healthcare organisation is integrating an existing ISO 9001 quality management system, an ISO/IEC 27001 information security management system and a new ISO/IEC 20000-1 service management system. Each standard has its own clause structure, and the leadership team wants a single set of management processes so that staff are not duplicating documentation or audits. The organisation's consultant suggests that the three systems should be integrated by using the common high-level structure shared by management system standards. Which statement BEST explains how this integration is achieved?
Correct Answer: CExplanationManagement system standards share a high-level structure with common clause headings and core text, which allows an organisation to build one integrated management system that addresses several standards at once. Integration does not depend on a single certification body or a combined audit, which is an arrangement that varies by certifier. A generic policy cannot replace the specific requirements of each standard, and documented information remains a requirement, so the integration reduces duplication rather than removing documentation.
-
5 Question 5 Single choice 2 Service Management System (SMS)
A public sector agency is revising its governance arrangements for its IT services following an audit finding. Currently the IT director makes all decisions about service changes, and business units have no formal say. The audit committee wants the arrangement changed so that decisions on service investments and risk acceptance are made with clear accountability and business input, and it expects this to be documented within the SMS. The agency has a limited budget and cannot appoint additional executives. Which governance arrangement BEST meets these requirements?
Correct Answer: CExplanationGovernance principles call for clear accountability and documented decision rights, with input from the business where investments and risks affect it. A service board with business representatives, under documented terms of reference, meets the audit finding without new executive posts. Giving one business unit control over everyone's investments would be unfair and undocumented in the way governance requires. Outsourcing decisions removes accountability, and publishing the current process changes visibility but not decision rights.
-
6 Question 6 Single choice 3 The Operation of the Service Management System
A software services company is preparing a supplier management review for its managed hosting contract. The hosting supplier has met its monthly availability target in only four of the last twelve months, but the contract's penalty clause has never been invoked. The service manager wants to strengthen the relationship so that performance improves, without immediately ending the contract, which would disrupt three product teams. The supplier has asked for a clearer view of what the company requires. Which action should the service manager take to BEST support supplier performance management?
Correct Answer: CExplanationSupplier management requires that supplier performance is measured against agreed requirements and that improvements are managed through regular review. Agreeing expectations and measures with the supplier, then reviewing against them, addresses the gap while keeping the three product teams supported. Invoking penalties mechanically without review damages cooperation, and immediate retendering ignores the continuity constraint. Reducing scope avoids the problem rather than fixing it.
-
7 Question 7 Multiple choice 3 The Operation of the Service Management System
A retail company is designing its service catalogue as part of a service portfolio redesign. Its current catalogue lists technical components such as database servers and network switches but does not show which services customers can request. The service manager must ensure that the catalogue supports the business and avoids confusion between the catalogue and the configuration data held in the CMDB. Which TWO actions should the service manager take? (Choose two.)
Correct Answer: A, DExplanationA service catalogue presents the services available to customers in terms of what they request and the outcomes they receive, while component detail belongs in the CMDB. Linking catalogue services to the configuration items that support them maintains the relationship between the catalogue and configuration data without merging them. Recording components in the catalogue confuses the two, replacing the CMDB removes configuration data the organisation still needs, and restricting the catalogue to fixed-price services is not a requirement.
-
8 Question 8 Single choice 2 Service Management System (SMS)
A logistics firm is documenting its service management system for certification. The quality manager has drafted procedures and records but finds that some documents are out of date, several staff are working from printed copies that were superseded, and the auditor has asked how the organisation controls its documented information. The firm already uses a shared document repository. The quality manager wants a control that satisfies the documentation requirements without creating unnecessary bureaucracy. Which action BEST meets this need?
Correct Answer: CExplanationDocumented information must be controlled, which means it is identified, approved, versioned, made available where needed and protected, with superseded versions withdrawn. A shared repository with version control, approval and access rules provides that control efficiently. Printed controlled copies are hard to keep current when the document is revised, removing procedures conflicts with the requirement for documented information, and team-maintained copies produce the version divergence the auditor has already flagged.
-
9 Question 9 Order list 3 The Operation of the Service Management System
A financial services firm must release a change to its online payments platform. The change has been approved by the change advisory board, and the release has passed testing. The platform carries a high business impact, so the release must be controlled, reversible and communicated to users. Arrange the steps in the correct order in which they must be performed.
Drag the steps into the correct order, or use the arrows.
- Notify affected users and the service desk of the deployment window and expected impact
- Close the change record and update the configuration items affected by the release
- Confirm the release package matches the approved change record and the tested build
- Deploy the release to the production environment using the agreed deployment procedure
- Verify the deployed service against the success criteria and record the outcome
Correct Answer:- Confirm the release package matches the approved change record and the tested build
- Deploy the release to the production environment using the agreed deployment procedure
- Verify the deployed service against the success criteria and record the outcome
- Notify affected users and the service desk of the deployment window and expected impact
- Close the change record and update the configuration items affected by the release
ExplanationA controlled release starts by confirming the package matches the approved change and tested build, so the correct version is deployed. Users and the service desk are then informed before deployment so they can prepare. The release is deployed through the agreed procedure, verified against success criteria and recorded, and only then is the change closed with configuration data updated. Verifying before notifying or closing before verifying would leave gaps in control and records.
-
10 Question 10 Single choice 1 Introduction to IT Service Management
A university IT department has improved its incident resolution time over two years, but students still report that services are unreliable during the exam period. The department's leadership wants to adopt a principle that drives sustained improvement rather than one-off projects. The team has limited capacity and wants an approach that fits into normal operations. Which approach BEST reflects the principles of continual improvement?
Correct Answer: DExplanationContinual improvement is a recurring cycle of measuring performance, analysing it, prioritising opportunities, acting and checking the result, which suits limited capacity because changes are small and built into operations. A single large redesign is a one-off project, a fixed target with unchanged practices offers no route to improvement, and excluding students ignores that service quality is judged by the people who use it.
-
11 Question 11 Drag and drop 2 Service Management System (SMS)
A national railway operator is designing its service management system for a new ticketing platform that will be introduced in phases. Stakeholders include the regulator, the ticketing software supplier and passenger groups, and the design team must decide how each requirement will be addressed before transition begins. Match each requirement to the SMS element that meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Establish that new ticketing changes are tested and approved before they reach live passengersEnsure that the regulator's passenger data requirements are reflected in service designConfirm that the ticketing supplier's delivered service meets the contracted availabilityKeep the phased rollout's performance results so that later phases can be evaluatedIdentifying interested parties and their requirementsAppointing a single individual to approve all ticketing releasesEstablishing an annual budget for ticketing hardware purchasesChange control and transition planning before releaseRecording and retaining documented evidence of performanceMonitoring supplier performance against agreed requirementsCorrect Answer:- Establish that new ticketing changes are tested and approved before they reach live passengers → Change control and transition planning before release
- Ensure that the regulator's passenger data requirements are reflected in service design → Identifying interested parties and their requirements
- Keep the phased rollout's performance results so that later phases can be evaluated → Recording and retaining documented evidence of performance
- Confirm that the ticketing supplier's delivered service meets the contracted availability → Monitoring supplier performance against agreed requirements
ExplanationTransition planning and change control ensure that new ticketing functionality is tested and approved before release, which fits the design and transition requirements. Interested parties and their requirements, such as the regulator's data rules, shape the design. Retained records support evaluation of later phases, and supplier performance monitoring confirms the contracted availability is delivered. The two extra targets relate to budgeting and approval concentration, which do not meet the stated requirements.
-
12 Question 12 Dropdown 3 The Operation of the Service Management System
A company's service desk supervisor is configuring the incident management tool so that the resolution service level is monitored and reported correctly. The agreed service level requires that critical incidents are resolved within four hours and that breaches are reported to the service level manager. Select the correct value for each blank in the configuration statement.
Choose the correct value for each blank.
Set the priority incident target to a resolution time of hours, with breach notification to the manager.Correct Answer:Set the priority critical incident target to a resolution time of 4 hours, with breach notification to the service level manager.
ExplanationThe agreed service level applies to critical incidents, so the critical priority must carry the four-hour resolution target, which is the value the stem gives. Breaches must go to the service level manager who owns the agreement, not to change, supplier or release roles. The other priorities and values are plausible settings but do not match the requirement.
-
13 Question 13 Single choice 3 The Operation of the Service Management System
A manufacturing company experienced a severe outage when a configuration item was changed without the relevant record being updated, so the team responsible could not identify which services depended on the affected server. The IT manager proposes a set of controls for the configuration management process. The company's audit must show that configuration records remain accurate and that changes can be traced to the items they affect. Which control BEST meets this requirement?
Correct Answer: BExplanationConfiguration management requires that changes identify the configuration items they affect and that records are updated and verified as the change is implemented, so dependencies stay traceable. Reducing recorded items removes the information needed for impact analysis, a yearly hardware-only audit ignores software dependencies that caused the outage, and delayed updates allow the records to drift out of step with reality, the exact failure described.
-
14 Question 14 Single choice 2 Service Management System (SMS)
A healthcare IT provider is reviewing how it allocates resources for its service management system. The provider has recently lost two experienced service analysts, and the remaining team is overloaded. Certain competencies required for the management system, such as incident analysis and change assessment, are now concentrated in one person. The provider wants to meet its resource management requirements without a large budget increase, and it must demonstrate to the auditor that people have the competence needed for their roles. Which action BEST addresses this requirement?
Correct Answer: AExplanationResource management requires the organisation to determine the competence needed for each role, verify that current staff have it, and act to close gaps, which is evidence the auditor will look for. Concentrating competence in one person creates a single point of failure, years of service do not prove competence, and immediate outsourcing is costly and does not address the requirement for demonstrated competence within the organisation's own roles.
-
15 Question 15 Multiple choice 1 Introduction to IT Service Management
A government digital agency is introducing a service management system that must align with ISO/IEC 20000-1:2018 and that will be audited against the standard. The programme manager wants to explain to the steering group what the certification will provide. The steering group needs to understand the purpose and benefits of the standard before approving funding. Which TWO statements correctly describe the purpose or benefits of ISO/IEC 20000-1? (Choose two.)
Correct Answer: C, EExplanationISO/IEC 20000-1 provides a requirements framework that lets an organisation show it manages services effectively, and certification gives customers and interested parties confidence that service requirements can be met. The standard does not mandate specific tools, cannot guarantee zero incidents, and still expects service levels to be agreed with customers, so the other statements misstate its purpose.
-
16 Question 16 Single choice 1 Introduction to IT Service Management
A insurance company wants to show customers that its IT services provide measurable value. Currently, reports show only the number of incidents closed and the percentage of calls answered within a target time. The head of claims says these measures do not reflect whether claims are processed faster or customers are better served. The company wants to describe the value of service management in a way that links IT performance to business outcomes. Which measure is MOST useful for demonstrating that value?
Correct Answer: CExplanationMeasuring claim submission to settlement time links an IT service to a business outcome the head of claims cares about, and comparing it before and after an improvement demonstrates value. Closure counts and call answer rates measure activity and responsiveness rather than outcomes, and average incident closure time ignores which business process is affected.
-
17 Question 17 Single choice 2 Service Management System (SMS)
A utilities company is establishing its service management objectives for the next financial year. Its existing objectives are mostly activity-based, such as completing a number of training sessions and reducing the number of open tickets. The steering group wants objectives that are consistent with the service management policy, can be measured and that support the business strategy of improving customer trust. Which objective BEST meets these criteria?
Correct Answer: BExplanationA good service management objective is consistent with policy, measurable and linked to a business goal, and raising a baselined satisfaction score measured quarterly supports customer trust. The training, ticket count and briefing objectives are activities or outputs that do not directly show whether customer trust has improved.
-
18 Question 18 Single choice 3 The Operation of the Service Management System
A hosting provider is reviewing its capacity management process after repeated slowdowns on its shared platform during peak trading periods. Monitoring data shows that resource utilisation is high only during specific business hours, while overall utilisation is low. The provider must keep response times within the agreed service levels while avoiding unnecessary spend on permanent hardware. Which action BEST supports these objectives?
Correct Answer: DExplanationCapacity management uses historical utilisation and demand forecasting to plan capacity that meets agreed service levels cost-effectively, which suits a peak-driven pattern. Buying hardware for the highest peak ignores the low utilisation outside peaks and wastes spend, lowering service levels breaches the requirement, and restricting customers removes the service the platform exists to provide.
These are 18 of the 78 questions in the full ITSM20FB pack.
Get All 78 QuestionsGet all 78 questions & answers
Full access options for Exin ITSM20FB
Self-study
PDF Version
- 78 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 78 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 78 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the ITSM20FB Exam (IT Service Management Foundation Bridge) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.