1 Question 1 Single choice Module 1 - Overview of Testing
A fintech team is three weeks from a release. The product owner insists that because the last sprint's regression suite passed with zero defects, the new payment-refund module needs no further testing, since 'testing proves the software is correct.' The test lead must respond to the stakeholder using the fundamental testing principles. Which response is most appropriate?
Correct Answer: DExplanationThe principle that testing shows the presence of defects, not their absence, is the decisive point here. A clean regression run reduces risk but cannot prove correctness, so the stakeholder's conclusion does not follow. The option demanding exhaustive testing contradicts the principle that exhaustive testing is impractical, and the option excluding the module treats absence of evidence as evidence of absence. The clustering option misreads the defect clustering principle, which concerns where defects concentrate, not a guarantee that other modules are clean.
-
2 Question 2 Multiple choice Module 2 - Test Plan
A medical device firm must produce test documentation for an audit of its embedded firmware validation. The auditors require that the plan define the scope of what is and is not tested, the test strategy and risk approach, and the criteria for ending testing. The team lead is deciding which elements belong in the Test Plan itself rather than in a separate artefact produced during execution. (Choose two.)
Correct Answer: A, CExplanationEntry and exit criteria and scope definitions, including what is excluded, are planning content and belong in the Test Plan, which defines objectives, scope and strategy. Test Incident Reports and test logs are produced during execution, and the final defect counts belong to the Test Summary Report, which is written after execution completes. Placing these execution artefacts in the plan would confuse the auditors about which document is a forward-looking commitment and which records what actually happened.
-
3 Question 3 Single choice Module 3 - Test Case and Execution
A banking application's reporting module has a defect in which monthly statements show the wrong closing balance only when the account has a transaction dated on the last day of a month. The team lead must decide which field of the defect report should carry the assessment of the impact on customers and the business, and which should carry how urgently the fix must be scheduled. The CAB wants these two judgments recorded separately so that a cosmetic misspelling is not scheduled ahead of this issue. Which pairing correctly describes the two judgments?
Correct Answer: AExplanationSeverity measures the technical impact of the defect on the system and its users, while priority sets the scheduling order of the fix relative to other work. Here the wrong closing balance is high severity, but the team may still set priority by business need and release timing, which is why the two are recorded separately. The option reversing the definitions swaps the two concepts, and the other two options assign unrelated attributes such as reproducibility, root cause or release milestone to these fields.
-
4 Question 4 Single choice Module 4 - Test Review
A team is preparing a requirements specification for a logistics platform that will be used by a regulator. The project manager wants the review to be as rigorous as possible, with a planned meeting, a moderator, a defined procedure, and recorded defect logging, because the regulator will audit the review evidence. The team has a tight schedule and must choose a review type. Which review type best satisfies these requirements?
Correct Answer: CExplanationA formal review is the review type with a defined procedure, a planned meeting led by a moderator, and documented findings, which is what the regulator's audit demands. Informal reviews are lightweight and lack the recorded procedure, and peer reviews are usually unstructured and not a moderated meeting. A technical review can be formal, but the option restricting it to architecture diagrams with no moderator omits the required rigour and the scope of a requirements document.
-
5 Question 5 Drag and drop Module 5 - Types of Testing
A retail company is planning its test strategy for a new e-commerce platform. The team must confirm that the system can handle 5,000 concurrent shoppers during a flash sale, that the payment page meets accessibility standards, and that testers without access to source code can verify the checkout business rules. Match each requirement to the testing type that best addresses it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Confirm the system handles 5,000 concurrent shoppers during a flash saleVerify the payment page meets accessibility standardsVerify checkout business rules without access to source codeUsability and accessibility testingUnit testingPerformance testingBlack box testingWhite box testingCorrect Answer:- Confirm the system handles 5,000 concurrent shoppers during a flash sale → Performance testing
- Verify the payment page meets accessibility standards → Usability and accessibility testing
- Verify checkout business rules without access to source code → Black box testing
ExplanationLoad and performance testing measures behaviour under concurrent demand, which is the correct match for the flash-sale requirement. Accessibility is a non-functional quality checked through usability and accessibility testing. Verifying business rules without source access is black box testing by definition. White box testing requires code visibility, which the testers lack, and unit testing operates at the code level and cannot confirm end-to-end checkout rules from the outside.
-
6 Question 6 Single choice Module 5 - Types of Testing
A government benefits portal must be verified before go-live. The security team has supplied the testers with the login and session design documents and read access to the authentication code, but the testers must also check the portal exactly as an external user would see it. The test lead wants the team to combine insight from the internal design with outside-in verification of user-visible behaviour. Which method should the test lead select?
Correct Answer: DExplanationGrey box testing sits between the two extremes: testers use partial knowledge of design and internals to target their tests while still checking behaviour as an external user sees it. This matches the access the team has and the outside-in verification the lead wants. Pure black box testing would discard the design documents the team already has, pure white box testing would focus on code paths rather than user-visible behaviour, and unit testing addresses one component at a lower level than the portal-wide check required.
-
7 Question 7 Dropdown Module 2 - Test Plan
A software team is documenting its test metrics for the monthly quality report, which must show how many planned test cases were executed and what share of executed tests found defects. The team wants to record the figures in the standard test metrics definitions used in its Test Summary Report. Complete the metric definitions by selecting the correct value for each blank.
Choose the correct value for each blank.
Test execution coverage = ( test cases executed / total planned test cases) x 100; Defect detection percentage = ( defects found / total test cases executed) x 100Correct Answer:Test execution coverage = (number of test cases executed test cases executed / total planned test cases) x 100; Defect detection percentage = (number of test cases that found defects defects found / total test cases executed) x 100
ExplanationTest execution coverage measures how much of the planned test set was actually run, so the numerator is the number of test cases executed. The defect detection percentage asks what share of the executed tests exposed a defect, so the numerator must count only the test cases that found defects over the total executed. Using defect counts or requirement counts in these positions, or the planned total in the denominator of the second metric, would mix up the metric definitions the Test Summary Report relies on.
-
8 Question 8 Single choice Module 1 - Overview of Testing
A product company is moving a mature legacy billing system from a waterfall-style release cycle to Scrum with two-week sprints. The QA manager must decide how the testing responsibilities should be structured for the new cadence, since the current model has a separate QA group testing only at the end of each release. The developers are willing to take on test automation, and the company wants to keep an independent test perspective for compliance. Which structure best meets these constraints?
Correct Answer: DExplanationIn Scrum, testing is a shared team activity carried out within the sprint rather than deferred to a single end-of-release phase, and the team delivers a working build each sprint. Keeping an independent tester perspective for compliance-critical stories satisfies the company's governance need without blocking the sprint cadence. Disbanding QA removes the independence the compliance constraint requires, keeping end-of-release testing contradicts the sprint model, and quarterly outsourcing is too far from the sprint build cycle to give timely feedback.
-
9 Question 9 Single choice Module 3 - Test Case and Execution
A team is writing test cases for a password-reset feature. The requirement states that after three failed reset attempts within 15 minutes, the account must be locked for 30 minutes and the user must be notified by email. A junior tester has written a case that only checks the lock message appears after the third failure. The test lead wants test cases that would fail if the behaviour were wrong and that trace back to the requirement. Which revision best meets this need?
Correct Answer: CExplanationEffective test cases state preconditions, specific steps and expected results that can actually detect a wrong implementation, and they must trace to the requirement. The rewrite checks the threshold, the lock duration, the notification and the time window, so each condition of the requirement is verified. Keeping the single message check leaves the expiry and notification unverified, a performance test does not test the lock rules, and a traceability matrix links cases to requirements rather than replacing the cases themselves.
-
10 Question 10 Single choice Module 5 - Types of Testing
A healthcare provider is deciding how to automate regression testing for its patient-scheduling web application, which changes every two weeks. The application's screens are stable, but the business rules for appointment slots change frequently and must be re-verified each release. The budget is limited, so the team wants automation with the highest return and lowest maintenance. Which automation decision is most appropriate?
Correct Answer: BExplanationAutomation delivers the best return on repetitive, stable checks that run on every release, such as the appointment-slot business rules that must be re-verified each cycle. Exploratory and usability work depends on human judgment and is poorly suited to scripted automation. Automating exploratory testing ignores the fact that automation checks only what it is programmed to check, while avoiding automation entirely forgoes savings on the repeated regression checks. Automating the one-off review wastes the budget because it is run least often.
-
11 Question 11 Single choice Module 1 - Overview of Testing
A testing consultant is advising a company on a candidate's professional conduct. During an assignment, the consultant discovers that a client's security test report was altered by a manager to hide a serious vulnerability before it was passed to regulators. The consultant has the evidence and must decide what to do first. Which action is most consistent with the ethical responsibilities of a testing professional?
Correct Answer: BExplanationA testing professional's code of ethics requires honesty and the duty to act in the public interest, which here means documenting the evidence and raising it through proper channels first, escalating to the regulator if needed. Quietly modifying production code bypasses accountability and does not address the falsified report. Public posting breaches confidentiality and can cause harm without due process, and deferring the matter allows the misrepresentation to reach regulators unchallenged.
-
12 Question 12 Dropdown Module 2 - Test Plan
A test lead is writing the Test Summary Report for a three-month project. The report must summarise the outcome of test execution against the plan so that the sponsor can decide on release. The lead wants to present the defect outcome in the standard terms used for test reporting. Complete the sentence by selecting the correct value for each blank.
Choose the correct value for each blank.
The Test Summary Report records the of the testing activities against the Test Plan, and the defects found are summarised by their and status to support the release decision.Correct Answer:The Test Summary Report records the outcome and results of the testing activities against the Test Plan, and the defects found are summarised by their severity and status to support the release decision.
ExplanationThe Test Summary Report summarises the outcome and results of testing against the plan, giving the sponsor the evidence needed for the release decision. Defects in that summary are grouped by severity and status so that the impact on release readiness is visible. Planning schedules belong in the Test Plan rather than the summary, requirements lists and build history are inputs rather than the outcome summary, and cost or author are not the attributes used to characterise defect impact in this report.
These are 12 of the 25 questions in the full CTIL-001 pack.
Get All 25 QuestionsGet all 25 questions & answers
Full access options for GAQM CTIL-001
Self-study
PDF Version
- 25 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 25 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 25 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee