Exam Information
Free practice questions with explanations
APM APM-PMQ Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 15
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice People and behaviours
A programme director is leading a regional infrastructure upgrade involving three contractor firms, a council planning department and two internal operations teams. A senior contractor repeatedly bypasses the agreed weekly coordination meeting and issues direct instructions to junior engineers, causing rework and friction. The director has already raised the issue informally twice. The contract includes a stakeholder engagement schedule and an escalation clause. What is the MOST appropriate NEXT action?
Correct Answer: BExplanationThe stated engagement schedule and escalation route make a documented, formal conversation with the contractor's account manager the proportionate next step after two informal attempts. Reassigning work or terminating ignores the contract's escalation path and would be disproportionate before the issue is formally raised. Copying the sponsor on communications treats the symptom without resolving the behaviour, and it may breach the protocol the team has already agreed to follow.
-
2 Question 2 Single choice Planning and managing deployment
A project to deploy a new customer billing system must be delivered before a fixed regulatory date. The critical path runs through a data migration activity that has a 40 percent chance of overrunning by up to three weeks, based on historical data from similar migrations. Management wants to protect the regulatory date while keeping contingency spend within the approved budget of 250,000 pounds. The team has already allocated the full schedule reserve to other risks. Which response is MOST cost-effective?
Correct Answer: BExplanationFast-tracking by overlapping activities shortens the critical path without new spend, which is what the budget constraint and exhausted schedule reserve demand, while the accepted rework risk should be logged and monitored. Doubling contingency would break the approved budget limit set by management. Deferring migration would leave the regulatory requirement unmet, and renegotiating a regulatory date is outside the project's control and was not offered as an option the team could rely on.
-
3 Question 3 Single choice Preparing for change
A government agency is procuring a managed service for its case management platform. The procurement team proposes awarding the contract on the lowest tender price. The business case emphasises service continuity during a live caseload migration, and the agency has previously suffered a provider failure that delayed casework by months. Evaluation criteria have not yet been published to bidders. What is the MOST appropriate action before the tender is issued?
Correct Answer: BExplanationWeighted criteria that reflect transition capability and continuity must be fixed and published before bidders respond, otherwise the evaluation is open to challenge and the stated business priority is not reflected in the award. Lowest-price award ignores the documented failure history. Awarding to the incumbent without competition may breach procurement rules, and deciding criteria after seeing proposals is non-transparent and unfair to bidders.
-
4 Question 4 Single choice Setting up for success
A transformation programme has been running for eighteen months across six business units. Benefits have not been tracked consistently, each unit reports to a different executive, and the steering group meets quarterly with no decision rights over funding. The sponsor wants governance that can authorise stage gates and reallocate funds between units. Which arrangement BEST meets this need?
Correct Answer: BExplanationThe governance gap is decision rights, so a programme board with delegated authority over stage gates and funding, backed by one benefits register, addresses both the reporting inconsistency and the inability to reallocate money. Monthly meetings without authority leave the decision problem unsolved. Per-unit analysts keep fragmented ownership, and invoice-level finance approval is operational control rather than programme governance.
-
5 Question 5 Multiple choice Preparing for change
A transition team is preparing to hand over a new logistics platform from the project to the operational service. Several items remain outstanding and the handover is scheduled in three weeks. Which TWO actions are MOST important to take before the operational service accepts ownership? (Choose two.)
Correct Answer: A, EExplanationOperational readiness depends on trained support staff who have exercised runbooks, and on agreed acceptance criteria with documented defects and workarounds, so the service owner knows what it is inheriting. Closing the cost centre early risks unallocated residual spend, removing production access before handover can stall the transfer, and publishing benefits forecasts is communication rather than a transition prerequisite.
-
6 Question 6 Single choice Planning and managing deployment
A software delivery team uses a backlog of 120 requirements for a claims portal. Stakeholders have changed priorities three times in the last month, and the sprint review shows a growing number of rejected features. The product owner proposes freezing scope for the next release to stabilise delivery. The contract allows change requests only through a formal change control board that meets fortnightly. Which action BEST addresses the root cause while respecting the change control process?
Correct Answer: AExplanationThe root cause is unstable priorities with no shared basis for decisions, so agreed value scoring combined with mandatory change board submission gives a consistent, auditable way to re-prioritise and shows the schedule impact. Bypassing the board breaches the contractual change control route. Longer sprints delay feedback rather than fixing priorities, and adding developers to a constantly changing backlog does not address the decision-making problem.
-
7 Question 7 Dropdown Planning and managing deployment
Choose the correct value for each blank.
Choose the correct value for each blank.
A project controls analyst is setting up earned value reporting for a construction programme. The planned value for the period is 480,000 pounds, earned value is 420,000 pounds and actual cost is 510,000 pounds. The Cost Performance Index is calculated as , which indicates the programme is budget.Correct Answer:A project controls analyst is setting up earned value reporting for a construction programme. The planned value for the period is 480,000 pounds, earned value is 420,000 pounds and actual cost is 510,000 pounds. The Cost Performance Index is calculated as 0.82, which indicates the programme is over budget.
ExplanationCPI is earned value divided by actual cost, so 420,000 divided by 510,000 gives 0.82, and a value below 1 means each pound spent is buying less work than planned, which is over budget. Option B uses planned value instead of earned value and mislabels the position. Option C inverts the ratio. Option D gets the correct index but misreads the meaning, since a CPI below 1 signals overspend.
-
8 Question 8 Order list Planning and managing deployment
A project manager must respond to a significant risk that a key supplier may fail to deliver a specialist component on time, threatening a major milestone. Put the following response steps into the correct order. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Select and approve a response strategy with the sponsor.
- Implement the agreed response and update the schedule.
- Assess the probability and impact of the supplier failing to deliver.
- Monitor the risk triggers and review the effectiveness of the response.
- Identify the risk and record it in the risk register with an owner.
Correct Answer:- Identify the risk and record it in the risk register with an owner.
- Assess the probability and impact of the supplier failing to deliver.
- Select and approve a response strategy with the sponsor.
- Implement the agreed response and update the schedule.
- Monitor the risk triggers and review the effectiveness of the response.
ExplanationThe risk must first be identified and logged with an owner, then assessed for probability and impact, then a response is selected and approved, implemented with schedule updates, and finally monitored against triggers. Assessing before the risk is recorded skips the register step. Choosing a response before assessment is out of sequence, and implementing before the sponsor approves the response breaks the agreed governance route.
-
9 Question 9 Single choice People and behaviours
A new programme director inherits a project team whose members have worked under a directive style for three years. Engagement survey results show low psychological safety, with team members reluctant to raise risks in meetings. The director wants to change behaviour without disrupting delivery over the next quarter. Which leadership approach is MOST likely to achieve sustainable change?
Correct Answer: BExplanationPsychological safety grows when leaders visibly model the behaviour they want and respond well when concerns are raised, which sustains change without disrupting delivery. Anonymous forms alone leave the meeting culture unchanged and do not build trust. A code of conduct mandating reporting may increase fear, and replacing people based on survey responses is unethical and damages inclusion.
-
10 Question 10 Single choice Setting up for success
A programme office is aligning four governance artefacts with their primary purpose. Match each artefact to its primary purpose.
1. Business case
2. Benefits realisation plan
3. Project initiation document
4. Stage gate review report
Targets: a) Justify investment by showing options and expected value; b) Define how and when benefits will be measured and owned; c) Set out the agreed scope, approach and controls for delivery; d) Provide evidence for a decision to proceed to the next stage.Correct Answer: AExplanationThe business case justifies investment by comparing options and expected value, the benefits realisation plan defines measurement and ownership, the project initiation document sets scope, approach and controls, and the stage gate report supports the proceed decision. Option B swaps the business case and benefits plan. Option C mismatches the initiation document with benefits and the benefits plan with controls. Option D misplaces both the initiation document and the stage gate report.
