Exam Information
Free practice questions with explanations
GAQM PPM-001 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 15
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Module 3 œ Intermediate Project Management
A regional logistics firm is building a warehouse management system over nine months. The sponsor insists the schedule be compressed by two months without reducing scope. The project has a fixed go-live date tied to a contractual penalty clause, and the team has already been running at full capacity with no float left on the critical path. Budget is locked, so adding headcount is not permitted. Which schedule compression technique should the project manager apply first?
Correct Answer: CExplanationFast-tracking overlaps phases that are normally sequential, and it shortens the schedule without adding cost, which fits the locked budget and the rule that scope must not shrink. Crashing would require added resources, and the stem explicitly rules out extra headcount and budget growth. Deferring the reporting module breaks the no-scope-reduction condition. Adding contingency reserve does not compress the schedule at all; it only protects a date that is already set. Fast-tracking does add rework risk, which the manager should monitor, but it is the option that meets every stated constraint.
-
2 Question 2 Single choice Module 8 œ Risk Management
A software consultancy is assessing a risk that a key third-party API provider will change its authentication model during the project. Past incidents show the provider gives only ten days' notice of changes. The impact on the delivery date would be severe, but the probability is low. The company wants to respond to this threat in a way that keeps the project's budget unchanged while still preparing for the event if it happens. Which response best meets these conditions?
Correct Answer: AExplanationBecause the probability is low and the budget must stay unchanged, accepting the risk while preparing a reaction plan is the defensible response. A pre-approved workaround that fits inside the ten-day notice window makes the reaction practical. Transferring through a contract clause is unlikely to be free and may not be negotiable with the provider. Replacing the API is an avoidance strategy that adds cost and effort well beyond a low-probability threat. A premium support contract adds spend, which violates the budget constraint, so it is not a free mitigation.
-
3 Question 3 Single choice Module 9 œ Crisis Management
A regional bank operates an emergency operations center that coordinates responses to branch network outages. During a simulated ransomware attack, the EOC lead discovers that the incident log, the communications tree and the recovery task list are maintained in three separate spreadsheets updated by different teams. Executives are receiving conflicting status updates. The bank's continuity policy requires that all incident status be visible to every EOC role within 15 minutes and that the solution cannot depend on the affected corporate network. What should the bank implement FIRST?
Correct Answer: BExplanationThe requirement is a single, consistent source of incident status that stays available if the corporate network is compromised, so an out-of-band board with defined ownership solves both the conflicting-updates problem and the independence constraint. A shared network drive depends on the corporate network that the policy explicitly excludes, and hourly mirroring cannot meet the 15-minute visibility target. Hourly calls are too slow and rely on verbal relay, which keeps the conflict problem alive. Email alerts from the ticketing system depend on the same corporate infrastructure and do not fix the fragmented record ownership.
-
4 Question 4 Multiple choice Module 4 œ Effective Planning & Scheduling
A construction project manager is developing the Work Breakdown Structure for a hospital wing expansion. The team has listed deliverables by trade, but the sponsor is concerned that some work packages are either too large to estimate reliably or overlap with other packages. The manager must refine the WBS so that each work package can be estimated, assigned and monitored. Which TWO actions are most appropriate? (Choose two.)
Correct Answer: B, EExplanationDecomposition to estimable, deliverable-oriented packages addresses the sponsor's concern directly, and assigning each package to a single control account removes ownership overlap. A WBS organised by schedule sequence mixes the deliverable hierarchy with dependencies, which belongs in the schedule network instead. Risk responses are not deliverables and should not sit in the WBS as a branch. Placing overhead as top-level work packages distorts the deliverable hierarchy and confuses estimation of the technical scope.
-
5 Question 5 Order list Module 1 œ Project Management Fundamentals
A new project manager has been asked to take over a stalled internal project to replace an aging customer billing platform. The sponsor wants a clear, approved baseline before any work continues. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Complete the project planning worksheets and obtain formal approval of the baseline
- Hold a vision workshop to articulate the desired end state of the billing platform
- Set measurable project goals that align with the sponsor's stated business objectives
- Draft the statement of work and confirm scope boundaries with the sponsor
Correct Answer:- Draft the statement of work and confirm scope boundaries with the sponsor
- Set measurable project goals that align with the sponsor's stated business objectives
- Complete the project planning worksheets and obtain formal approval of the baseline
- Hold a vision workshop to articulate the desired end state of the billing platform
ExplanationA vision is established first so that goals have a reference point. Goals are then derived from it, the statement of work formalises scope against those goals, and the planning worksheets build the baseline that receives formal approval. Writing the statement of work before the goals would define scope without a stated target to measure it against. Approving the baseline before the worksheets are complete would approve an unfinished plan.
-
6 Question 6 Single choice Module 6 œ Team Building
A product team of eight engineers from three countries has been working together for two months. The project manager notices that during design reviews, the same two senior engineers dominate discussion while others rarely contribute, and decisions are being made informally before meetings. The manager wants to shift the team toward shared leadership and fuller participation without disrupting the delivery schedule. Which intervention is most appropriate?
Correct Answer: BExplanationRotating facilitation and using round-robin turns give quieter members a structured route into the discussion, which builds shared leadership while keeping the review cadence intact. Reassigning the senior engineers penalises expertise and disrupts delivery. Letting the project manager decide every question concentrates leadership rather than sharing it. Asynchronous comments may help some members but remove live debate and do not address the informal pre-meeting decision-making the manager observed.
-
7 Question 7 Drag and drop Module 2 œ Project Management Training
A mid-sized engineering firm is preparing a project plan for a new fleet telematics rollout. The sponsor has asked that each planning element be documented so the team can estimate and control the work. Match each planning element to the purpose it serves in the plan.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Recording the estimated cost of each work package over timeListing all deliverables in hierarchical decompositionDocumenting threats and their planned responsesDescribing the formal close-out criteria and handover stepsSpecifies how the project is formally ended and acceptedPrepares the team for uncertain events that could affect objectivesDefines the complete scope of work the project must produceSets the order in which the sponsor will approve change requestsLists the individual team members' performance review schedulesEstablishes the spending baseline against which costs are controlledCorrect Answer:- Listing all deliverables in hierarchical decomposition → Defines the complete scope of work the project must produce
- Recording the estimated cost of each work package over time → Establishes the spending baseline against which costs are controlled
- Documenting threats and their planned responses → Prepares the team for uncertain events that could affect objectives
- Describing the formal close-out criteria and handover steps → Specifies how the project is formally ended and accepted
ExplanationThe work breakdown structure defines the scope of deliverables, and cost estimates by time phase form the budget baseline that cost control measures against. The risk register captures threats with their responses, and the closing section documents acceptance and handover criteria. The two distractors describe governance and HR activities that are not planning elements of the scope, cost, risk or closure categories the plan is built around.
-
8 Question 8 Dropdown Module 5 œ Advanced Project Management
A project manager is preparing the communication plan for a three-year ERP implementation. The executive sponsor requires only summarised status each month, while the delivery team needs detailed daily updates. Complete the communication plan entry by selecting the correct value for each blank.
Choose the correct value for each blank.
Audience: Executive sponsor. Channel: . Frequency: . Content: status summary with top three risks.Correct Answer:Audience: Executive sponsor. Channel: monthly steering report. Frequency: Monthly. Content: Milestone-level status summary with top three risks.
ExplanationExecutives are served by a monthly steering report pitched at milestone level, which matches the requirement for summarised status and a risk view. Daily stand-up notes and task trackers are detailed artefacts meant for the delivery team, and a raw defect export is far too granular for a sponsor. Weekly or ad hoc frequency would exceed the monthly summary cadence the sponsor asked for, and task-level or timesheet-level content would bury the sponsor in detail.
-
9 Question 9 Single choice Module 12 œ Self-Leadership
A senior IT project manager has been leading three concurrent projects for a financial services client. Over the past quarter, her commitments have crept upward, and she is finding it hard to keep her energy consistent across all three. Her manager wants her to sustain performance without burning out, and she has limited ability to delegate because two of the projects lack trained deputies. She wants a self-leadership approach that addresses her own motivation and change readiness. What should she do FIRST?
Correct Answer: BExplanationSelf-leadership begins with knowing who you are and what drives your performance, so a self-assessment of strengths, energy and readiness for change should come before any structural decision. Reducing the portfolio is a management decision that may not be available and skips self-knowledge. Training deputies is a worthwhile longer-term action but does not address her own motivation. A rigid schedule imposed without understanding her energy patterns risks the same burnout it is meant to prevent.
-
10 Question 10 Single choice Module 7 œ Building Better Teams
A newly formed cross-functional team of data analysts, business analysts and developers is delivering a reporting platform. After six weeks, the team is struggling: members hesitate to share incomplete work and defer to the lead developer on every question. The project manager wants to build team trust and establish norms the team will follow. Which action is the most appropriate first step?
Correct Answer: BExplanationNorms the team creates together are more likely to be followed, and co-creating them builds the trust the team currently lacks while addressing the reluctance to share incomplete work. A manager-authored code signed without discussion imposes norms rather than building ownership. External mentors do not address the team-level dynamic. Removing the lead developer is punitive and avoids the underlying trust problem rather than solving it.
-
11 Question 11 Multiple choice Module 13 œ Communication Strategies
A project manager is coaching a senior engineer who consistently responds to stakeholder challenges with sharp, defensive remarks that escalate meetings. The engineer is technically excellent and wants to improve how he handles disagreement without losing his directness. Which TWO techniques would most directly help him communicate assertively while keeping relationships positive? (Choose two.)
Correct Answer: D, EExplanationRestating the other person's point shows active listening and lowers defensiveness, and I-statements express his view assertively without accusing the stakeholder. Refusing to engage and using rhetorical questions are passive-aggressive or dismissive, which damages relationships. Raising volume and speed is aggressive and makes the meeting more confrontational rather than more persuasive.
-
12 Question 12 Single choice Module 14 œ Knowledge Management
A consulting firm has lost several senior architects over the past year, and their hard-won delivery methods have left with them. The firm wants to capture the tacit knowledge these experts hold about client integration patterns. The knowledge management initiative must not rely on the architects spending large amounts of billable time documenting, and it must preserve context rather than producing generic checklists. Which approach best meets these constraints?
Correct Answer: BExplanationTacit knowledge is best elicited through stories and reviews, which preserve context, and facilitated sessions keep the time commitment small. Codifying recurring lessons into a pattern library converts that knowledge into explicit, reusable form. A full manual demands heavy billable time and tends to strip context. Migrating uncurated files stores explicit documents without capturing tacit insight. Generic checklists from published standards lose the firm-specific context the initiative is meant to preserve.
-
13 Question 13 Single choice Module 11 œ Leadership Skills
A project manager is leading a 40-person delivery programme. A senior developer who was highly committed during the design phase has become disengaged during build, missing stand-ups and producing lower-quality code. The developer is not in a performance management process. The project manager wants to re-engage the developer using an approach consistent with the commitment curve and employee development models. What should she do FIRST?
Correct Answer: AExplanationCommitment and development models point to understanding the cause of disengagement first, such as lost challenge or unclear purpose, before intervening. A private conversation with a development plan fits that sequence. Reassigning the developer treats the symptom and may signal demotion. Formal escalation is premature because no performance process exists and the cause is unknown. Closer monitoring increases pressure without addressing motivation.
-
14 Question 14 Drag and drop Module 8 œ Risk Management
A transport authority is running a large signalling upgrade and has built a risk register with several categories of risk exposure. The risk manager must align each risk response with the response strategy it represents. Match each risk response to the risk strategy it exemplifies.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Adding a second qualified vendor to remove dependence on a single supplierPurchasing an insurance policy covering delay damages on the signalling contractDropping the proposed live-cutover feature that carries unacceptable safety exposureSetting aside a funded reserve for schedule slippage on integration testingAvoidAccept with contingencyMitigateExploitEscalateTransferCorrect Answer:- Purchasing an insurance policy covering delay damages on the signalling contract → Transfer
- Adding a second qualified vendor to remove dependence on a single supplier → Mitigate
- Dropping the proposed live-cutover feature that carries unacceptable safety exposure → Avoid
- Setting aside a funded reserve for schedule slippage on integration testing → Accept with contingency
ExplanationInsurance shifts financial exposure to a third party, which is transfer. Adding a second vendor reduces the probability or impact of a supplier failure, which is mitigation. Removing the unacceptable feature eliminates the exposure entirely, which is avoidance. A funded reserve for known slippage is acceptance backed by contingency. Escalate and exploit are not the strategies these responses represent; exploit applies to positive risks and escalation is a governance route rather than a response strategy.
-
15 Question 15 Order list Module 9 œ Crisis Management
A hospital network has experienced a sudden loss of its patient records system after a data centre power failure. The crisis team must move from the initial event to recovery in a controlled way and must confirm the situation before committing resources. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Perform a risk level analysis to determine which clinical services are affected and how urgently
- Execute business continuity recovery procedures and monitor progress until services are restored
- Activate the emergency operations center and confirm the incident commander and role assignments
- Consult the facilities and clinical informatics experts to verify the root cause before choosing a response
- Develop and approve a response process covering patient care workarounds and communication to staff
Correct Answer:- Activate the emergency operations center and confirm the incident commander and role assignments
- Perform a risk level analysis to determine which clinical services are affected and how urgently
- Consult the facilities and clinical informatics experts to verify the root cause before choosing a response
- Develop and approve a response process covering patient care workarounds and communication to staff
- Execute business continuity recovery procedures and monitor progress until services are restored
ExplanationThe EOC must be activated and roles assigned before any analysis can be coordinated. Risk level analysis then establishes which services are most urgent, and expert consultation confirms the cause before a response is chosen. An approved response process is developed on that basis, and recovery procedures are executed last. Performing recovery before the cause is confirmed risks repeating the failure, and developing the response before analysis would prioritise the wrong services.
These are 15 of the 650 questions in the full PPM-001 pack.
Get All 650 QuestionsGet all 650 questions & answers
Full access options for GAQM PPM-001
Self-study
PDF Version
- 650 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 650 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 650 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PPM-001 Exam (Professional in Project Management (PPM) - Standard Package) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.