Exam Information
Free practice questions with explanations
AACE International CCP Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Cost Control
A capital program is 40 percent complete by physical progress. Cumulative earned value is 3.2 million, actual cost is 3.6 million, and planned value is 4.0 million. The sponsor asks for the estimate at completion assuming current cost performance continues for the remaining work, and the contract is cost-reimbursable with no change orders yet approved. The cost engineer must report the figure that best reflects the trend in cost efficiency rather than schedule. Which forecast should be reported?
Correct Answer: DExplanationWith cumulative CPI equal to earned value divided by actual cost, 3.2 divided by 3.6 is about 0.89, so the cost-efficiency forecast is BAC divided by CPI, roughly 9.0 million on a BAC of 8.0 million. This is the standard EVM formula for assuming the current cost efficiency persists over the remaining work. The tempting remaining-budget approach ignores the observed overrun trend entirely and simply assumes future work will be performed at budget. The SPI-based option uses a schedule index, which measures timing rather than cost, so it answers the wrong question. Adding planned value to actual cost mixes a schedule baseline into a cost forecast and yields an unrealistic number.
-
2 Question 2 Order list Cost Estimating
A plant expansion estimate must be prepared for a board decision in six weeks. Historical data from two prior similar plants is available, but the scope has changed, and the contingency basis has not been agreed. The estimator must move from raw data to a defensible estimate that can be audited later. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Apply a parametric cost-capacity relationship to the new scope and adjust for location factors
- Define the estimate basis, scope, and assumptions and agree them with the project team
- Quantify contingency using a risk analysis tied to the identified cost risks
- Normalize historical costs to a common base year and currency using escalation indices
- Screen the historical cost records for scope comparability and remove unusable outliers
Correct Answer:- Normalize historical costs to a common base year and currency using escalation indices
- Screen the historical cost records for scope comparability and remove unusable outliers
- Define the estimate basis, scope, and assumptions and agree them with the project team
- Apply a parametric cost-capacity relationship to the new scope and adjust for location factors
- Quantify contingency using a risk analysis tied to the identified cost risks
ExplanationA defensible estimate starts by confirming the basis and scope so every later adjustment has a reference point. Only then should historical records be screened for comparability, since outliers and mismatched scope distort any relationship. Normalizing to a common base year and currency must precede parametric application, otherwise capacity relationships blend price levels. Contingency is quantified last, once the estimate body exists and the risks can be linked to its elements.
-
3 Question 3 Single choice Basic Skills and Knowledge
A cost engineer is benchmarking the installed unit cost of pipeline construction across three projects completed in different years and regions. The company wants a comparison that will hold up under review by the finance committee. The three projects used different cost indices, and one project was bid during a period of steep steel price volatility. Which benchmarking approach is most defensible?
Correct Answer: DExplanationA defensible benchmark requires a common price basis, so each project is escalated to one base period using a consistent index, then adjusted for location and scope differences. Comparing nominal figures ignores inflation across years, which is why the certification of totals does not help. Removing the highest project is an arbitrary outlier rule that hides rather than explains volatility. Converting at a single invoice-date spot rate introduces currency timing noise and does not address the price-level and scope differences that actually drive the comparison.
-
4 Question 4 Drag and drop Planning and Scheduling
A construction schedule for a refinery turnaround has a critical path that passes through a long-lead heat exchanger. The planner must analyze schedule risk, report the time impact of identified risks to the sponsor, and sequence the activities for resource leveling without breaking the completion milestone. Match each requirement to the technique that best meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Identify which activities would most reduce the project finish if shortenedEstimate the probability that the completion milestone is met given uncertain durationsReduce peak crew demand without extending the project finish dateEarned schedule calculationCritical path analysisMonte Carlo schedule simulationResource leveling within total floatCorrect Answer:- Estimate the probability that the completion milestone is met given uncertain durations → Monte Carlo schedule simulation
- Reduce peak crew demand without extending the project finish date → Resource leveling within total float
- Identify which activities would most reduce the project finish if shortened → Critical path analysis
ExplanationMonte Carlo simulation is the technique that produces a probability distribution of finish dates from uncertain durations, which answers the milestone-confidence question. Leveling uses float to smooth resource demand, and it must stay inside total float to protect the finish date. Critical path analysis identifies the activities that govern the finish, so shortening them is the only way to move it. Earned schedule is a performance measurement method for tracking progress, not a risk or leveling technique.
-
5 Question 5 Single choice Enterprise in Cost Management
A diversified engineering company runs its project cost data in an ERP system, but project managers record forecasts in separate spreadsheets. Executives report that portfolio cost figures disagree between finance and project controls each month. The company wants a fix that improves consistency without adding manual reconciliation each cycle. Which action is the best first step?
Correct Answer: BExplanationThe root cause is that actuals and forecasts live in unaligned structures, so the first step is a common cost breakdown structure mapped to ERP codes with a governed data source. This removes the reconciliation burden rather than repeating it. Monthly certification keeps the manual process that causes the disagreement. Replacing the ERP is disproportionate and does not fix the alignment problem by itself. A more frequent variance meeting treats the symptom and leaves the underlying structures disconnected.
-
6 Question 6 Multiple choice Cost Control
A project controls team reports that its schedule performance index has dropped below 0.8 for three consecutive periods while cost performance remains near 1.0. The sponsor wants early warning of whether the cost forecast is at risk before the next baseline review. Which two actions best support this objective? (Choose two.)
Correct Answer: A, CExplanationSchedule and cost metrics must be read together, because schedule slippage often converts into indirect and extended-duration cost later, so tracking schedule variance alongside cost is the early warning the sponsor needs. The to-complete performance index measures the efficiency required on remaining work to hit the budget at completion, which directly tests the forecast's achievability. Immediate rebaselining to restore a favorable index misrepresents performance and is governance-improper. Reporting only cost variance hides the leading signal. Earned value does measure schedule performance through the schedule index, so discounting it is incorrect.
-
7 Question 7 Dropdown Project Management
A project team is configuring its document control system for a capital project subject to a formal change control procedure. The procurement lead must ensure that any change affecting contract value is routed for approval before the work is authorized. Complete the workflow statement by selecting the correct value for each blank.
Choose the correct value for each blank.
Change requests affecting contract value must be submitted to the and approved before a is issued to the contractor.Correct Answer:Change requests affecting contract value must be submitted to the change control board and approved before a purchase order change is issued to the contractor.
ExplanationA formal change control procedure routes contract-affecting changes to the change control board, which holds authority over scope and cost impacts before work is authorized. The contractual authorization that alters the commitment to the supplier is the purchase order change, which must follow approval. A project scheduler or cost estimator may analyze the impact but does not hold approval authority. A daily progress report and an inspection certificate record status and quality, not contractual authorization. A bid evaluation occurs before award, not during change control.
-
8 Question 8 Single choice Cost Estimating
A cost estimator for a mining project finds that the single-point estimate for a haul road earthworks package is 18 million, but the package contains a large unquantified geotechnical risk. The estimate must support a go or no-go decision by the board, which requires a stated confidence level. Historical overruns on similar work have been strongly skewed to the high side. Which approach best produces the estimate the board needs?
Correct Answer: DExplanationBecause the risk is unquantified and the historical overruns are skewed, a probabilistic model using three-point distributions that capture the skew, followed by simulation, gives a cost at a stated confidence level, which is what the board requires. A flat percentage contingency does not reflect the skew or the confidence level and is applied without reference to the risk profile. Averaging recent overrun percentages uses a non-representative sample and yields no confidence statement. Treating 18 million as P50 wrongly assumes symmetry, since the skewed history means the median sits above the point estimate.
-
9 Question 9 Single choice Planning and Scheduling
A project team is managing a pipeline construction schedule in which a key subcontractor has reported that its productivity assumption may be optimistic by up to 20 percent. The schedule is resource-constrained, with a single pipe-welding crew shared across two work fronts. The sponsor wants to know the earliest a risk-adjusted schedule can be presented. Which step must the planner complete first?
Correct Answer: CExplanationA risk-adjusted schedule is only meaningful against a valid baseline, so the planner must first establish calibrated durations with the resource constraints explicitly recorded, then apply the productivity uncertainty. Leveling before the uncertainty is applied fixes a profile that the risk analysis would later need to change. Increasing crew size is a mitigation decision, not a prerequisite for the risk-adjusted view. Fast-tracking changes logic and adds risk before the baseline is understood.
-
10 Question 10 Single choice Project Management
A contractor has submitted a claim for delay costs on a government infrastructure contract, citing a late issue of design drawings. The contract requires notice within 28 days of the delaying event, and the claim was filed 45 days after the drawings were issued. The owner's project manager must decide the NEXT action. Which action is correct?
Correct Answer: BExplanationThe next step is to examine the notice clause together with any evidence of prejudice or waiver, and to document the time-bar position before any entitlement assessment, because many contracts and courts treat late notice differently depending on prejudice. Rejecting outright skips that review and may expose the owner to dispute risk. Accepting the claim ignores a stated contractual condition and is not supported by the stem. The insurer is not the decision-maker on the owner's contract claim, so referring it there does not address the owner's obligation.
-
11 Question 11 Drag and drop Basic Skills and Knowledge
A cost engineer is advising a finance team on how to present cost information for a multi-year capital investment decision. The team needs measures that reflect the time value of money, a count of how many years are needed to recover the investment, and an indicator of the economic return rate. Match each requirement to the financial measure that meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Compare projects of unequal lives on a present-value basis using a consistent discount rateShow how many years of cash flow are needed to recover the initial investmentExpress the expected annual return as the discount rate at which NPV equals zeroInternal rate of returnAccounting rate of returnPayback periodNet present valueCorrect Answer:- Compare projects of unequal lives on a present-value basis using a consistent discount rate → Net present value
- Show how many years of cash flow are needed to recover the initial investment → Payback period
- Express the expected annual return as the discount rate at which NPV equals zero → Internal rate of return
ExplanationNet present value discounts all cash flows at a consistent rate, which makes projects of different lives comparable on a present-value basis. Payback period counts the years needed to recover the initial investment, which is what the finance team asked for. Internal rate of return is the discount rate that sets NPV to zero, so it expresses the implied return. Accounting rate of return uses accounting profit rather than discounted cash flow and ignores the time value of money, so it does not meet the stated requirement.
-
12 Question 12 Single choice Cost Control
A project has a budget at completion of 20 million and is 30 percent complete by earned value, with actual cost of 8 million. A stakeholder argues that the project should be considered on track because cost performance is favourable. However, the project team has a large volume of unpriced change orders that will likely be approved in the coming months. Which conclusion about the cost forecast is most defensible?
Correct Answer: CExplanationCost performance indices capture historical efficiency, but a forecast must also reflect known exposures, so the probable cost of pending change orders should be added to the trend-based estimate. Using only the index ignores a clearly identified exposure that the team expects to be approved. Schedule performance does not determine cost exposure from change orders. Subtracting earned value from the budget at completion assumes the remaining work will be delivered exactly at budget, which contradicts the stated likelihood of additional approved change.
These are 12 of the 189 questions in the full CCP pack.
Get All 189 QuestionsGet all 189 questions & answers
Full access options for AACE International CCP
Self-study
PDF Version
- 189 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 189 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 189 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CCP Exam (Certified Cost Professional (CCP) Exam) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.