APM APM-PFQ Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understand communication in the context of a project.
A project manager at a regional engineering firm is coordinating a design change that affects four departments across two sites. The change is time-sensitive, and the team has previously lost decisions in long email chains where people replied to different subsets of recipients. The project manager needs a method that gives an immediate, two-way exchange so questions can be resolved on the spot, but the outcome must also be recorded for people who could not attend. The firm has a strict policy that decisions must be traceable. Which communication approach best meets these needs?
Correct Answer: BExplanationA live video conference gives rich, two-way exchange so ambiguities are resolved immediately, which fits the time pressure. Recording it and circulating a written decision summary satisfies the traceability policy and reaches people who could not attend. A written notice is one-way and slow, a collated email reintroduces the fragmented replies that caused the earlier problem, and individual calls with memory-based updates produce no auditable record.
-
2 Question 2 Single choice Understand leadership and teamwork within a project
A newly appointed project manager inherits a team of eight analysts. Two members have been working in the same group for years and consistently defer to each other, while the remaining members rarely contribute in meetings. Performance reviews show the team has not yet agreed on how work is prioritised. The project manager wants to use a recognised team development model to diagnose where the group currently stands before choosing interventions. Which action should the project manager take FIRST?
Correct Answer: DExplanationThe brief asks for a diagnosis using a team development model before intervening, so assessing the team's current stage (forming, storming, norming, performing) is the correct first step. Individual objectives, replacing members, and incentives are all interventions chosen without diagnosis, and each may fail to address the actual stage the team is in.
-
3 Question 3 Single choice Understand project life cycles
A government department is delivering a new citizen portal. Requirements are only partially understood, and the department expects user feedback to reshape the product substantially during delivery. Funding is released in tranches, and the sponsor wants a usable increment visible to users within the first quarter. The project manager must select a life cycle approach. Which life cycle best fits these constraints?
Correct Answer: BExplanationIncomplete requirements and expected feedback-driven change point to an iterative life cycle, and repeated increments give the sponsor a usable release in the first quarter that aligns with tranche funding. A linear approach with frozen requirements conflicts with the expected change, and deferring the first increment until sign-off defeats the visibility the sponsor asked for.
-
4 Question 4 Single choice Understand project management and the operating environment
A mid-sized logistics company runs a routine monthly invoicing process that is repeated without change every period. Separately, it is planning a one-off replacement of its warehouse management system, with a fixed start and end date, a unique scope, and a budget approved by the board. A newly hired coordinator is asked to explain to her team why the warehouse replacement should be managed as a project rather than as routine operations. Which statement is the most accurate explanation?
Correct Answer: BExplanationA project is defined by a temporary endeavour that creates a unique product, service or result, with a defined start and end, while business as usual is ongoing and repetitive. The warehouse replacement meets the temporary and unique criteria, whereas invoicing is recurring operations. Cost size does not define a project, governance by budget does not turn routine work into a project, and having a team is not a distinguishing feature.
-
5 Question 5 Single choice Understand project management planning
A project manager is preparing a business case for a software upgrade that will cut manual processing across three regional offices. The sponsor asks the project manager to draft the sections that justify the investment. The sponsor also needs to know which parts of the business case the sponsor owns and which the project manager prepares. The board requires that the case show the expected benefits, the options considered, and the cost-benefit position. Which allocation of responsibilities is most appropriate?
Correct Answer: BExplanationThe sponsor is accountable for the business case, including the justification of benefits, while the project manager supplies delivery-related inputs such as the approach, cost and timeline estimates. Making the project manager fully responsible ignores the sponsor's accountability for benefits, delegating to finance removes the project perspective, and giving the project manager ownership of benefits conflicts with the sponsor's role.
-
6 Question 6 Single choice Understand project risk and issue management in the context of a project.
During a construction project, the team identifies that a key supplier might fail to deliver steel in time, a risk that could delay the structural phase. The project manager logs it in the risk register, but three weeks later the supplier has already missed a delivery date and the delay is now certain. The team is debating whether to keep this item in the risk register or move it elsewhere. Which action is correct?
Correct Answer: DExplanationOnce a risk has occurred it becomes an issue, which is managed through the issue log with the goal of resolving it, rather than remaining in the risk register as a probability-based item. Keeping it unchanged misrepresents its status, deleting it loses traceability, and a delay does not automatically constitute a scope change requiring a change request.
-
7 Question 7 Single choice Understand project scope management.
A consultancy is delivering a fit-out of a new office. The project manager has a product breakdown structure listing the required physical products, and a work breakdown structure listing the activities needed to produce them. Late in the project, the client asks for a new meeting room to be added. The team agrees to add it, but two days later the joinery subcontractor starts work on the existing design, and the finance team discovers the baseline cost has changed without approval. Which control mechanism should have prevented this outcome?
Correct Answer: AExplanationChange control governs how proposed changes to the baseline are assessed, approved, and only then implemented, which is exactly what was skipped here. Configuration management tracks the status and identity of products rather than approving changes, the organisational breakdown structure shows the reporting hierarchy rather than approval authority, and the responsibility assignment matrix maps tasks to people without controlling changes.
-
8 Question 8 Single choice Understand quality in the context of a project.
A medical device firm is preparing a prototype for regulatory submission. The quality team has defined the acceptance criteria, scheduled testing points within the build plan, and assigned staff to inspect prototypes before they move to the next stage. A senior manager asks the project manager to explain which part of the quality system is responsible for checking that the planned processes are being followed correctly across the project, rather than just inspecting the prototype outputs. Which element should the project manager identify?
Correct Answer: CExplanationQuality assurance focuses on whether the processes used on the project are being followed and are fit for purpose, which is the concern raised here. Quality planning sets criteria in advance, quality control inspects the outputs themselves, and reporting summarises results without verifying the processes.
-
9 Question 9 Single choice Understand resource, scheduling and optimisation in a project.
A project to launch a retail app has a critical path of design, build, and test activities, with a fixed launch date tied to a seasonal marketing campaign. Two developers are shared with another project and are not available until week five. The schedule shows the build activity is the critical path, and total float on the test activity is two days. The project manager wants to shorten the schedule without changing the launch date. Which option is most likely to help while respecting the shared developer constraint?
Correct Answer: AExplanationFast-tracking overlaps sequential activities that are not strictly dependent, shortening the critical path without requiring resources that are unavailable. Lengthening non-critical work does not reduce duration, starting the build in week one ignores that the developers are unavailable until week five, and removing a milestone does not change the critical path or the scheduled launch.
-
10 Question 10 Single choice Understand the roles and responsibilities within projects
A public sector organisation has launched a digital services project with a steering group, a sponsor, a project manager, and a team of developers. The end users are local council staff who will rely on the new system daily. During user acceptance testing, a council team lead asks the project manager to approve a change that would add new reporting features. The project manager is uncertain whether to agree. Which action is most appropriate for the project manager to take?
Correct Answer: AExplanationScope and funding changes are decided through governance, so the sponsor and steering group should consider the request through change control rather than the project manager acting alone. Approving it unilaterally exceeds the project manager's authority, asking developers to implement it bypasses governance, and rejecting it without review ignores the end user's legitimate input and the change process.
-
11 Question 11 Multiple choice Understand communication in the context of a project.
A project manager is drafting the communication plan for a healthcare IT rollout that affects clinical staff, suppliers, and the regulator. Which TWO items should be included in the communication plan? (Choose two.)
Correct Answer: C, DExplanationA communication plan records who needs information, why, how often, through which channel, and who is responsible, which covers the audiences and the frequency and channel items. Opinions about stakeholder competence have no place in a plan, while financial ledgers and full design documents belong in other project records rather than the communication plan.
-
12 Question 12 Order list Understand project risk and issue management in the context of a project.
A project manager is handling a new risk in a software migration project. Place the following stages of a typical risk management procedure into the correct order, from first to last. Choose the correct sequence. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Monitor and review the risk responses and the risk register.
- Plan and implement responses to the prioritised risks.
- Identify potential risks and record them in the risk register.
- Assess each risk for likelihood and impact to prioritise them.
Correct Answer:- Identify potential risks and record them in the risk register.
- Assess each risk for likelihood and impact to prioritise them.
- Plan and implement responses to the prioritised risks.
- Monitor and review the risk responses and the risk register.
ExplanationA typical procedure starts by identifying risks and recording them, then assessing them for likelihood and impact, then planning and implementing responses, and finally monitoring and reviewing. Assessing before identifying is impossible, and monitoring cannot precede responses, so the other sequences break logical dependencies.
-
13 Question 13 Single choice Understand leadership and teamwork within a project
A project manager wants to match each team development or leadership action to the most suitable purpose. Match each numbered item to the purpose it best serves.
1. A regular one-to-one review with each team member
2. Using a shared team charter that the team writes together
3. Explicitly recognising the efforts of a team member after a difficult milestone
Targets: (i) building trust and shared ground rules; (ii) reinforcing motivation and performance; (iii) tracking individual progress and development needs.
Which mapping is correct?Correct Answer: BExplanationRegular one-to-one reviews track individual progress and development, a jointly written team charter builds trust and agreed ground rules, and explicit recognition reinforces motivation and performance. The other mappings assign a team charter to motivation or recognition to ground rules, which does not match what each action is designed to achieve.
-
14 Question 14 Dropdown Understand project management planning
Choose the correct value for each blank.
Choose the correct value for each blank.
A project manager is reviewing the monitoring approach for a deployment that must stay within an agreed baseline. The planned cost of the deployment is recorded as the baseline, and the project manager compares actual spend with it each reporting period to see whether the project is on track. Complete the statement: The represents the agreed plan against which progress and results are measured, and the monitoring of actual performance against that plan is called .
Choose the correct values for and .Correct Answer:A project manager is reviewing the monitoring approach for a deployment that must stay within an agreed baseline. The planned cost of the deployment is recorded as the baseline, and the project manager compares actual spend with it each reporting period to see whether the project is on track. Complete the statement: The deployment baseline represents the agreed plan against which progress and results are measured, and the monitoring of actual performance against that plan is called progress monitoring.
Choose the correct values for deployment baseline and progress monitoring.ExplanationThe deployment baseline is the agreed plan used as the reference point for measuring progress, and comparing actual spend and progress against it is progress monitoring. The business case justifies investment rather than serving as the measurement reference, stakeholder analysis identifies and engages stakeholders, and the responsibility assignment matrix and configuration management serve different purposes.
These are 14 of the 409 questions in the full APM-PFQ pack.
Get All 409 QuestionsGet all 409 questions & answers
Full access options for APM APM-PFQ
Self-study
PDF Version
- 409 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 409 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 409 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the APM-PFQ Exam (APM Project Fundamentals Qualification) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.