-
11 Question 11 Single choice Preparing for change
A project has completed its build phase and an independent assurance review has identified that the quality plan does not define exit criteria for system testing. The testing lead argues that testing can start immediately because the build is stable. The go-live date is fixed and the next steering group is in ten days. What is the MOST appropriate action?
Correct Answer: BExplanationEntry and exit criteria should be agreed and documented before testing so that readiness can be judged objectively, and reporting the gap to the steering group keeps governance informed. Starting testing and defining exit criteria afterwards makes the criteria influenced by results. Removing the finding hides a genuine assurance issue, and a one-year deferral is disproportionate given the stated fixed date.
-
12 Question 12 Single choice Planning and managing deployment
A construction project has an approved monthly resource profile showing a peak demand for crane operators in weeks 14 to 17. The resource histogram reveals that the same operators are also scheduled for a second site in those weeks, creating an overallocation of 160 percent. The site manager needs a fix that does not extend the overall duration beyond the contractual 40-week completion date and keeps the total labour budget unchanged. Which action is MOST appropriate?
Correct Answer: AExplanationResource levelling that moves float-holding activities away from the constrained crane resource removes the overallocation without changing the 40-week finish or the labour budget. Hiring operators breaks the budget constraint and extending duration breaks the contractual date. Removing the second site's crane allocation simply moves the conflict and creates an unacknowledged delay to another milestone.
-
13 Question 13 Multiple choice People and behaviours
A cross-functional team of twelve people, including two contractors and a remote engineer in a different time zone, is delivering a regulatory reporting tool. Team members report that meetings are dominated by two senior staff and that the contractors feel excluded from decisions. The project manager wants to improve inclusion and reduce conflict. Which TWO actions are MOST effective? (Choose two.)
Correct Answer: B, EExplanationRotating facilitation and structured turn-taking brings in quieter members and the remote engineer, while a shared decision log that everyone can comment on before sign-off gives contractors a genuine route into decisions. Scheduling only for head office hours excludes the remote engineer, restricting contractors is exclusionary and unfair, and having senior staff summarise discussions keeps the power imbalance in place.
-
14 Question 14 Single choice Setting up for success
A public sector organisation is considering a long-term infrastructure asset with an expected operational life of 40 years. The sustainability target requires lifecycle carbon emissions to be reduced by 30 percent compared with the reference design, and the capital budget is constrained. The design team proposes a lower-capital option with higher maintenance emissions. Which approach to the business case BEST reflects sustainable decision-making?
Correct Answer: BExplanationA whole-life appraisal of both cost and carbon over the 40-year life shows whether the option meets the 30 percent target while staying within the budget logic, which is the sustainable and defensible business case. Restricting the target to construction misses the stated lifecycle emissions requirement. Separating carbon as a footnote and ignoring cost both fail to give decision makers a balanced comparison.
-
15 Question 15 Single choice Preparing for change
A programme has agreed to deliver benefits through a new customer portal, with a target to reduce call centre volumes by 25 percent within six months of go-live. Three months after go-live, call volumes have fallen by 8 percent, but the operations team reports that customers are now using a manual email workaround for complex cases. The benefits owner wants to declare the benefit on track because the portal is live. What is the MOST appropriate response?
Correct Answer: BExplanationThe benefit is at risk because customers have shifted to an unplanned workaround, so the programme needs to measure the displaced demand, check whether the transition design caused it, and give the board an honest forecast. Declaring the benefit on track ignores the workaround that will erode the target. Lowering the target to match current performance and closing activity early both abandon the benefits realisation responsibility.
These are 15 of the 40 questions in the full APM-PMQ pack.
Get All 40 QuestionsGet all 40 questions & answers
Full access options for APM APM-PMQ
Self-study
PDF Version
- 40 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 40 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 40 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the APM-PMQ Exam (APM Project Management Qualification Exam) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.