CIMA CIMAPRA19-E02-1 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 11
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Business Models
Harbourline Foods, a mid-sized chilled-goods distributor, is reviewing its business model after a pilot in which customers were offered free next-day delivery in exchange for a 12-month minimum purchase commitment. The pilot raised average order value by 18 percent but delivery costs rose faster than revenue, and two of the largest customers have asked to move to pay-per-delivery pricing. The board requires a decision within one quarter and wants the performance measures to reflect how value is created and captured rather than only short-term margin. Which action is the BEST next step for management accountants to recommend?
Correct Answer: CExplanationHarbourline's problem is a business model question: value is being offered (free delivery) without capturing its cost, and the board wants measures reflecting value creation and capture. A segment-level unit-economics analysis that ties delivery cost drivers to the revenue each segment generates lets management compare the commitment-based and pay-per-delivery models on the same basis. Renegotiating surcharges only treats a cost symptom and leaves the model unchanged. Accepting the large customers' request without analysis risks repeating the margin problem across the base. Lengthening the commitment locks in a loss-making structure rather than testing whether it is viable.
-
2 Question 2 Single choice Business Models
Quillon Software sells a subscription analytics platform. Its finance team has reported strong subscription revenue growth for three years, yet cash generation has fallen. Analysis shows that customer acquisition costs have roughly doubled, and customers on the lowest-priced tier churn within eight months, before acquisition costs are recovered. Leadership wants to restructure its performance reporting so that the business model is assessed on the economics of each customer cohort. Which measure should management accountants prioritise to best evaluate whether the subscription model is sustainable?
Correct Answer: CExplanationQuillon's sustainability question hinges on whether revenue from each cohort exceeds the cost of acquiring and serving it. Comparing customer lifetime value with acquisition cost by cohort and tier exposes the lowest tier's early churn before acquisition costs are recovered, which total recurring revenue hides. Total ARR growth is precisely the figure that looked healthy while cash fell. Revenue per sales employee measures sales efficiency, not whether the customers themselves are profitable. Hosting gross margin ignores the acquisition spend that is driving the cash problem.
-
3 Question 3 Single choice Managing people performance
Brightwater Clinics runs a performance management system in which line managers rate staff quarterly on a five-point scale. A review finds that ratings for staff in one region average 4.6, while the company average is 3.1, and the regional managers' bonus pool is funded from the average rating of their teams. The HR director wants to improve the reliability of the appraisal process within the next two review cycles, without removing managerial judgement or introducing a new software platform, which the board has declined to fund. Which action is the MOST appropriate first step?
Correct Answer: DExplanationThe regional rating inflation, combined with a bonus funded by team ratings, creates a clear incentive problem that calibration addresses directly. Calibration sessions compare ratings across managers against shared evidence, improving consistency without removing judgement or buying software, which satisfies both constraints. A binary scale discards the differentiation the business needs and does not fix the bias. Forcing ratings down to the average is a manipulation that undermines the appraisal's credibility. Rewarding managers for having more above-average staff creates the opposite incentive and worsens inflation.
-
4 Question 4 Single choice Managing people performance
Stellan Logistics measures warehouse supervisors on a balanced scorecard that includes units picked per hour, error rate and staff engagement survey scores. Over the last year, pick rates have risen sharply, but error rates have also increased and two supervisors resigned citing unrealistic targets. The operations director wants a performance measure that discourages supervisors from gaining pick rates at the expense of accuracy and wellbeing. Which change to the scorecard is the MOST appropriate?
Correct Answer: AExplanationStellan's scorecard rewards pick rates in isolation, so supervisors can trade accuracy for speed without penalty. Making the pick-rate score conditional on staying below an error threshold builds the trade-off into the measure, so improvements that raise errors earn nothing. Removing the engagement measure eliminates the one signal that warns of wellbeing problems. Increasing the weight on pick rate intensifies the very incentive that is causing the problem. A fixed target ignoring seasonal demand may be unfair, but it does not address the accuracy trade-off the director is concerned about.
