1 Question 1 Single choice Scrum Practices
A Scrum Team of seven developers has been asked by its Product Owner to take on a two-week sprint. Midway through the sprint, a senior stakeholder asks the team to add a new reporting feature that is outside the Sprint Goal. The Scrum Master notices the team is considering accepting the request to keep the stakeholder happy. The Product Owner is unavailable until the sprint review. What is the BEST action for the Developers?
Correct Answer: BExplanationThe Product Owner owns the product backlog and its ordering, so a new request belongs there, and the Developers should protect the Sprint Goal once the sprint has started. Adding the feature to the sprint backlog changes the sprint's scope mid-sprint, which Scrum does not permit. Reassigning a developer splits the team's focus and undermines the Sprint Goal. Cancelling the sprint is reserved for the Product Owner and cannot be used to absorb an out-of-scope request.
-
2 Question 2 Single choice Advanced Scrum Concepts
A financial services company is scaling Scrum across eleven teams that all work on one payment platform. The teams deliver integrated increments, but each team currently runs its own sprint review with no shared view of integration status. Dependencies between teams cause repeated late integration failures. The company requires that a single integrated increment be inspected each sprint, and that no team's sprint boundary is changed to suit another. Which approach BEST meets these requirements?
Correct Answer: DExplanationScaled Scrum keeps each team's sprint intact while requiring that a single integrated increment be inspected, which a combined sprint review achieves with all teams presenting together. Merging teams violates the stated constraint of keeping team structures, and lengthening sprints is ruled out because sprint boundaries may not change. Status reports replace inspection of working software with reporting, which Scrum does not accept as a substitute for inspecting the increment.
-
3 Question 3 Multiple choice Agile Way of Thinking
A product group that has used a fixed-scope waterfall plan for years is adopting Agile. Leadership wants predictability of delivery dates without giving up the ability to respond to changing market needs. Which TWO statements describe how Agile brings both predictability and flexibility? (Choose two.)
Correct Answer: B, DExplanationTimeboxed iterations produce regular delivery points that make forecasting more reliable, while frequent inspection of working software allows the product direction to adapt to feedback. Fixing scope and deferring change contradicts the flexibility Agile provides. Exhaustive upfront documentation conflicts with the iterative refinement Scrum relies on. Per-feature fixed deadlines do not guarantee predictability because they ignore the empirical adjustment that Agile depends on.
-
4 Question 4 Order list Scrum Planning and Estimation
A Scrum Team has agreed on the next sprint's timebox and is preparing for Sprint Planning. The Product Owner has refined the top items of the product backlog. Arrange the steps in the correct order they must be performed during Sprint Planning.
Drag the steps into the correct order, or use the arrows.
- The Developers decide how the selected items will be delivered and create the sprint backlog.
- The Scrum Team agrees on a Sprint Goal that the selected work will achieve.
- The Product Owner proposes the highest-ordered product backlog items and explains their intent.
- The Developers select the product backlog items they can complete in the sprint.
Correct Answer:- The Developers select the product backlog items they can complete in the sprint.
- The Product Owner proposes the highest-ordered product backlog items and explains their intent.
- The Developers decide how the selected items will be delivered and create the sprint backlog.
- The Scrum Team agrees on a Sprint Goal that the selected work will achieve.
ExplanationSprint Planning begins with the Product Owner presenting the highest-ordered backlog items, after which the Developers select the work they can complete. The Scrum Team then agrees on a Sprint Goal that the selected work serves. The plan for how to deliver the items is last, producing the sprint backlog. Placing the Sprint Goal first would be wrong because the goal is shaped by the items chosen.
-
5 Question 5 Drag and drop Monitoring Scrum Projects
A distributed team of developers in three time zones needs to make the state of its sprint work visible to all members and to stakeholders who cannot attend the daily stand-up. The team wants each element to serve a specific monitoring purpose. Match each monitoring need to the artifact that best meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Give a continuous, at-a-glance view of sprint progress and impediments in a shared locationShow cumulative completed work against remaining work across the sprintShow each work item's flow from to-do through done, with work-in-progress limitsInformation radiatorSprint retrospective logBurndown chartVelocity estimation tableKanban boardCorrect Answer:- Show each work item's flow from to-do through done, with work-in-progress limits → Kanban board
- Show cumulative completed work against remaining work across the sprint → Burndown chart
- Give a continuous, at-a-glance view of sprint progress and impediments in a shared location → Information radiator
ExplanationA Kanban board visualizes work flow and limits work in progress, while a burndown chart tracks remaining work over the sprint against time. An information radiator is the general concept of a visible, shared display that keeps everyone informed without a meeting. The retrospective log records improvement ideas rather than monitoring progress, and the velocity table supports forecasting across sprints, so neither matches a live monitoring need.
-
6 Question 6 Dropdown Scrum Planning and Estimation
A new Scrum Team has completed three sprints of two weeks each and wants to forecast how many story points it can take into the next sprint. The Scrum Master records the completed points for each sprint and explains how the forecast should be calculated. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
The team's velocity is calculated as the of story points completed across the last sprints, and the forecast for the next sprint uses that value.Correct Answer:The team's velocity is calculated as the sum of story points completed across the last three sprints, and the forecast for the next sprint uses that average value.
ExplanationVelocity is commonly derived by totaling the story points of completed work over recent sprints and dividing by the number of sprints, so the sum across the three sprints feeds into an average used for forecasting. Using a single sprint would not give a stable basis, and taking the highest or lowest value distorts the forecast in one direction. Median and maximum options would not match the standard approach taught for estimating team velocity.
-
7 Question 7 Single choice Scrum Practices
A Scrum Team's sprint review is scheduled on the final day of the sprint. During the review, the Developers present a feature that works, but the Product Owner notices that two backlog items marked done do not meet the team's Definition of Done because automated tests were skipped. The Product Owner wants to accept the work to meet a release date. What should the Scrum Master do FIRST?
Correct Answer: DExplanationWork that does not meet the Definition of Done cannot be counted as done, and the Scrum Master's role is to make that transparent and help the team decide how to handle it. Accepting the items as done would misrepresent the increment, and building tests during the review is not a legitimate use of the event. Removing items from the increment without first agreeing on the situation skips the transparency step that should precede any decision.
-
8 Question 8 Single choice Advanced Scrum Concepts
A software vendor has signed a fixed-price contract for a government client to deliver a product in Scrum. The client demands a fixed scope and a fixed price, while the vendor wants to keep Scrum's empirical approach. The contract also requires invoices at defined milestones. Which contract arrangement BEST supports Scrum while meeting the client's milestone requirement?
Correct Answer: BExplanationA fixed-price arrangement can work with Scrum when milestones are linked to delivery of working increments, letting the client see progress and the vendor keep the empirical process. Time and materials without milestones does not meet the milestone requirement. Committing all items before sprints begin removes the empirical adjustment Scrum depends on. Billing per sprint without tying payment to delivered product breaks the link between payment and value.
-
9 Question 9 Multiple choice Scrum Practices
A Scrum Master is coaching a new Product Owner who has created a product backlog containing items such as 'Improve the system' and 'Build the database layer'. The stakeholders want the backlog to support effective sprint planning. Which TWO actions would BEST improve the backlog items? (Choose two.)
Correct Answer: A, BExplanationGood backlog items are written as user stories describing user need and value, and large items are split so they fit within a sprint and can be planned. Converting items into technical task lists assigned upfront removes the Developers' self-management. Uniform sizing without refinement ignores the need for items to reflect their actual scope. Removing the ordering contradicts the role of the Product Owner in ordering the backlog by value.
-
10 Question 10 Drag and drop Scrum Practices
A Scrum Team has noticed several problems in its recent work: the daily scrum has become a status report to the manager, the sprint review has turned into a demonstration with no feedback, and the retrospective never produces any action. Match each observed problem to the event characteristic it violates.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
The retrospective produces no improvements the team carries into the next sprintThe sprint review does not seek stakeholder feedback on the incrementThe daily scrum is directed at a manager and not at the Developers planning their daySprint planning sets the team's velocity targetDaily scrum is a Developers-owned, 15-minute planning eventSprint review is an inspection of the increment to adapt the product backlogSprint is a fixed one-month timeboxSprint retrospective creates a plan for improvements in the next sprintCorrect Answer:- The daily scrum is directed at a manager and not at the Developers planning their day → Daily scrum is a Developers-owned, 15-minute planning event
- The sprint review does not seek stakeholder feedback on the increment → Sprint review is an inspection of the increment to adapt the product backlog
- The retrospective produces no improvements the team carries into the next sprint → Sprint retrospective creates a plan for improvements in the next sprint
ExplanationThe daily scrum belongs to the Developers as a short planning event, so reporting upward violates its purpose. The sprint review's purpose is to inspect the increment and adapt the backlog, which requires feedback from stakeholders. The retrospective must yield a concrete improvement plan for the next sprint. The distractors describe a sprint length that the team has not violated and a velocity target that Scrum does not set in planning.
-
11 Question 11 Single choice Monitoring Scrum Projects
A product owner in a regulated company wants a single view showing whether the sprint is on track, with the remaining work measured against the time left. The Scrum Master proposes a chart for the sprint backlog that tracks remaining work each day. The company's audit team requires that the artifact show progress only toward the Sprint Goal and never be used as a performance measure of individual developers. Which artifact BEST meets these requirements?
Correct Answer: BExplanationA sprint burndown chart shows remaining sprint work against time and supports the Sprint Goal without measuring individuals, and it works well as an information radiator. Per-developer dashboards and per-person velocity comparisons break the audit constraint by turning the artifact into an individual performance measure. A cumulative flow diagram tracks flow across the team rather than the sprint's remaining work, and tracking each developer's done items again points toward individual measurement.
-
12 Question 12 Dropdown Agile Way of Thinking
A coach is explaining to a team why the Agile Manifesto values working software over comprehensive documentation during a project with frequent requirement changes. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
The Agile Manifesto states that the team should value over , and this supports by keeping the product aligned with what customers actually need.Correct Answer:The Agile Manifesto states that the team should value working software over comprehensive documentation, and this supports responding to change by keeping the product aligned with what customers actually need.
ExplanationThe Agile Manifesto values working software over comprehensive documentation, which keeps delivery focused on product that customers can inspect and use. That emphasis supports responding to change because working product generates feedback that informs adjustments. Contract negotiation and fixed scope are not the manifesto's stated values, and budget control and vendor lock-in are unrelated to the trade-off described.
-
13 Question 13 Single choice Scrum Planning and Estimation
A Scrum Team of six developers is using planning poker to estimate backlog items. For one item, the estimates range from 2 to 40 story points. The Product Owner asks the team to settle on a single number quickly so the item can be planned. Which action BEST applies sound estimation practice to resolve the spread?
Correct Answer: CExplanationIn planning poker, a wide spread signals differing understanding, so the team discusses the highest and lowest estimates and re-estimates until the numbers converge. Averaging hides the disagreement, and accepting the highest value overestimates the work by design. Assigning sizing to the Product Owner misplaces estimation, which belongs to the Developers.
-
14 Question 14 Order list Monitoring Scrum Projects
A team is introducing a Kanban board to make its sprint work visible. The board currently has no defined columns and no limit on how much work is in progress. Arrange the steps in the correct order the team should perform to set up the board properly.
Drag the steps into the correct order, or use the arrows.
- Place every current sprint backlog item on the board in the column matching its actual state.
- Define work-in-progress limits for the stages where work tends to pile up.
- Review the board in the daily scrum and adjust the limits when flow problems appear.
- Agree on the workflow stages each work item passes through, such as to do, in progress, and done.
Correct Answer:- Agree on the workflow stages each work item passes through, such as to do, in progress, and done.
- Place every current sprint backlog item on the board in the column matching its actual state.
- Define work-in-progress limits for the stages where work tends to pile up.
- Review the board in the daily scrum and adjust the limits when flow problems appear.
ExplanationThe team first agrees on the workflow stages so that items have somewhere to go, then places the current work in the correct states. Work-in-progress limits are defined once the stages and actual flow are visible, and the board is reviewed afterward to adjust limits. Setting limits before the stages exist would have no meaning, and reviewing before placing work gives nothing to review.
-
15 Question 15 Single choice Advanced Scrum Concepts
A company runs two Scrum Teams that have been asked to work together on a single product from two offices in different countries. The teams share no overlapping working hours, and the Product Owner needs regular inspection of the product. The company wants to keep the team cohesive and avoid adding a separate project manager. Which arrangement BEST supports the virtual teams' Scrum events?
Correct Answer: CExplanationScrum events can be held virtually using video conferencing and shared digital boards, and making the Product Owner accessible across time zones keeps the team cohesive and the product inspected. Splitting sprints by office fragments the team and the Sprint Goal. Replacing the daily scrum with email removes the synchronous coordination the event provides. Appointing a traditional project manager conflicts with the Scrum principle that no such role exists.
These are 15 of the 59 questions in the full ASF pack.
Get All 59 QuestionsGet all 59 questions & answers
Full access options for Exin ASF
Self-study
PDF Version
- 59 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 59 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 59 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the ASF Exam (EXIN Agile Scrum Foundation) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.