2026 Actual AACE International AACE-PSP Dumps, Updated Exam Questions for Guaranteed Pass

Planning & Scheduling Professional (PSP) Exam - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorAACE International
Exam codeAACE-PSP
Exam namePlanning & Scheduling Professional (PSP) Exam
Questions in pack216
Last updatedNovember 21, 2026
Related certificationsPSP Certification

Free practice questions with explanations

AACE International AACE-PSP Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
14
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Basic Development Scheduling and Planning

    A civil contractor is developing the baseline schedule for a 14-month bridge replacement. The client's contract requires that the pile-driving subcontractor cannot mobilise until a geotechnical sign-off is received, and that the steel girder fabrication lead time of 16 weeks must be respected. The planner has entered the sign-off as a milestone with zero duration but no predecessor link. What is the most likely consequence, and what should the planner do FIRST?

  2. 2 Question 2 Single choice Basic Development Scheduling and Planning

    A hospital refurbishment programme must keep one ward operational throughout the works. The infection-control team has restricted noisy demolition to a window of 19:00 to 06:00 on weekdays. The planner is building the activity calendars for the ward-strip package, which is a 22-working-day task. The working-hours calendar currently used by the project is 08:00 to 17:00, Monday to Friday, with the UK bank holidays excluded. What is the BEST way to represent the restriction in the schedule?

  3. 3 Question 3 Single choice Communication

    A tower crane on a mixed-use scheme has been out of service for three days due to a hydraulic fault, and the planner has recalculated that the superstructure milestone will slip by six working days. The client's project director, who is not a scheduler, must decide within 24 hours whether to approve a weekend shift at extra cost to recover the slip. The contract requires notification of any milestone slip exceeding five working days under the delay clause. Which memo approach BEST serves the decision-maker and the contract?

  4. 4 Question 4 Single choice Planning and Scheduling Applications

    A programme manager is updating a 900-activity schedule at the end of period four. The project team has entered actual start and finish dates for completed work, but several in-progress activities show remaining durations that were not reviewed. The contract requires schedule updates to reflect the status date and to be submitted in a form where progress can be audited. Which update practice is MOST appropriate?

  5. 5 Question 5 Single choice Planning and Scheduling Applications

    A rail infrastructure client has issued a change order that adds 40 days of signalling works to a live programme. The planner must predict the effect on the completion of a separate track-possession package that shares the same signalling team and possession windows. The predecessor-successor logic for the new work is still being confirmed by the client. What is the MOST defensible way to predict the impact right now?

  6. 6 Question 6 Single choice Planning and Scheduling Applications

    A planner is maintaining the schedule for a data-centre fit-out. A review shows that the critical path runs through a 12-day commissioning activity with no float, and the team proposes to reduce its duration by adding a second commissioning crew. The commissioning activity is driven by a single specialist test rig that can only run one test cycle at a time, and the cycle length is fixed. Which action should the planner take to manage the schedule correctly?

  7. 7 Question 7 Single choice Basic Development Scheduling and Planning

    A planner preparing the planning data for an office block must record the inputs before building the network. The client has supplied an approved design freeze date, the contractor has confirmed a 6-week procurement lead time for lifts, and the building control authority requires a sign-off before the lift shaft can be closed up. Which of the following should be recorded as a planning constraint rather than as an activity?

  8. 8 Question 8 Single choice Planning and Scheduling Applications

    A planner is comparing two schedule-update methods for a programme that is being reforecast after a disruption: the windows method, which updates the schedule at each period and records the forecast at that time, and a retrospective method, which analyses delays after the fact by inserting or removing delay events in sequence. The client wants to attribute delay responsibility for a claim on a contract that allows extensions of time only for compensable events. Which method is MOST suitable, and why?

  9. 9 Question 9 Single choice Planning and Scheduling Applications

    A planner is reviewing a schedule update for a 3-year infrastructure project. The current status date is 30 June. Twelve activities show actual start dates after the status date, and four show actual finish dates. A senior manager asks why the forecast finish has moved two months earlier than the previous update despite no reported acceleration. Which action should the planner take FIRST?

  10. 10 Question 10 Single choice Basic Development Scheduling and Planning

    A planner is developing the deliverables list for a power station outage project. The outage must finish within a fixed 28-day window, because the grid operator has contracted replacement capacity that ends on that date. Procurement of a turbine rotor has a 20-week lead time and must be ordered before the outage starts. The owner asks the planner to confirm which planning output should be treated as the controlling deliverable for schedule approval. What is the BEST answer?

  11. 11 Question 11 Single choice Planning and Scheduling Applications

    A planner is preparing a predictive analysis for a stadium roof installation that depends on delivery of steel sections from an overseas supplier. The supplier has reported a 30% chance of a three-week slip, and the planner wants to show the effect on the handover date. The client's standards require that any predictive result be traceable to its assumptions. Which approach BEST meets the requirement?

  12. 12 Question 12 Multiple choice Planning and Scheduling Applications

    A planner is maintaining a schedule for a retail fit-out and must manage the schedule over successive updates. Which TWO practices best support the integrity of the schedule through repeated updates? (Choose two.)

  13. 13 Question 13 Multiple choice Planning and Scheduling Applications

    A planner is analysing a schedule for a water treatment plant upgrade. The network has a near-critical path with total float of 2 days on the plant commissioning chain, and a separate chain of civil works with 0 days of float. A stakeholder proposes accelerating the civil works to gain margin. Which THREE considerations should the planner raise before accepting the proposal? (Choose three.)

  14. 14 Question 14 Multiple choice Planning and Scheduling Applications

    A planner is preparing a schedule for a bridge deck pour that is weather-sensitive and must follow a curing period before the next activity. The contract requires the schedule to show the effect of rain delays. Which TWO approaches correctly represent these conditions in the schedule? (Choose two.)

These are 14 of the 216 questions in the full AACE-PSP pack.

Get All 216 Questions

Get all 216 questions & answers

744 Satisfied customers
95.6% Pass rate feedback
82.3% Said questions matched
97% Found material helpful

Full access options for AACE International AACE-PSP

Self-study

PDF Version

$40.00 $20.00
  • 216 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 216 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the AACE-PSP Exam (Planning & Scheduling Professional (PSP) Exam) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed