2026 Actual CIMA CIMAPRA19-E02-1 Dumps, Updated Exam Questions for Guaranteed Pass

E2 Managing Performance - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorCIMA
Exam codeCIMAPRA19-E02-1
Exam nameE2 Managing Performance
Questions in pack185
Last updatedNovember 22, 2026
Related certificationsCIMA Professional Qualification

Free practice questions with explanations

CIMA CIMAPRA19-E02-1 Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
11
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Business Models

    Harbourline Foods, a mid-sized chilled-goods distributor, is reviewing its business model after a pilot in which customers were offered free next-day delivery in exchange for a 12-month minimum purchase commitment. The pilot raised average order value by 18 percent but delivery costs rose faster than revenue, and two of the largest customers have asked to move to pay-per-delivery pricing. The board requires a decision within one quarter and wants the performance measures to reflect how value is created and captured rather than only short-term margin. Which action is the BEST next step for management accountants to recommend?

  2. 2 Question 2 Single choice Business Models

    Quillon Software sells a subscription analytics platform. Its finance team has reported strong subscription revenue growth for three years, yet cash generation has fallen. Analysis shows that customer acquisition costs have roughly doubled, and customers on the lowest-priced tier churn within eight months, before acquisition costs are recovered. Leadership wants to restructure its performance reporting so that the business model is assessed on the economics of each customer cohort. Which measure should management accountants prioritise to best evaluate whether the subscription model is sustainable?

  3. 3 Question 3 Single choice Managing people performance

    Brightwater Clinics runs a performance management system in which line managers rate staff quarterly on a five-point scale. A review finds that ratings for staff in one region average 4.6, while the company average is 3.1, and the regional managers' bonus pool is funded from the average rating of their teams. The HR director wants to improve the reliability of the appraisal process within the next two review cycles, without removing managerial judgement or introducing a new software platform, which the board has declined to fund. Which action is the MOST appropriate first step?

  4. 4 Question 4 Single choice Managing people performance

    Stellan Logistics measures warehouse supervisors on a balanced scorecard that includes units picked per hour, error rate and staff engagement survey scores. Over the last year, pick rates have risen sharply, but error rates have also increased and two supervisors resigned citing unrealistic targets. The operations director wants a performance measure that discourages supervisors from gaining pick rates at the expense of accuracy and wellbeing. Which change to the scorecard is the MOST appropriate?

  5. 5 Question 5 Multiple choice Managing people performance

    Ostrander Engineering uses annual performance reviews in which project engineers are rated on delivery against objectives. Feedback shows engineers avoid collaborative tasks that would reduce their own individual output figures, and the HR team is concerned that the appraisal measures are damaging teamwork. The company wants changes that reward collaboration and reduce the distorting effect of individual output measures, using measures that are consistent with good performance management practice. Which TWO actions best meet these requirements? (Choose two.)

  6. 6 Question 6 Order list Managing projects

    Calder Infrastructure is running a 30-month bridge refurbishment project with a fixed budget. At month 14 the project is reporting a schedule variance and the sponsor has asked the project accountant to produce an updated forecast and recovery plan for the steering committee. The accountant must use earned value information to do this rigorously. Arrange the steps in the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Validate the work package progress percentages against measured physical completion before relying on them.
    2. Calculate earned value for the reporting date using budgeted cost of work performed and actual cost data.
    3. Compute the schedule performance index and cost performance index from the earned value figures.
    4. Agree a recovery plan with the project manager and present the revised forecast to the steering committee.
    5. Derive an estimate at completion using the cost performance index, adjusted for any known remaining risks.
  7. 7 Question 7 Order list Managing projects

    Vantra Telecom is replacing its billing system through a 14-month project with a fixed-price vendor contract. The finance director wants the project's cost control to be set up correctly before significant spend is committed. The project accountant must establish the control framework in a sensible sequence. Arrange the steps in the order they must be performed.

    Drag the steps into the correct order, or use the arrows.

    1. Record actual costs against the cost codes monthly and report variances against the baseline.
    2. Establish the authorisation thresholds and change control process for variations to the baseline.
    3. Agree the work breakdown structure with the project manager and map each work package to a cost code.
    4. Compare the baseline with the vendor contract milestones to confirm that payments track delivered work.
    5. Set a cost baseline by approving the budgeted cost for each work package at the outset.
  8. 8 Question 8 Drag and drop Managing projects

    Pembrook Retail is running a portfolio of three projects: a store refit, a loyalty app and a warehouse automation scheme. The programme board wants each project's reported position to be assessed using the most appropriate project performance technique for the question being asked. Match each reporting requirement to the technique that best meets it.

    Drag each item onto its matching target. On a phone: tap an item, then tap a target.

    Identifying which tasks lie on the longest sequence and drive the completion date
    Forecasting the final project cost from performance to date
    Judging whether the project is ahead or behind its planned schedule in value terms
    Break-even volume analysis
    Estimate at completion using cost performance index
    Schedule variance from earned value
    Net present value of projected cash flows
    Critical path analysis
  9. 9 Question 9 Dropdown Managing projects

    Greyhaven Housing is monitoring a residential development project at month 9. The project accountant is entering earned value figures into a spreadsheet to calculate the performance indices. The budgeted cost of work scheduled is 1,200,000, the budgeted cost of work performed is 1,050,000 and the actual cost of work performed is 1,120,000. Complete the formulae by selecting the correct value for each blank.

    Choose the correct value for each blank.

    Schedule performance index = / ; Cost performance index = /
  10. 10 Question 10 Dropdown Managing projects

    Ashgrove Pharma is running a clinical equipment upgrade project under a board-approved budget that must not be exceeded. The project accountant needs to set the approved baseline and then assess whether a proposed change is within authority. The project's approved budget at completion is 4,800,000 and the revised estimate for an additional sensor module is 310,000, which exceeds the 250,000 limit the project manager can approve alone. Complete the statement by selecting the correct value for each blank.

    Choose the correct value for each blank.

    The sensor module change must be authorised by the because it exceeds the limit, and the cost baseline is only updated once the change is .
  11. 11 Question 11 Single choice Business Models

    Meridian Print Solutions has historically earned most of its revenue from selling industrial printers and then charging for consumables. Sales of printers are falling as customers extend equipment life, and consumables revenue is now under pressure from third-party cartridges. The CFO is evaluating whether to shift towards a managed print service in which customers pay a fixed monthly fee per device covering hardware, maintenance and supplies. The service would need significant upfront investment, and the board requires the business model change to be assessed on the value it creates for customers and the economics it captures for Meridian. Which analysis is the MOST appropriate to support the decision?

These are 11 of the 185 questions in the full CIMAPRA19-E02-1 pack.

Get All 185 Questions

Get all 185 questions & answers

728 Satisfied customers
94.3% Pass rate feedback
83.2% Said questions matched
93% Found material helpful

Full access options for CIMA CIMAPRA19-E02-1

Self-study

PDF Version

$40.00 $20.00
  • 185 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 185 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CIMAPRA19-E02-1 Exam (E2 Managing Performance) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed