2026 Actual Exin ASM Dumps, Updated Exam Questions for Guaranteed Pass

Agile Scrum Master - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorExin
Exam codeASM
Exam nameAgile Scrum Master
Questions in pack230
Last updatedNovember 22, 2026
Related certificationsAgile Scrum

Free practice questions with explanations

Exin ASM Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
18
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Adopting Agile

    A traditional project manager at a regional insurer is becoming the Scrum Master for a team that has just moved from a waterfall process. The former manager used to assign tasks, track Gantt chart dates, and approve every change request personally. During the first sprints, the team keeps asking the new Scrum Master to decide task ownership and resequence the backlog for them. The organisation has a strict rule that all changes to scope must be traceable, and the sponsor wants visible progress every two weeks. Which action should the Scrum Master take FIRST to help the team move to self-management?

  2. 2 Question 2 Multiple choice Adopting Agile

    A software organisation is transitioning three legacy teams to Scrum. Each team has separate testers in a QA department that reports to a different director, and testers only receive work after developers hand off finished code. Sprints regularly end with stories marked done that have not been tested. Leadership wants to improve this without adding headcount. Which TWO actions best address the root cause and align with the Scrum concept of a cross-functional team? (Choose two.)

  3. 3 Question 3 Single choice Agile Way of Thinking

    A manufacturing company compares delivery approaches for a new scheduling feature. Requirements are uncertain, and stakeholders expect to learn what they need from early working versions. The head of operations wants predictable delivery dates for budgeting, yet also wants to change priorities after each two-week period. A consultant proposes a plan that fixes the full scope and date upfront to satisfy budgeting, while the team would still review progress each sprint. Which response best reflects the Agile way of thinking about predictability and flexibility?

  4. 4 Question 4 Drag and drop Agile Way of Thinking

    A product team wants to borrow ideas from other Agile approaches without abandoning Scrum. The Scrum Master is comparing approaches to decide which practices fit specific needs of the team. Match each stated need to the framework that best describes the practice.

    Drag each item onto its matching target. On a phone: tap an item, then tap a target.

    Scaling a single product backlog across many Scrum teams in one product
    Visualising work in progress and limiting the number of items active at once
    Engineering practices such as pair programming and test-driven development
    A framework for coordinating many Scrum teams with a portfolio of planning events
    LeSS
    Crystal
    Kanban
    Extreme Programming
    SAFe
  5. 5 Question 5 Single choice Complex Projects

    A bank is scaling Scrum across eight teams working on one online banking product. Each team has its own backlog, and the teams keep building overlapping features and discovering integration problems late in sprints. The Product Owner is overwhelmed trying to set priorities across all teams. The bank requires one prioritised view of the product's work for governance. Which arrangement BEST uses a single product backlog in this scaled environment?

  6. 6 Question 6 Dropdown Complex Projects

    A large insurer is adopting Nexus to coordinate three Scrum teams that share one integration pipeline. The integration failures happen because each team tests only its own changes. The Scrum Master is documenting the cross-team integration activity in the Nexus framework. Complete the description by selecting the correct value for each blank.

    Choose the correct value for each blank.

    In Nexus, the cross-team activity that surfaces integration issues and plans dependency resolution is called the , which is held after the Sprint and is facilitated by the .
  7. 7 Question 7 Order list Complex Projects

    A healthcare software company has decided to move its first team to Scrum after deciding that Agile suits its product. The company's regulatory context requires that the team demonstrate it can build increments before the wider organisation is committed to the change. Arrange the steps in the order they must be performed to start the pilot with the requirement that the team's first sprint produces a working increment. Arrange the steps in the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Perform the sprint with daily Scrum events to inspect progress toward the Sprint Goal
    2. Hold the sprint review to inspect the increment and adjust the product backlog
    3. Agree the Definition of Done and the product backlog ordering with the Product Owner
    4. Run the sprint planning event to select backlog items the Developers can commit to
  8. 8 Question 8 Single choice Scrum Master accountability

    In its second sprint, a Scrum team at a logistics firm is consistently failing to meet its Sprint Goal. The Developers say that a database administrator from another department must approve every schema change, and that approver is available only twice a week. Each approval request sits in an email queue. The Scrum Master has authority to escalate impediments in the organisation. The Product Owner suggests adding scope to the sprint so that the team looks busier. Which action is the Scrum Master's most appropriate response?

  9. 9 Question 9 Multiple choice Scrum Master accountability

    A Scrum Master is supporting a team where the Product Owner has begun directing individual Developers on how to implement stories, and the Developers have stopped raising technical concerns in the sprint. The Scrum Master wants to coach the team back to healthy roles. Which TWO actions best coach the team and respect the accountabilities within the Scrum framework? (Choose two.)

  10. 10 Question 10 Single choice Agile requirements and proper environment

    A government agency's procurement office has traditionally awarded contracts only when every requirement is written and signed. A team wants to adopt Scrum for a case-management system, but the contract requires a fixed scope and fixed price. The agency's managers agree that scope will change as users learn the system. Before the team starts, the director asks what cultural changes are needed for Agile to work. Which change is MOST essential before adoption?

  11. 11 Question 11 Single choice Agile Estimating, Planning, Monitoring and Control

    A Scrum team at a media company estimates its product backlog using story points. After four sprints, the velocity is trending upward, but a stakeholder shows the Scrum Master a release forecast based on that velocity that has slipped twice. The Developers have quietly started splitting stories into smaller stories at the end of sprints so each fits, and they have raised the point value of small items to match larger historical ones. The Scrum Master needs to correct the planning error. Which is the most appropriate response?

  12. 12 Question 12 Drag and drop Agile Estimating, Planning, Monitoring and Control

    A Scrum team at a hospital software vendor is preparing its next planning session and reviewing the artefacts it uses to estimate and track work. The Scrum Master wants each concept applied to the right purpose so that the forecast and the daily tracking remain honest. Match each planning practice to the purpose it best serves.

    Drag each item onto its matching target. On a phone: tap an item, then tap a target.

    Expressing effort as uninterrupted time without meetings or interruptions
    Showing remaining work across the sprint to monitor progress toward the Sprint Goal
    Measuring the amount of work the team completed per sprint to forecast future sprints
    Estimating effort by comparing the size of items to a reference item
    Velocity
    Release date commitment
    Relative sizing with story points
    Ideal days
    Sprint burndown chart
  13. 13 Question 13 Single choice Agile Estimating, Planning, Monitoring and Control

    A Product Owner at a telecommunications company writes a user story as: As the system, I want the billing module to be refactored into microservices, so that the code is better. The Developers cannot estimate it and the sprint review is likely to reject any increment that shows nothing a user can see. The Scrum Master is coaching the Product Owner on user story writing for a product. Which revision BEST follows good practice for user stories?

  14. 14 Question 14 Order list Agile Estimating, Planning, Monitoring and Control

    A Scrum team at an airline's operations software group has a product backlog containing many large, vague items that it cannot yet estimate. The Scrum Master wants the team to prepare the backlog so that sprint planning can select items with confidence. Arrange the steps in the order they must be performed to prepare the backlog, with the requirement that only refined items enter a sprint. Arrange the steps in the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Order the product backlog so the most valuable refined items appear at the top
    2. Hold sprint planning and select items from the refined top of the product backlog
    3. Refine the top items with the Developers until they meet the team's Definition of Ready
    4. Split the large, vague items into smaller items the team can understand and estimate
  15. 15 Question 15 Single choice Agile Estimating, Planning, Monitoring and Control

    A Scrum team at an energy company has a Definition of Done that requires code review, automated tests passing, and documentation updated in the product wiki. Recently a story was marked done and demonstrated at the sprint review, but the release manager found that the story did not pass the security scan, which the team had never included. The team asks the Scrum Master why the increment was accepted as done. Which action should the Scrum Master coach the team to take FIRST?

  16. 16 Question 16 Dropdown Agile Estimating, Planning, Monitoring and Control

    A Scrum team at a retail bank wants to track sprint progress honestly and to plan the next sprint realistically. The Scrum Master is explaining the team's tracking artefacts to a new stakeholder. Complete the explanation by selecting the correct value for each blank.

    Choose the correct value for each blank.

    The shows the remaining work across the sprint and is used to monitor progress toward the Sprint Goal, while the is the sum of the story points of work completed per sprint, and it is used to forecast how much the team can commit to in .
  17. 17 Question 17 Single choice Scrum Master accountability

    A Scrum Master at a travel company notices that the Daily Scrum has become a status report to the Product Owner, with each Developer reporting to the Product Owner in turn while the Scrum Master takes notes. Two Developers have stopped attending regularly and the team's Sprint Goal is at risk. Which tool or approach would BEST help the Scrum Master facilitate the team back to a Daily Scrum that serves the Developers?

  18. 18 Question 18 Single choice Agile Way of Thinking

    A software team at an online retailer has improved its delivery but the Scrum Master notices the same release problems recur every quarter. Retrospectives produce long lists of actions that are rarely completed. The team wants a systematic way to establish continuous improvement across sprints. Which approach BEST establishes continuous improvement in the Agile way of thinking?

These are 18 of the 230 questions in the full ASM pack.

Get All 230 Questions

Get all 230 questions & answers

742 Satisfied customers
95.5% Pass rate feedback
81.6% Said questions matched
96% Found material helpful

Full access options for Exin ASM

Self-study

PDF Version

$40.00 $20.00
  • 230 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 230 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the ASM Exam (Agile Scrum Master) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed