Exam Information
Free practice questions with explanations
AACE International AACE-PSP Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Basic Development Scheduling and Planning
A civil contractor is developing the baseline schedule for a 14-month bridge replacement. The client's contract requires that the pile-driving subcontractor cannot mobilise until a geotechnical sign-off is received, and that the steel girder fabrication lead time of 16 weeks must be respected. The planner has entered the sign-off as a milestone with zero duration but no predecessor link. What is the most likely consequence, and what should the planner do FIRST?
Correct Answer: AExplanationA milestone without a logical tie floats freely, so the network allows pile driving to start regardless of the geotechnical sign-off, which breaks the contractual dependency. Linking the sign-off as a finish-to-start predecessor fixes the logic before any other change. Giving the milestone a lead-time duration misrepresents a gate that consumes no work time, and a start-no-earlier-than constraint on fabrication addresses a different problem entirely. Splitting pile driving does not create a logical dependency and leaves the defect in place.
-
2 Question 2 Single choice Basic Development Scheduling and Planning
A hospital refurbishment programme must keep one ward operational throughout the works. The infection-control team has restricted noisy demolition to a window of 19:00 to 06:00 on weekdays. The planner is building the activity calendars for the ward-strip package, which is a 22-working-day task. The working-hours calendar currently used by the project is 08:00 to 17:00, Monday to Friday, with the UK bank holidays excluded. What is the BEST way to represent the restriction in the schedule?
Correct Answer: CExplanationWorking-time restrictions belong in calendars, and a dedicated resource calendar assigned only to the noisy activity keeps the day-shift work on the standard calendar intact. Changing the project default would wrongly move every activity to nights, and constraints are not the mechanism for recurring availability windows. A start-no-earlier-than constraint on segments fragments the logic and does not express the working window, while a mandatory finish does not control when work occurs.
-
3 Question 3 Single choice Communication
A tower crane on a mixed-use scheme has been out of service for three days due to a hydraulic fault, and the planner has recalculated that the superstructure milestone will slip by six working days. The client's project director, who is not a scheduler, must decide within 24 hours whether to approve a weekend shift at extra cost to recover the slip. The contract requires notification of any milestone slip exceeding five working days under the delay clause. Which memo approach BEST serves the decision-maker and the contract?
Correct Answer: CExplanationA decision memo for a non-scheduler should lead with the impact, the options with quantified recovery and cost, the contractual trigger that a six-day slip exceeds, and a clear deadline for the decision. Attaching the native file or listing activity IDs burdens the reader with detail they cannot act on, and deferring numbers ignores the 24-hour window and the notice clause. Vague reassurance fails both the decision need and the contractual obligation.
-
4 Question 4 Single choice Planning and Scheduling Applications
A programme manager is updating a 900-activity schedule at the end of period four. The project team has entered actual start and finish dates for completed work, but several in-progress activities show remaining durations that were not reviewed. The contract requires schedule updates to reflect the status date and to be submitted in a form where progress can be audited. Which update practice is MOST appropriate?
Correct Answer: AExplanationRemaining durations for in-progress work must be reviewed against the status date, and deriving them from original duration minus elapsed time gives a traceable starting point that can be audited. Resetting the status date to a finish date misstates the reporting period, and percent complete alone does not drive a credible forecast in most scheduling tools. Deleting actuals destroys the audit trail the contract requires.
-
5 Question 5 Single choice Planning and Scheduling Applications
A rail infrastructure client has issued a change order that adds 40 days of signalling works to a live programme. The planner must predict the effect on the completion of a separate track-possession package that shares the same signalling team and possession windows. The predecessor-successor logic for the new work is still being confirmed by the client. What is the MOST defensible way to predict the impact right now?
Correct Answer: CExplanationScenario analysis with explicit assumptions gives a credible forecast range while the logic is unconfirmed, and it documents the sensitivity to each linking option for the client. A single hard link presents one assumed outcome as fact, and extending a duration bypasses the network and hides the shared-resource effect. Refusing to forecast leaves the client without the information needed to decide on the change order.
-
6 Question 6 Single choice Planning and Scheduling Applications
A planner is maintaining the schedule for a data-centre fit-out. A review shows that the critical path runs through a 12-day commissioning activity with no float, and the team proposes to reduce its duration by adding a second commissioning crew. The commissioning activity is driven by a single specialist test rig that can only run one test cycle at a time, and the cycle length is fixed. Which action should the planner take to manage the schedule correctly?
Correct Answer: CExplanationThe duration here is governed by the sequential cycle on a single rig, so the rig is the true constraint and must be modelled as a resource with its capacity limit. Adding crews reduces nothing if the rig is the bottleneck, and splitting the activity artificially or cutting a real dependency produces an invalid network. The schedule should reflect the physical constraint rather than assume a shorter duration.
-
7 Question 7 Single choice Basic Development Scheduling and Planning
A planner preparing the planning data for an office block must record the inputs before building the network. The client has supplied an approved design freeze date, the contractor has confirmed a 6-week procurement lead time for lifts, and the building control authority requires a sign-off before the lift shaft can be closed up. Which of the following should be recorded as a planning constraint rather than as an activity?
Correct Answer: CExplanationAn external approval the planner does not control is a gate that constrains when downstream work can proceed, so it belongs in the planning data as a constraint with a required-by date. The lift installation and procurement period are work that the schedule must contain as activities, and a design freeze is a deliverable milestone rather than an inherent constraint on the network. Recording the approval correctly lets the planner test its effect on the shaft closure.
-
8 Question 8 Single choice Planning and Scheduling Applications
A planner is comparing two schedule-update methods for a programme that is being reforecast after a disruption: the windows method, which updates the schedule at each period and records the forecast at that time, and a retrospective method, which analyses delays after the fact by inserting or removing delay events in sequence. The client wants to attribute delay responsibility for a claim on a contract that allows extensions of time only for compensable events. Which method is MOST suitable, and why?
Correct Answer: DExplanationThe windows method preserves a contemporaneous record of how each event changed the forecast, which is what a claim on compensable events needs to establish causation and timing. The retrospective method as described depends on the chosen delay events and does not inherently exclude concurrency, and it cannot run without real progress data. Claims that rely on an idealised baseline recalculation are typically weaker than a contemporaneous analysis.
-
9 Question 9 Single choice Planning and Scheduling Applications
A planner is reviewing a schedule update for a 3-year infrastructure project. The current status date is 30 June. Twelve activities show actual start dates after the status date, and four show actual finish dates. A senior manager asks why the forecast finish has moved two months earlier than the previous update despite no reported acceleration. Which action should the planner take FIRST?
Correct Answer: DExplanationActual dates later than the status date are a data integrity error, and they can pull logic and driving relationships in ways that produce an apparent early forecast without any real acceleration. Correcting the entries is the first step before any float or critical path analysis, since analysis on corrupted data is unreliable. Re-baselining hides the problem, and moving the status date to fit the data falsifies the reporting period.
-
10 Question 10 Single choice Basic Development Scheduling and Planning
A planner is developing the deliverables list for a power station outage project. The outage must finish within a fixed 28-day window, because the grid operator has contracted replacement capacity that ends on that date. Procurement of a turbine rotor has a 20-week lead time and must be ordered before the outage starts. The owner asks the planner to confirm which planning output should be treated as the controlling deliverable for schedule approval. What is the BEST answer?
Correct Answer: DExplanationThe fixed outage window is the contractual constraint, and the controlling deliverable for approval is the milestone that proves the schedule meets it, with the other outputs supporting that test. The rotor order is critical to feasibility but is an input to the milestone rather than the approval deliverable, and the crew histogram and full activity list are supporting artefacts. Approval hinges on demonstrating the fixed window.
-
11 Question 11 Single choice Planning and Scheduling Applications
A planner is preparing a predictive analysis for a stadium roof installation that depends on delivery of steel sections from an overseas supplier. The supplier has reported a 30% chance of a three-week slip, and the planner wants to show the effect on the handover date. The client's standards require that any predictive result be traceable to its assumptions. Which approach BEST meets the requirement?
Correct Answer: CExplanationA probabilistic analysis with a documented distribution and reported confidence level gives a result traceable to its assumptions, which is what the client's standard requires. A single multiplier applies an arbitrary factor with no stated basis, and a fixed buffer hides the risk outside the network. Using the best-case date contradicts the stated 30% probability and misrepresents the forecast.
-
12 Question 12 Multiple choice Planning and Scheduling Applications
A planner is maintaining a schedule for a retail fit-out and must manage the schedule over successive updates. Which TWO practices best support the integrity of the schedule through repeated updates? (Choose two.)
Correct Answer: B, CExplanationRetaining versioned updates with status dates lets the team compare forecasts over time and audit how the schedule evolved, which is central to schedule governance. Recording the reason for significant changes gives traceability for why logic, durations, or constraints moved. Overwriting the baseline destroys the reference point for variance analysis, removing completed activities loses the record of what was done, and forcing baseline dates on in-progress work corrupts the forecast.
-
13 Question 13 Multiple choice Planning and Scheduling Applications
A planner is analysing a schedule for a water treatment plant upgrade. The network has a near-critical path with total float of 2 days on the plant commissioning chain, and a separate chain of civil works with 0 days of float. A stakeholder proposes accelerating the civil works to gain margin. Which THREE considerations should the planner raise before accepting the proposal? (Choose three.)
Correct Answer: B, C, EExplanationAccelerating a critical chain can move the critical path to another chain, so the expected gain may not materialise, and this must be checked in the network. Acceleration often draws on shared resources that the commissioning chain also needs, which can erode the benefit. Changes in total float on non-critical activities alter their risk exposure and must be reviewed. Deleting activities falsifies the network, and moving the status date misstates the reporting period, so neither is a valid consideration.
-
14 Question 14 Multiple choice Planning and Scheduling Applications
A planner is preparing a schedule for a bridge deck pour that is weather-sensitive and must follow a curing period before the next activity. The contract requires the schedule to show the effect of rain delays. Which TWO approaches correctly represent these conditions in the schedule? (Choose two.)
Correct Answer: C, EExplanationWeather-dependent working days are represented by a calendar that excludes those days, which lets the tool calculate the effect rather than relying on guesswork. A curing period enforced as a lag on the finish-to-start link keeps the required time inside the network logic. A fixed buffer hides the effect and does not respond to actual weather, switching to start-to-start breaks the curing requirement, and a mandatory start removes the modelled variability the contract asks to show.
These are 14 of the 216 questions in the full AACE-PSP pack.
Get All 216 QuestionsGet all 216 questions & answers
Full access options for AACE International AACE-PSP
Self-study
PDF Version
- 216 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 216 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 216 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the AACE-PSP Exam (Planning & Scheduling Professional (PSP) Exam) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.