-
5 Question 5 Multiple choice Managing people performance
Ostrander Engineering uses annual performance reviews in which project engineers are rated on delivery against objectives. Feedback shows engineers avoid collaborative tasks that would reduce their own individual output figures, and the HR team is concerned that the appraisal measures are damaging teamwork. The company wants changes that reward collaboration and reduce the distorting effect of individual output measures, using measures that are consistent with good performance management practice. Which TWO actions best meet these requirements? (Choose two.)
Correct Answer: C, EExplanationIncluding team-level outcome measures in individual objectives makes collaboration part of what each engineer is rewarded for, directly counteracting the output-only incentive. A structured peer-feedback element captures the support behaviours that output figures cannot show, and is a recognised feature of balanced appraisal. Ranking by individual output and basing bonuses solely on it reinforces the distortion the company is trying to remove. Dropping objectives in favour of an unstructured manager impression reduces transparency and reliability, which works against good practice.
-
6 Question 6 Order list Managing projects
Calder Infrastructure is running a 30-month bridge refurbishment project with a fixed budget. At month 14 the project is reporting a schedule variance and the sponsor has asked the project accountant to produce an updated forecast and recovery plan for the steering committee. The accountant must use earned value information to do this rigorously. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Validate the work package progress percentages against measured physical completion before relying on them.
- Calculate earned value for the reporting date using budgeted cost of work performed and actual cost data.
- Compute the schedule performance index and cost performance index from the earned value figures.
- Agree a recovery plan with the project manager and present the revised forecast to the steering committee.
- Derive an estimate at completion using the cost performance index, adjusted for any known remaining risks.
Correct Answer:- Calculate earned value for the reporting date using budgeted cost of work performed and actual cost data.
- Compute the schedule performance index and cost performance index from the earned value figures.
- Derive an estimate at completion using the cost performance index, adjusted for any known remaining risks.
- Agree a recovery plan with the project manager and present the revised forecast to the steering committee.
- Validate the work package progress percentages against measured physical completion before relying on them.
ExplanationThe reliable sequence starts by validating the progress data, because earned value is only as good as the percent-complete figures feeding it. Earned value is then calculated for the reporting date, followed by the performance indices derived from those values. The estimate at completion is built from the cost performance index and adjusted for remaining risk, and only then can a recovery plan be agreed and presented. Presenting a forecast before validating progress would base the steering committee's decision on unverified data.
-
7 Question 7 Order list Managing projects
Vantra Telecom is replacing its billing system through a 14-month project with a fixed-price vendor contract. The finance director wants the project's cost control to be set up correctly before significant spend is committed. The project accountant must establish the control framework in a sensible sequence. Arrange the steps in the order they must be performed.
Drag the steps into the correct order, or use the arrows.
- Record actual costs against the cost codes monthly and report variances against the baseline.
- Establish the authorisation thresholds and change control process for variations to the baseline.
- Agree the work breakdown structure with the project manager and map each work package to a cost code.
- Compare the baseline with the vendor contract milestones to confirm that payments track delivered work.
- Set a cost baseline by approving the budgeted cost for each work package at the outset.
Correct Answer:- Agree the work breakdown structure with the project manager and map each work package to a cost code.
- Set a cost baseline by approving the budgeted cost for each work package at the outset.
- Establish the authorisation thresholds and change control process for variations to the baseline.
- Record actual costs against the cost codes monthly and report variances against the baseline.
- Compare the baseline with the vendor contract milestones to confirm that payments track delivered work.
ExplanationA cost baseline can only be set once the work breakdown structure defines the work packages and their cost codes, so the structure comes first. The baseline is then approved, and change control governs any later movement away from it. Actual costs are recorded and variances reported only once there is a baseline to measure against. Checking the baseline against contract milestones is a final reconciliation step that depends on the baseline and reporting being in place.
-
8 Question 8 Drag and drop Managing projects
Pembrook Retail is running a portfolio of three projects: a store refit, a loyalty app and a warehouse automation scheme. The programme board wants each project's reported position to be assessed using the most appropriate project performance technique for the question being asked. Match each reporting requirement to the technique that best meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Identifying which tasks lie on the longest sequence and drive the completion dateForecasting the final project cost from performance to dateJudging whether the project is ahead or behind its planned schedule in value termsBreak-even volume analysisEstimate at completion using cost performance indexSchedule variance from earned valueNet present value of projected cash flowsCritical path analysisCorrect Answer:- Forecasting the final project cost from performance to date → Estimate at completion using cost performance index
- Judging whether the project is ahead or behind its planned schedule in value terms → Schedule variance from earned value
- Identifying which tasks lie on the longest sequence and drive the completion date → Critical path analysis
ExplanationForecasting the final cost from performance to date is the purpose of an estimate at completion built on the cost performance index. Schedule variance from earned value measures whether value earned is ahead or behind plan. The critical path identifies the sequence of tasks that determines the completion date. Net present value evaluates investment appeal and break-even analysis addresses volume and profit thresholds, so neither answers a project performance reporting question.
-
9 Question 9 Dropdown Managing projects
Greyhaven Housing is monitoring a residential development project at month 9. The project accountant is entering earned value figures into a spreadsheet to calculate the performance indices. The budgeted cost of work scheduled is 1,200,000, the budgeted cost of work performed is 1,050,000 and the actual cost of work performed is 1,120,000. Complete the formulae by selecting the correct value for each blank.
Choose the correct value for each blank.
Schedule performance index = / ; Cost performance index = /Correct Answer:Schedule performance index = Budgeted cost of work performed / Budgeted cost of work scheduled; Cost performance index = Budgeted cost of work scheduled / Actual cost of work performed
ExplanationThe schedule performance index is earned value divided by planned value, so budgeted cost of work performed is divided by budgeted cost of work scheduled. The cost performance index is earned value divided by actual cost, so budgeted cost of work performed is divided by actual cost of work performed. Using the scheduled value as the numerator of the cost index inverts the ratio, and estimate at completion is an output of the indices rather than an input to them.
-
10 Question 10 Dropdown Managing projects
Ashgrove Pharma is running a clinical equipment upgrade project under a board-approved budget that must not be exceeded. The project accountant needs to set the approved baseline and then assess whether a proposed change is within authority. The project's approved budget at completion is 4,800,000 and the revised estimate for an additional sensor module is 310,000, which exceeds the 250,000 limit the project manager can approve alone. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
The sensor module change must be authorised by the because it exceeds the limit, and the cost baseline is only updated once the change is .Correct Answer:The sensor module change must be authorised by the steering committee because it exceeds the 250,000 authority limit, and the cost baseline is only updated once the change is approved.
ExplanationThe change of 310,000 exceeds the project manager's 250,000 authority, so it must go to the steering committee, which holds the higher approval level. The cost baseline changes only when the change has been formally approved, not when it is merely forecast, invoiced or reported. The 4,800,000 budget is the baseline itself rather than the authority limit, so it is not the threshold the change breaches.
-
11 Question 11 Single choice Business Models
Meridian Print Solutions has historically earned most of its revenue from selling industrial printers and then charging for consumables. Sales of printers are falling as customers extend equipment life, and consumables revenue is now under pressure from third-party cartridges. The CFO is evaluating whether to shift towards a managed print service in which customers pay a fixed monthly fee per device covering hardware, maintenance and supplies. The service would need significant upfront investment, and the board requires the business model change to be assessed on the value it creates for customers and the economics it captures for Meridian. Which analysis is the MOST appropriate to support the decision?
Correct Answer: CExplanationChoosing between a product-sale model and a managed service is a business model decision, so the analysis must compare the lifetime economics of each model, including how much value customers receive and what Meridian captures and spends serving them. Customer lifetime value compared across the two models, with cost to serve, does exactly that. A payback period that ignores future revenue understates a recurring-revenue model. Margin comparisons on printers and cartridges describe the current model only, not the alternative. Manufacturing budget savings address cost, not the choice of how value is delivered and charged for.
These are 11 of the 185 questions in the full CIMAPRA19-E02-1 pack.
Get All 185 QuestionsGet all 185 questions & answers
Full access options for CIMA CIMAPRA19-E02-1
Self-study
PDF Version
- 185 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 185 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 185 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CIMAPRA19-E02-1 Exam (E2 Managing Performance) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.