Exin ASM Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 18
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Adopting Agile
A traditional project manager at a regional insurer is becoming the Scrum Master for a team that has just moved from a waterfall process. The former manager used to assign tasks, track Gantt chart dates, and approve every change request personally. During the first sprints, the team keeps asking the new Scrum Master to decide task ownership and resequence the backlog for them. The organisation has a strict rule that all changes to scope must be traceable, and the sponsor wants visible progress every two weeks. Which action should the Scrum Master take FIRST to help the team move to self-management?
Correct Answer: BExplanationSelf-management means the Developers decide how to do the work and who does which task, so the Scrum Master should coach the team to make these decisions rather than make them. Facilitating an agreement on how work is pulled and assigned, then stepping back, addresses the dependence created by the former project manager role. Assigning tasks centrally recreates the old command model and breaks the team's ownership. Giving the Product Owner sprint backlog ownership confuses accountabilities, since the Developers own the sprint backlog. Keeping a Gantt chart preserves the traditional mindset the transition is meant to replace.
-
2 Question 2 Multiple choice Adopting Agile
A software organisation is transitioning three legacy teams to Scrum. Each team has separate testers in a QA department that reports to a different director, and testers only receive work after developers hand off finished code. Sprints regularly end with stories marked done that have not been tested. Leadership wants to improve this without adding headcount. Which TWO actions best address the root cause and align with the Scrum concept of a cross-functional team? (Choose two.)
Correct Answer: D, EExplanationScrum's Developers are a cross-functional group that includes all skills needed to create the increment, so placing testers in the team addresses the handoff root cause. A Definition of Done that explicitly covers testing makes it impossible to call untested work done, and the team owns how it meets that standard. A separate testing sprint reintroduces a waterfall phase and leaves the increment unverified until late. Assigning sign-off to the Scrum Master gives a non-Developer authority over the done state. Moving test writing to the Product Owner misplaces accountability, since the Product Owner orders the backlog and does not build the increment.
-
3 Question 3 Single choice Agile Way of Thinking
A manufacturing company compares delivery approaches for a new scheduling feature. Requirements are uncertain, and stakeholders expect to learn what they need from early working versions. The head of operations wants predictable delivery dates for budgeting, yet also wants to change priorities after each two-week period. A consultant proposes a plan that fixes the full scope and date upfront to satisfy budgeting, while the team would still review progress each sprint. Which response best reflects the Agile way of thinking about predictability and flexibility?
Correct Answer: AExplanationAgile achieves predictability through a fixed cadence, frequent inspection of working software, and forecasts that are revised as evidence accumulates, while flexibility comes from keeping the product backlog open to reordering. Fixing scope and date upfront contradicts the stated need to change priorities and ignores the uncertainty in requirements. Writing a complete requirements document assumes uncertainty can be removed in advance, which Agile rejects. Locking the sprint backlog for the whole project misunderstands that the sprint backlog belongs to a single sprint and that the Product Owner should adjust the product backlog continuously.
-
4 Question 4 Drag and drop Agile Way of Thinking
A product team wants to borrow ideas from other Agile approaches without abandoning Scrum. The Scrum Master is comparing approaches to decide which practices fit specific needs of the team. Match each stated need to the framework that best describes the practice.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Scaling a single product backlog across many Scrum teams in one productVisualising work in progress and limiting the number of items active at onceEngineering practices such as pair programming and test-driven developmentA framework for coordinating many Scrum teams with a portfolio of planning eventsLeSSCrystalKanbanExtreme ProgrammingSAFeCorrect Answer:- Visualising work in progress and limiting the number of items active at once → Kanban
- Scaling a single product backlog across many Scrum teams in one product → LeSS
- Engineering practices such as pair programming and test-driven development → Extreme Programming
- A framework for coordinating many Scrum teams with a portfolio of planning events → SAFe
ExplanationKanban is built around visualising the workflow and limiting work in progress, which the team can apply within Scrum. LeSS scales Scrum by keeping one product backlog and one Product Owner across multiple teams. Extreme Programming is the framework known for engineering practices such as pair programming and test-driven development. SAFe provides a layered portfolio and program coordination model for many teams. Crystal is a family of methods shaped by team size and criticality, and it does not match any of the stated practices here.
-
5 Question 5 Single choice Complex Projects
A bank is scaling Scrum across eight teams working on one online banking product. Each team has its own backlog, and the teams keep building overlapping features and discovering integration problems late in sprints. The Product Owner is overwhelmed trying to set priorities across all teams. The bank requires one prioritised view of the product's work for governance. Which arrangement BEST uses a single product backlog in this scaled environment?
Correct Answer: BExplanationIn a scaled setting, the product backlog remains a single ordered list for the product, so one Product Owner can give one prioritised view of work across all teams as the governance requirement demands. Splitting the backlog per team recreates the overlapping features and local priorities the bank is trying to remove. Merging sprint backlogs ignores that each team plans its own sprint work. Having several Product Owners on one backlog breaks the single source of product ordering and the one-owner accountability.
-
6 Question 6 Dropdown Complex Projects
A large insurer is adopting Nexus to coordinate three Scrum teams that share one integration pipeline. The integration failures happen because each team tests only its own changes. The Scrum Master is documenting the cross-team integration activity in the Nexus framework. Complete the description by selecting the correct value for each blank.
Choose the correct value for each blank.
In Nexus, the cross-team activity that surfaces integration issues and plans dependency resolution is called the , which is held after the Sprint and is facilitated by the .Correct Answer:In Nexus, the cross-team activity that surfaces integration issues and plans dependency resolution is called the Nexus Integration Team, which is held after the Sprint Review and is facilitated by the Scrum Master.
ExplanationNexus uses the Nexus Integration Team to keep the combined increment integrated, and integration problems are identified in the Nexus Sprint Review, which takes place after the Sprint. In practice the Scrum Master facilitates the Nexus Sprint Review as a cross-team event that helps plan dependency resolution. The Nexus Integration Team is a role that owns integration rather than a meeting, so it cannot be the facilitator. Sprint Planning happens at the start of a sprint rather than after it. Nexus has no Chief Architect role, so that option is not part of the framework.
-
7 Question 7 Order list Complex Projects
A healthcare software company has decided to move its first team to Scrum after deciding that Agile suits its product. The company's regulatory context requires that the team demonstrate it can build increments before the wider organisation is committed to the change. Arrange the steps in the order they must be performed to start the pilot with the requirement that the team's first sprint produces a working increment. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Perform the sprint with daily Scrum events to inspect progress toward the Sprint Goal
- Hold the sprint review to inspect the increment and adjust the product backlog
- Agree the Definition of Done and the product backlog ordering with the Product Owner
- Run the sprint planning event to select backlog items the Developers can commit to
Correct Answer:- Agree the Definition of Done and the product backlog ordering with the Product Owner
- Run the sprint planning event to select backlog items the Developers can commit to
- Perform the sprint with daily Scrum events to inspect progress toward the Sprint Goal
- Hold the sprint review to inspect the increment and adjust the product backlog
ExplanationA Scrum pilot must first establish a Definition of Done and an ordered product backlog so that planning has a standard for completeness and a priority order. Sprint Planning then selects what the Developers can commit to based on that backlog. The sprint is executed with Daily Scrums inspecting progress toward the Sprint Goal. The Sprint Review follows completion to inspect the increment with stakeholders and adjust the product backlog. Running Sprint Planning before the Definition of Done and ordering are agreed would leave the team unable to judge which items are ready or complete.
-
8 Question 8 Single choice Scrum Master accountability
In its second sprint, a Scrum team at a logistics firm is consistently failing to meet its Sprint Goal. The Developers say that a database administrator from another department must approve every schema change, and that approver is available only twice a week. Each approval request sits in an email queue. The Scrum Master has authority to escalate impediments in the organisation. The Product Owner suggests adding scope to the sprint so that the team looks busier. Which action is the Scrum Master's most appropriate response?
Correct Answer: CExplanationA core Scrum Master accountability is removing impediments that the team cannot remove itself, and an external approval queue is exactly that kind of impediment that needs escalation. Helping the team propose an alternative, such as a standing approval or a self-service review, addresses the root cause. Adding scope worsens planning and does not solve the constraint. Dropping the schema work reduces the Sprint Goal without fixing the impediment. The Scrum Master taking over approval would give the role an authority outside Scrum and does not build the team's capability.
-
9 Question 9 Multiple choice Scrum Master accountability
A Scrum Master is supporting a team where the Product Owner has begun directing individual Developers on how to implement stories, and the Developers have stopped raising technical concerns in the sprint. The Scrum Master wants to coach the team back to healthy roles. Which TWO actions best coach the team and respect the accountabilities within the Scrum framework? (Choose two.)
Correct Answer: C, EExplanationThe Product Owner is accountable for ordering the product backlog and maximising the value of the work, while the Developers are accountable for how the work is turned into an increment. Clarifying these boundaries and facilitating a shared agreement on how the two collaborate is coaching the team toward healthy roles. Routing concerns only through the Scrum Master or removing the Product Owner from events cuts off the collaboration Scrum relies on. Assigning technical design to the Product Owner reverses the accountability for how work is done.
-
10 Question 10 Single choice Agile requirements and proper environment
A government agency's procurement office has traditionally awarded contracts only when every requirement is written and signed. A team wants to adopt Scrum for a case-management system, but the contract requires a fixed scope and fixed price. The agency's managers agree that scope will change as users learn the system. Before the team starts, the director asks what cultural changes are needed for Agile to work. Which change is MOST essential before adoption?
Correct Answer: CExplanationAdopting Agile in a fixed-price environment requires a shift in mindset in which the buyer accepts that requirements emerge and that the Product Owner can order and reorder the backlog within agreed boundaries. Without that acceptance, the contract will keep forcing a frozen scope that Scrum is designed to revisit. Freezing all requirements up front recreates the waterfall premise that Agile is meant to replace. Assigning developers to fixed milestones conflicts with the team's ownership of the sprint. Removing Product Owner involvement contradicts the role's central part in ordering the backlog.
-
11 Question 11 Single choice Agile Estimating, Planning, Monitoring and Control
A Scrum team at a media company estimates its product backlog using story points. After four sprints, the velocity is trending upward, but a stakeholder shows the Scrum Master a release forecast based on that velocity that has slipped twice. The Developers have quietly started splitting stories into smaller stories at the end of sprints so each fits, and they have raised the point value of small items to match larger historical ones. The Scrum Master needs to correct the planning error. Which is the most appropriate response?
Correct Answer: DExplanationThe velocity has been distorted because the team is inflating and splitting estimates to make work look bigger or to fit sprints, so the forecast is built on a corrupted baseline. Re-estimating against a consistent reference and being transparent that the old velocity is unreliable addresses the estimation error directly. Switching to ideal hours keeps the same distortion, since the estimates are inflated regardless of unit. Counting stories is sensitive to splitting and does not fix the underlying error. Fixing point values and adding a buffer hides the problem rather than correcting it.
-
12 Question 12 Drag and drop Agile Estimating, Planning, Monitoring and Control
A Scrum team at a hospital software vendor is preparing its next planning session and reviewing the artefacts it uses to estimate and track work. The Scrum Master wants each concept applied to the right purpose so that the forecast and the daily tracking remain honest. Match each planning practice to the purpose it best serves.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Expressing effort as uninterrupted time without meetings or interruptionsShowing remaining work across the sprint to monitor progress toward the Sprint GoalMeasuring the amount of work the team completed per sprint to forecast future sprintsEstimating effort by comparing the size of items to a reference itemVelocityRelease date commitmentRelative sizing with story pointsIdeal daysSprint burndown chartCorrect Answer:- Estimating effort by comparing the size of items to a reference item → Relative sizing with story points
- Measuring the amount of work the team completed per sprint to forecast future sprints → Velocity
- Expressing effort as uninterrupted time without meetings or interruptions → Ideal days
- Showing remaining work across the sprint to monitor progress toward the Sprint Goal → Sprint burndown chart
ExplanationRelative sizing with story points compares items to a reference, which avoids time-based bias. Velocity measures completed work per sprint and is used to forecast future capacity. Ideal days express effort as uninterrupted time and are used to size work without the distortion of real interruptions. A sprint burndown chart shows remaining work over the sprint to monitor progress toward the Sprint Goal. A release date commitment is an outcome of forecasting rather than a monitoring or estimating artefact, so it does not match any of the planning practices listed.
-
13 Question 13 Single choice Agile Estimating, Planning, Monitoring and Control
A Product Owner at a telecommunications company writes a user story as: As the system, I want the billing module to be refactored into microservices, so that the code is better. The Developers cannot estimate it and the sprint review is likely to reject any increment that shows nothing a user can see. The Scrum Master is coaching the Product Owner on user story writing for a product. Which revision BEST follows good practice for user stories?
Correct Answer: BExplanationA good user story names a real user, a valuable outcome, and a benefit, which lets the Developers estimate and the review show something useful. The finance clerk story describes a concrete, testable value for a named user. The developer story is an internal technical task that has no user-visible value. The Product Owner story sets a deadline rather than a user need. The system-as-user story is not a real actor and the outcome is not something a user would experience.
-
14 Question 14 Order list Agile Estimating, Planning, Monitoring and Control
A Scrum team at an airline's operations software group has a product backlog containing many large, vague items that it cannot yet estimate. The Scrum Master wants the team to prepare the backlog so that sprint planning can select items with confidence. Arrange the steps in the order they must be performed to prepare the backlog, with the requirement that only refined items enter a sprint. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Order the product backlog so the most valuable refined items appear at the top
- Hold sprint planning and select items from the refined top of the product backlog
- Refine the top items with the Developers until they meet the team's Definition of Ready
- Split the large, vague items into smaller items the team can understand and estimate
Correct Answer:- Split the large, vague items into smaller items the team can understand and estimate
- Refine the top items with the Developers until they meet the team's Definition of Ready
- Order the product backlog so the most valuable refined items appear at the top
- Hold sprint planning and select items from the refined top of the product backlog
ExplanationLarge vague items must first be split into smaller, understandable items so that the team can estimate them. Refinement of the top items then makes them ready for planning. Ordering the product backlog ensures the most valuable refined items sit at the top, where the Developers will pull them from. Sprint planning comes last, selecting from the refined top. Ordering before splitting would sort items that cannot yet be compared, and planning before refinement would select items the team cannot estimate.
-
15 Question 15 Single choice Agile Estimating, Planning, Monitoring and Control
A Scrum team at an energy company has a Definition of Done that requires code review, automated tests passing, and documentation updated in the product wiki. Recently a story was marked done and demonstrated at the sprint review, but the release manager found that the story did not pass the security scan, which the team had never included. The team asks the Scrum Master why the increment was accepted as done. Which action should the Scrum Master coach the team to take FIRST?
Correct Answer: CExplanationThe Definition of Done defines what done means for the increment, and the gap here is that a required quality check is missing from it. The first step is for the whole team to review the Definition of Done and add the security scan so that every increment meets the same standard. Removing documentation lowers the quality bar rather than fixing the gap. Having the Product Owner refuse stories at review places the done judgement outside the team and does not correct the definition. A separate security sprint reintroduces a late phase that the Definition of Done is meant to prevent.
-
16 Question 16 Dropdown Agile Estimating, Planning, Monitoring and Control
A Scrum team at a retail bank wants to track sprint progress honestly and to plan the next sprint realistically. The Scrum Master is explaining the team's tracking artefacts to a new stakeholder. Complete the explanation by selecting the correct value for each blank.
Choose the correct value for each blank.
The shows the remaining work across the sprint and is used to monitor progress toward the Sprint Goal, while the is the sum of the story points of work completed per sprint, and it is used to forecast how much the team can commit to in .Correct Answer:The sprint burndown chart shows the remaining work across the sprint and is used to monitor progress toward the Sprint Goal, while the velocity is the sum of the story points of work completed per sprint, and it is used to forecast how much the team can commit to in the next sprint.
ExplanationA sprint burndown chart displays remaining work across the sprint and helps the team and stakeholders see whether the Sprint Goal is on track. Velocity is the amount of completed work per sprint, measured using story points, and it helps forecast capacity for future sprints. Velocity is used to plan the next sprint rather than the product vision or a release retrospective. The release roadmap and velocity chart mislabel the first blank, and the definition of done is a quality standard rather than a tracker.
-
17 Question 17 Single choice Scrum Master accountability
A Scrum Master at a travel company notices that the Daily Scrum has become a status report to the Product Owner, with each Developer reporting to the Product Owner in turn while the Scrum Master takes notes. Two Developers have stopped attending regularly and the team's Sprint Goal is at risk. Which tool or approach would BEST help the Scrum Master facilitate the team back to a Daily Scrum that serves the Developers?
Correct Answer: CExplanationThe Daily Scrum is for the Developers to inspect progress toward the Sprint Goal and plan the next day's work, and a visible Sprint Goal board supports that focus on the team's own coordination. It moves the event away from reporting to the Product Owner. A weekly status report to the Product Owner keeps the reporting pattern the team is trying to escape. A Gantt chart maintained for the Product Owner recreates status tracking rather than team planning. Having the Product Owner run the event and assign tasks takes ownership away from the Developers.
-
18 Question 18 Single choice Agile Way of Thinking
A software team at an online retailer has improved its delivery but the Scrum Master notices the same release problems recur every quarter. Retrospectives produce long lists of actions that are rarely completed. The team wants a systematic way to establish continuous improvement across sprints. Which approach BEST establishes continuous improvement in the Agile way of thinking?
Correct Answer: AExplanationContinuous improvement in Agile comes from a cycle of inspection and adaptation, where the team picks a small number of changes, inspects whether they helped at the next retrospective, and keeps or drops them. This matches the recurring issues the team faces while keeping the workload realistic. Adding more actions compounds the existing problem of incomplete follow-through. Holding retrospectives only at release milestones removes the frequent inspection that improvement requires. Making the Scrum Master or the Product Owner solely responsible for process change takes it away from the team, which owns its own way of working.
These are 18 of the 230 questions in the full ASM pack.
Get All 230 QuestionsGet all 230 questions & answers
Full access options for Exin ASM
Self-study
PDF Version
- 230 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 230 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 230 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the ASM Exam (Agile Scrum Master) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.