Exam Information
Free practice questions with explanations
GIAC GCPM Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 13
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Delivery Performance Domain
A healthcare IT project is delivering a patient-portal release in four increments. Increment 2 has met its acceptance criteria functionally, but the sponsor notes that two of the nine business-value benefits tied to the release (reduced call-centre volume and portal adoption above 60 percent) cannot yet be measured because the analytics instrumentation was descoped. The steering committee must decide whether Increment 2 counts as delivered. Regulatory audit requires that benefits realisation be evidenced within 90 days of go-live. Which action best ensures the project delivers the business value it was undertaken to achieve?
Correct Answer: CExplanationFunctional acceptance alone does not demonstrate delivery of the business value the project was chartered to achieve. Because the audit requires benefits evidence within 90 days, the instrumentation that produces the measures must be in place at go-live, so reinstating it as scope and holding closure keeps the benefit linkage intact. Signing off on functional criteria alone leaves two of nine benefits unverifiable, which fails the audit requirement. Handing measurement to operations without changing the plan leaves no owner or funding for the work, and deferring the benefits update to Increment 4 means adoption data arrives too late to meet the 90-day window.
-
2 Question 2 Order list Development Approach and Life Cycle Performance Domain
A logistics company is moving a warehouse-routing module from a waterfall plan to an iterative cadence after two failed releases. The team currently has a fixed-scope contract for a single delivery date, and the sponsor has agreed to convert it to a time-and-materials arrangement with a prioritised backlog. The first sprint must not start until the scope governance is agreed, because the contract requires change control through the vendor's assigned manager. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Hold a sprint planning session to commit the first increment of backlog items
- Establish the release cadence and sprint length with the delivery team
- Run the first sprint and present a working increment for stakeholder review
- Agree the revised change-control and approval thresholds with the vendor manager
- Prioritise the existing requirements into a product backlog with business-value ranking
Correct Answer:- Agree the revised change-control and approval thresholds with the vendor manager
- Prioritise the existing requirements into a product backlog with business-value ranking
- Establish the release cadence and sprint length with the delivery team
- Hold a sprint planning session to commit the first increment of backlog items
- Run the first sprint and present a working increment for stakeholder review
ExplanationBefore the iterative cadence can operate, the contractual governance must change, so change-control and approval thresholds are agreed first. Only then does it make sense to rank requirements into a backlog that will be governed under those thresholds. The cadence and sprint length can be set once the backlog is ordered, sprint planning commits work from the top of that backlog, and the review of a working increment comes last. Starting sprint planning before governance is agreed would commit scope the vendor manager has not approved, which the contract forbids.
-
3 Question 3 Single choice Earned Value Technique EVT
A data-migration project was baselined at a budget at completion of 480,000 units of cost over a 12-month schedule. At the end of month 6, the planned value is 240,000, the earned value is 200,000, and the actual cost is 260,000. The project manager must forecast the estimate at completion, assuming the current cost efficiency continues for the remaining work. The sponsor has asked for the forecast that reflects the observed cost performance rather than the original plan. Which EAC should the project manager report?
Correct Answer: DExplanationThe cost performance index is earned value divided by actual cost, which gives 200,000 over 260,000, or about 0.769. Dividing the 480,000 BAC by this CPI yields an estimate at completion of roughly 624,000, which reflects the observed cost efficiency continuing. Adding remaining budget to actual cost would ignore the fact that the remaining work is priced at the current efficiency. Dividing by the schedule index mixes schedule performance into a cost forecast. Keeping the original BAC ignores the 60,000 overrun already incurred, which is exactly the forecast the sponsor asked the project manager to avoid.
-
4 Question 4 Dropdown Earned Value Technique EVT
A construction program manager reviews a weekly status report for a building fit-out. The schedule performance index is 0.82 and the cost performance index is 1.05. The manager needs the report's formula lines to be correct so that the forecast of total duration reflects the schedule slippage and not the cost position. Select the correct value for each blank in the forecast statement.
Choose the correct value for each blank.
Estimate at completion for schedule-driven duration = divided byCorrect Answer:Estimate at completion for schedule-driven duration = Budget at completion divided by Schedule performance index
ExplanationSchedule-based duration forecasting divides the budget at completion by the schedule performance index, so that schedule slippage stretches the projected time. Using the cost performance index here would confuse the duration signal with the favourable cost position of 1.05. The planned value is a measure of work scheduled, not a basis for dividing, and cost variance is a difference rather than a ratio. Estimate to complete is a remaining-work figure, not a divisor, so it cannot correctly complete this forecast statement.
-
5 Question 5 Multiple choice Effective Communication
A pharmaceutical software project has 14 stakeholders across regulatory, clinical, vendor, and executive groups. The communications plan currently sends a single weekly status email to everyone, and the regulatory affairs lead has complained that vendor-level technical detail obscures compliance risks. Two executives have stated they only want exception reporting. The project manager must revise the plan so that each group receives information matching its decision needs. Which TWO changes best achieve this? (Choose two.)
Correct Answer: D, EExplanationA stakeholder-specific communications matrix matches content, frequency, and channel to each group, which directly addresses the regulatory lead's complaint about irrelevant technical detail. An exception-based summary for executives respects their stated need and tolerance-based thresholds. A glossary does not stop the same unfiltered content reaching people who need compliance risks, and daily email to everyone increases noise. Removing direct distribution in favour of a dashboard leaves stakeholders responsible for finding their own information, which conflicts with the need for targeted delivery.
-
6 Question 6 Drag and drop Managing Project Quality
A medical device firm must validate a firmware release that will be shipped to hospitals. The quality plan requires that each quality requirement be measured with an agreed method, that defects be recorded and traced, and that the final release be independently validated before shipment. The quality manager is building the quality control records for the release. Match each quality activity to the technique that best fulfils it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Confirm the firmware meets the documented requirements before shipmentDetect recurring defect causes across successive test cyclesRecord each defect with its originating requirement for traceabilityMonitor the stability of the test pass-rate over timeCost of quality estimationIndependent validation against acceptance criteriaPareto analysis of defect categoriesStakeholder engagement assessmentRequirements traceability matrixControl chart with defined upper and lower limitsCorrect Answer:- Confirm the firmware meets the documented requirements before shipment → Independent validation against acceptance criteria
- Detect recurring defect causes across successive test cycles → Pareto analysis of defect categories
- Monitor the stability of the test pass-rate over time → Control chart with defined upper and lower limits
- Record each defect with its originating requirement for traceability → Requirements traceability matrix
ExplanationIndependent validation against acceptance criteria is the mechanism that confirms a release meets its documented requirements before shipment. A Pareto analysis ranks defect categories to surface the recurring causes that dominate. A control chart with limits shows whether a process such as test pass-rate is stable or drifting. Linking each defect to its requirement is the purpose of a traceability matrix. Cost of quality and stakeholder engagement assessment are real project-management concepts, but neither produces the validation, cause-ranking, stability, or traceability records this release requires.
-
7 Question 7 Single choice Managing Project Quality
A regional bank's payments-integration project has a quality requirement that transaction reconciliation must match the ledger within 0.01 percent on every batch. During a three-week test window, the team's control chart shows the reconciliation variance drifting upward, though every individual batch remains within the 0.01 percent limit. The project manager is asked what action best protects the quality requirement before the production cutover in five weeks. Which action should the project manager take FIRST?
Correct Answer: CExplanationA control chart can show a non-random pattern such as a sustained upward drift even when every point stays inside the specification limit, and that pattern indicates a likely special cause that should be investigated before cutover. Declaring the requirement met on individual batch results ignores the trend the chart reveals. Widening the tolerance changes the requirement itself, which the bank has not authorised. Removing batches from the sample to make the chart look stable is data manipulation that would invalidate the quality evidence.
-
8 Question 8 Dropdown Delivery Performance Domain
A government digital-services project must show the steering board how scope is being controlled against the accepted change log. The project office maintains a register in which each approved change is recorded with its impact on baseline scope. The register currently shows 27 changes, of which 19 are approved and 8 remain pending, and the board wants only approved changes reflected in the current scope baseline. Select the correct value for each blank in the register filter.
Choose the correct value for each blank.
Filter the change register to show approved changes only: change_status = AND baseline_applied =Correct Answer:Filter the change register to show approved changes only: change_status = Approved AND baseline_applied = Yes
ExplanationThe board's requirement is that only approved changes shape the current scope baseline, so the filter must select the approved status and require that those changes have actually been applied to the baseline. Pending changes are the eight awaiting decision and must be excluded from the baseline view. Rejected and deferred changes are also not approved, so they cannot be used as the status value here. The baseline_applied flag must be set to Yes, since partial or unknown values would not give the clean scope picture the board asked for.
-
9 Question 9 Single choice Development Approach and Life Cycle Performance Domain
A hospital is implementing a clinical scheduling system using a phased life cycle with a fixed regulatory go-live date in nine months. The vendor proposes a rolling-wave plan in which detailed requirements for later phases are elaborated just before each wave starts. The compliance office objects because the regulator requires that the full set of safety-critical requirements be approved before any build begins. Yet the operations director wants early delivery of the appointment module, which has no safety-critical requirements. Which approach best satisfies both the regulatory constraint and the early-delivery goal?
Correct Answer: CExplanationThe regulator's rule is specific to safety-critical requirements, so those must be fully approved before build, while the appointment module carries no such requirement and can be delivered earlier through rolling-wave elaboration. This split honours the regulation and the operations director's need for early value. A pure waterfall plan delays value unnecessarily for modules the rule does not cover. Building first and approving retrospectively directly violates the stated precondition, and seeking a waiver assumes an exception the regulator has not offered.
-
10 Question 10 Drag and drop Development Approach and Life Cycle Performance Domain
A retail bank runs a digital-lending program that combines an iterative development team with a central governance board that meets quarterly. The program office wants each governance activity matched to the life cycle concern it best addresses, so that the cadence of decisions fits the development rhythm. Match each activity to the life cycle concern it addresses.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Sprint review with the business ownerQuarterly portfolio funding reviewArchitecture review before a new integration phaseDaily stand-up of the delivery teamChecking technical design before committing build effortSurfacing impediments to the current iterationValidating working increments against stakeholder expectationsFinal contract settlement with the vendorAnnual external audit of the business caseConfirming investment continues to justify its costCorrect Answer:- Sprint review with the business owner → Validating working increments against stakeholder expectations
- Quarterly portfolio funding review → Confirming investment continues to justify its cost
- Daily stand-up of the delivery team → Surfacing impediments to the current iteration
- Architecture review before a new integration phase → Checking technical design before committing build effort
ExplanationA sprint review puts working increments in front of the business owner to validate them, which is its purpose within an iterative life cycle. Quarterly portfolio funding reviews test whether continued investment is still justified, matching the governance cadence to the funding concern. The daily stand-up surfaces impediments inside the current iteration, and an architecture review before a new integration phase checks the design before build effort is committed. Final contract settlement and an annual external audit are real governance activities but do not address the iteration-level and cadence concerns the program office is mapping.
-
11 Question 11 Single choice Delivery Performance Domain
A utilities company is running an advanced metering rollout across 40 regional sites. The project has a benefit of reducing manual meter reads by 70 percent within 12 months of full deployment. Six months in, the deployment is 30 percent complete on schedule, but the vendor's firmware fix for a communication fault is delayed by four months, and the operations director proposes accepting the existing meters as complete so that the benefit-tracking metric can start on the sites already live. The procurement contract states that a site is only accepted once it is communicating reliably for 30 consecutive days. Which action should the project manager take?
Correct Answer: BExplanationThe contract defines acceptance as 30 consecutive days of reliable communication, so only sites meeting that rule count as delivered, and benefit tracking should be based on those verified sites. Accepting live sites that are not yet communicating reliably contradicts the contract and inflates the delivery picture. Redefining the benefit to a meter count changes what the project promised to deliver and hides the shortfall. Assuming the firmware fix will work is an unverified expectation that the measurement cannot rely on.
-
12 Question 12 Order list Earned Value Technique EVT
A software program manager must produce an earned value report for the steering committee at the end of a reporting period. The schedule uses a control account with work packages that were baselined with planned values, and some work packages are only partially complete. The report must reflect the earned value method rather than a simple percent-complete estimate from the team. Arrange the steps in the order the program manager must perform them.
Drag the steps into the correct order, or use the arrows.
- Confirm the planned value baseline for each control account before measuring progress
- Record the actual cost incurred for each control account for the period
- Measure the percent complete of each work package using the agreed earned value rule
- Compare earned value with planned value and actual cost to derive variances and indices
- Calculate earned value by applying percent complete to each work package budget
Correct Answer:- Record the actual cost incurred for each control account for the period
- Measure the percent complete of each work package using the agreed earned value rule
- Calculate earned value by applying percent complete to each work package budget
- Compare earned value with planned value and actual cost to derive variances and indices
- Confirm the planned value baseline for each control account before measuring progress
ExplanationEarned value analysis depends on a fixed reference, so the planned value baseline for each control account must be confirmed first. Progress is then measured using the agreed rule for each work package, and that percent complete is converted into earned value against the work package budget. Actual cost is recorded from the accounting data for the same period, and only then can variances and performance indices be derived by comparing earned value, planned value, and actual cost. Deriving indices before the baseline and earned value are set would produce results with no valid reference point.
-
13 Question 13 Multiple choice Managing Project Quality
A pharmaceutical contract research project must validate a clinical data-capture application before a regulator's inspection. The quality plan requires that validation evidence be complete, traceable, and reproducible. The project manager is reviewing the validation approach with the quality assurance lead, who has noted that the team's current test records are only screenshots without linked requirement identifiers. Which TWO actions will best ensure the validation evidence meets these requirements? (Choose two.)
Correct Answer: A, DExplanationA traceability matrix that links each requirement to its tests and results gives the complete and traceable chain the quality plan requires. Version-controlled test scripts with captured environment configuration make the evidence reproducible, because the same test can be rerun with the same setup. Replacing automated regression testing with a manual sign-off removes reproducibility, and relying on memory to link screenshots fails the traceability requirement outright. Limiting validation to recently changed requirements leaves the rest of the system unvalidated, so the evidence would be incomplete.
These are 13 of the 400 questions in the full GCPM pack.
Get All 400 QuestionsGet all 400 questions & answers
Full access options for GIAC GCPM
Self-study
PDF Version
- 400 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 400 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 400 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the GCPM Exam (GIAC Certified Project Manager) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.