- 216 Actual Exam Questions
- Compatible with all Devices
- Printable Format
- No Download Limits
- 90 Days Free Updates
Get All Planning & Scheduling Professional (PSP) Exam Questions with Validated Answers
Vendor: | AACE International |
---|---|
Exam Code: | AACE-PSP |
Exam Name: | Planning & Scheduling Professional (PSP) Exam |
Exam Questions: | 216 |
Last Updated: | October 8, 2025 |
Related Certifications: | PSP Certification |
Exam Tags: | Professional Level Project plannersschedulers |
Looking for a hassle-free way to pass the AACE International Planning & Scheduling Professional (PSP) Exam? DumpsProvider provides the most reliable Dumps Questions and Answers, designed by AACE International certified experts to help you succeed in record time. Available in both PDF and Online Practice Test formats, our study materials cover every major exam topic, making it possible for you to pass potentially within just one day!
DumpsProvider is a leading provider of high-quality exam dumps, trusted by professionals worldwide. Our AACE International AACE-PSP exam questions give you the knowledge and confidence needed to succeed on the first attempt.
Train with our AACE International AACE-PSP exam practice tests, which simulate the actual exam environment. This real-test experience helps you get familiar with the format and timing of the exam, ensuring you're 100% prepared for exam day.
Your success is our commitment! That's why DumpsProvider offers a 100% money-back guarantee. If you don’t pass the AACE International AACE-PSP exam, we’ll refund your payment within 24 hours no questions asked.
Don’t waste time with unreliable exam prep resources. Get started with DumpsProvider’s AACE International AACE-PSP exam dumps today and achieve your certification effortlessly!
Which statement is true?
Compensability and Excusability:
Excusable delays are those beyond the contractor's control, while compensable delays are excusable delays for which the owner bears responsibility.
If a delay is compensable, it inherently qualifies as excusable.
PSP Study Guide Reference:
The relationship between excusability and compensability is clarified in delay analysis discussions.
Conclusion: The correct answer is D, as compensability implies excusability.
Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?
The use of a winter/wet weather seasonal calendar is essential in planning and scheduling to account for climatic conditions that can impact project timelines. The PSP Study Guide emphasizes identifying project variables, such as environmental conditions, and incorporating them into the project plan to manage risks and constraints effectively. Seasonal calendars help planners predict periods of reduced productivity, increased costs, and potential delays due to adverse weather conditions (PSP Study Guide, Subchapter 1.2.4, 'Project Variables').
These calendars are particularly useful for:
Forecasting potential schedule impacts during specific periods.
Enhancing the accuracy of risk management plans (PSP Study Guide, Section 1.3.13, 'Risk and Recovery Plan').
Aiding in decision-making regarding resource allocation during slow periods.
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
Late Finish (LF) Transition Rule:
Late finish (LF) is calculated by adding one day to the early finish (EF) of the final activity.
EF of Activity 11001 is given, and the late finish is simply EF+1EF + 1EF+1.
Cross-Verification with PSP Guidelines: PSP methodologies state that late finish is derived from the forward pass using early finish logic, with specific adjustments based on activity relationships (Ref: PSP Study Guide, Chapter 2A: Forward and Backward Pass Calculations).
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
Column Pour Requirements:
Each column pour requires 60 lifts per day.
Crane Capacity:
Each crane can perform 35 lifts per day.
Determine Minimum Cranes Required:
Minimum Cranes = Column Lifts Crane Capacity = 60 35 1.71 cranes.
Since partial cranes cannot be used, round up to 3 cranes.
Cross-Verification:
Option A (2 cranes): Incorrect. Insufficient lifts per day.
Option B (1 crane): Incorrect. Infeasible.
Option C (4 cranes): Incorrect. Exceeds requirement.
Option D (3 cranes): Correct. Satisfies lift requirements efficiently.
PSP Study Guide (2019), Sections on Equipment Productivity and Resource Allocation.
AACE Recommended Practices, RP 10S-90.
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.
The Estimate to Complete (ETC) quantifies the cost required to complete all remaining work.
Option A (Budget at Completion - BAC) is the total approved budget.
Option B (Budgeted Cost of Work Performed - BCWP) measures earned value.
Option D (Estimate at Completion - EAC) includes both actual costs to date and ETC.
ETC is used to forecast project completion costs as outlined in standard project management practices.
Security & Privacy
Satisfied Customers
Committed Service
Money Back Guranteed