Exam Information
Free practice questions with explanations
WGU Operations-Management Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Forecasting and Capacity Planning
A regional bakery chain sells a seasonal pastry whose weekly demand is strongly driven by holidays. Over the past three years, weekly sales show a steady upward trend and a repeating 52-week seasonal pattern with spikes before major holidays. The planning manager wants a forecasting method that captures both the trend and the seasonality, uses only historical sales data, and can be refreshed weekly by a non-statistician using a spreadsheet. Ingredient lead times are two weeks, so forecasts must be produced at least that far ahead. Which forecasting approach is the BEST fit?
Correct Answer: CExplanationHolt-Winters triple exponential smoothing models level, trend and seasonal components together, which matches the upward trend and the repeating annual cycle in the bakery data, and it can be implemented in a spreadsheet and refreshed weekly. A four-week moving average lags the trend and ignores seasonality entirely. Single exponential smoothing also has no trend or seasonal terms, so it will systematically miss the holiday spikes. Linear regression on week number captures the trend but not the repeating seasonal pattern, leaving large seasonal errors.
-
2 Question 2 Single choice Process Design and Improvement Strategies
A hospital outpatient lab is experiencing long patient waiting times between specimen collection and result reporting. A process improvement team has mapped the current workflow and found that specimens wait an average of 90 minutes in a batch queue before centrifugation, although centrifugation itself takes only 8 minutes per batch. Leadership wants to cut turnaround time by at least 50 percent within one quarter and has no budget for new analyzers. The team is considering a value stream analysis, a Six Sigma DMAIC project with a full statistical design of experiments, lean elimination of batch queues with one-piece flow, or a complete replacement of the laboratory information system. Which action should the team take FIRST to meet the constraints?
Correct Answer: CExplanationThe mapped waste is the 90-minute queue, not the 8-minute processing step, so removing batch waiting by adopting one-piece or small-batch flow attacks the constraint directly and needs no capital spending. A designed experiment on centrifuge settings would target the step that already takes only 8 minutes. Replacing the information system is outside the no-budget constraint and does not address specimen queuing. Buying extra centrifuges adds capacity but the bottleneck is the batching rule, and the budget prohibits new equipment.
-
3 Question 3 Single choice Project Management and Operational Efficiency
A manufacturing plant is running a 14-week project to install a new packaging line. The critical path runs through equipment delivery and electrical commissioning. A software vendor has warned that the integration module may slip by three weeks, which would push the project past a contractual go-live date that carries a daily penalty. The project manager has four weeks of float on the non-critical activities but none on the critical path. Crashing the schedule by adding overtime to electrical commissioning would cost a modest premium. Which action is the MOST appropriate first step?
Correct Answer: CExplanationFloat on non-critical activities cannot absorb a delay to the critical path, so the first step is to confirm whether the integration work is critical and then compare crashing options against the penalty. Only after that analysis makes sense to re-baseline or request a date change. Relying on float that only exists on non-critical tasks mistakes total float for protection the critical path does not have. Fast-tracking all activities ignores the hard dependency between equipment delivery and commissioning and risks rework.
-
4 Question 4 Single choice Quality Management and Performance Excellence
A medical device manufacturer runs a control chart on the torque applied during assembly of a fastener. Subgroups of five units are sampled hourly. The X-bar chart shows all points inside the control limits, but the R chart shows several consecutive subgroups with range values near the upper control limit, and the team notes that the most recent 12 subgroup averages all fall above the centre line. The customer specification is a tolerance band of 20 to 30 newton-metres. The engineer wants the BEST interpretation of the current process state before adjusting equipment. Which conclusion is best supported?
Correct Answer: AExplanationTwelve consecutive points on the same side of the centre line is a standard run rule signal of a special cause shifting the process mean, and rising ranges near the upper limit suggest increasing variation that also needs investigation. Points inside the limits alone do not establish control when run patterns are present. Capability cannot be claimed from control charts with a small sample without computing capability indices against the specification, and a single-point rule is not the only signal for an R chart.
-
5 Question 5 Single choice Supply Chain and Logistics Management
A distributor of industrial fasteners operates one central warehouse serving 40 regional customers. Demand averages 1,200 units per week with a standard deviation of 180 units. The supplier lead time is six weeks with a standard deviation of one week, and the company targets a 98 percent cycle service level. The purchasing manager proposes ordering from a new overseas supplier that offers a lower unit price but a lead time of 14 weeks with high variability, and has no contractual lead-time guarantees. The operations director must decide the approach that best balances inventory cost and service. Which action BEST meets these requirements?
Correct Answer: AExplanationSafety stock must reflect both demand variability and lead-time variability, and the domestic supplier's six-week, low-variance lead time is the most reliable base for the target 98 percent service level. Evaluating the overseas source only as a secondary option with no lead-time guarantees keeps risk controlled. Moving entirely to the overseas supplier ignores that a 14-week variable lead time would require much larger safety stock, likely erasing the price advantage. Targeting 100 percent service drives infinite safety stock and is not a sound policy, and weekly fixed ordering does not remove the variability that safety stock protects against.
-
6 Question 6 Single choice AI Skills Fundamentals Certificate in Operations Management
A logistics company wants to use a machine learning model to predict daily delivery delays across 300 routes so dispatchers can reassign vehicles in advance. The operations analyst has three years of historical data including weather, traffic speed, driver shifts and past delays. The model reaches 94 percent accuracy on the training set but only 61 percent on a held-out set from the most recent quarter. Management must approve deployment within two weeks and cannot accept any model that makes decisions it cannot explain to dispatchers. Which action is the MOST appropriate next step?
Correct Answer: CExplanationThe gap between 94 percent training and 61 percent recent-quarter accuracy signals overfitting, and a time-aware validation split is the right test because delay patterns shift over time. Simplifying the model and examining feature importance addresses both the performance gap and the explainability requirement. Deploying on training accuracy ignores the held-out failure. Adding complexity worsens overfitting and reduces explainability, while removing the held-out set eliminates the only honest measure of generalization.
-
7 Question 7 Single choice Forecasting and Capacity Planning
A call center plans staffing for a customer support line that receives calls with a Poisson arrival pattern averaging 60 calls per hour during peak periods. Each agent handles an average of 6 calls per hour. The service target is that at least 90 percent of calls are answered within 20 seconds, and management has determined that the required staffing must be found using queueing analysis rather than a simple ratio. Which capacity planning approach is the MOST appropriate for determining the number of agents?
Correct Answer: AExplanationErlang C is the standard queueing model for a multi-server system with Poisson arrivals and exponential service, and it lets the planner find the smallest number of agents that meets a probabilistic service level such as 90 percent answered within 20 seconds. Dividing arrival by service rate gives only the minimum for stability, not the service target. A fixed ratio ignores the queueing dynamics that determine wait times. The M/M/1 model represents a single server, which does not apply to a multi-agent pool.
-
8 Question 8 Single choice Process Design and Improvement Strategies
A furniture manufacturer's assembly process has a 35 percent first-pass yield because operators frequently attach drawer slides before checking alignment, requiring costly rework. The process engineer wants to design the workflow to prevent the error at the source rather than detect it later. The shop floor has limited space, and the solution must not add a step that increases cycle time. Which approach is the BEST application of error-proofing principles?
Correct Answer: CExplanationA fixture that physically prevents incorrect seating is a poka-yke mistake-proofing device, and it prevents the defect at the source without adding inspection time or floor space. A final inspection still lets defects occur and adds handling. Training and signage depend on operator attention, which is the root cause the engineer wants to eliminate.
-
9 Question 9 Single choice Project Management and Operational Efficiency
A hospital IT team is managing a project to upgrade its electronic scheduling system during a period when clinical staff availability is limited to a set number of hours. The project has 6 specialists available for 240 hours total in the testing phase, and 4 activities need to be scheduled. The project sponsor requires that no resource is loaded beyond 100 percent in any week and that the testing phase finish within 8 weeks. Which scheduling technique should the project manager apply to meet these requirements?
Correct Answer: BExplanationResource leveling adjusts activity start times so that resource demand stays within the stated capacity limits, which is what the 100 percent weekly loading cap requires, even though it may extend the schedule. Resource smoothing keeps the end date fixed and does not guarantee the capacity cap when the critical path is involved. Earned value measures cost and schedule performance rather than scheduling resources. Monte Carlo estimates probability of completion but does not itself allocate resources to meet a loading limit.
-
10 Question 10 Multiple choice Quality Management and Performance Excellence
A food packaging plant is preparing for a customer audit and wants to strengthen its quality management system so that customer complaints about seal failures decline sustainably. The quality manager proposes several actions. Which TWO actions are most likely to produce sustained improvement in seal integrity in line with continuous improvement frameworks? (Choose two.)
Correct Answer: B, DExplanationA control plan with monitored process parameters and documented reaction plans keeps the process in control and turns variation into a managed response, which supports sustained gains. Pareto analysis focuses corrective effort on the vital few causes of complaints, which is the disciplined improvement approach the framework calls for. Replacing equipment before understanding failure modes spends capital without evidence. Increasing inspection to 100 percent detects defects but does not prevent them. Changing the complaint form hides the problem rather than solving it and would damage quality reporting integrity.
-
11 Question 11 Single choice Supply Chain and Logistics Management
A consumer electronics firm sources a critical chip from a single supplier that has recently experienced capacity shortfalls. The procurement director must reduce supply risk without doubling inventory carrying costs, which are already high because of product obsolescence. The chip is a commodity specification available from two other qualified manufacturers, but qualifying a second source requires a 12-week validation period. Which strategy is the BEST balance of risk and cost?
Correct Answer: BExplanationStarting the 12-week qualification now shortens the time to a dual-source position, and a moderate, time-limited buffer covers the validation window without building the obsolescence exposure of a year of stock. A twelve-month order multiplies carrying cost and obsolescence risk for a product with high obsolescence. Accepting the risk relies on expensive expediting and does not reduce exposure. Switching to an unqualified supplier introduces quality risk the validation process exists to prevent.
-
12 Question 12 Single choice AI Skills Fundamentals Certificate in Operations Management
A manufacturing company has deployed an automated anomaly detection tool that monitors vibration sensors on 80 industrial pumps and generates alerts to maintenance supervisors. Since deployment, the alert volume has risen sharply, and technicians are ignoring many alerts because most turn out to be harmless sensor noise. The company wants to keep the automation benefits while restoring alert credibility within a month and without removing the human review step required by its maintenance policy. Which action BEST meets these requirements?
Correct Answer: AExplanationTuning the detector using technician-labeled outcomes improves precision with the data the team already has, and keeping human confirmation honors the maintenance policy. Removing the review step breaks a stated requirement. Adding sensors increases noise and data without fixing the false-positive rate. Disabling the tool abandons the automation benefit the company wants to keep.
-
13 Question 13 Single choice Forecasting and Capacity Planning
A contract manufacturer is planning capacity for a new product line with uncertain demand. Forecasts suggest demand could be either 4,000 or 9,000 units per month, with equal probability. Building capacity for 9,000 units requires a fixed investment of 2 million dollars, while building for 4,000 units costs 800,000 dollars. If capacity is built for 4,000 units but demand reaches 9,000, the company can outsource the excess 5,000 units at an additional cost of 600,000 dollars per month. The planning team wants to choose the option with the highest expected net result over the first month, using expected value. Which capacity decision maximizes the expected value of the first month's outcome, assuming revenue is 350 dollars per unit and variable production cost is already embedded in the figures given?
Correct Answer: BExplanationUnder equal probabilities, building for 4,000 units costs 800,000 dollars up front, and in the high-demand case outsourcing 5,000 units adds 600,000 dollars, giving an expected extra cost of 300,000 dollars; total expected capacity-related cost is 1,100,000 dollars, compared with 2,000,000 dollars for the 9,000-unit build. Revenue is the same for every unit served in both options, so the cheaper expected capacity cost wins. Accepting lost sales forfeits revenue on 5,000 units, a cost the stem's assumptions show to be substantial. Waiting for confirmation is not an option the scenario allows, since the team must commit now.
-
14 Question 14 Single choice Process Design and Improvement Strategies
A software company's release process requires a manual sign-off from four departments in sequence, and each sign-off waits on the previous one, causing a median release cycle of 19 days. The head of operations wants to shorten the cycle by at least 40 percent while preserving the regulatory requirement that legal and security sign-offs remain mandatory for every release. Process mapping shows that the QA and documentation sign-offs are often completed within a day but wait for the earlier steps to clear. Which redesign is the BEST option?
Correct Answer: AExplanationMapping shows the QA and documentation reviews are quick but idle while waiting in sequence, so running reviews concurrently on one release candidate cuts elapsed time while keeping every required approval. Removing legal or security sign-offs breaks the regulatory constraint. A single approver removes the separation of duties the departments rely on and may not satisfy governance requirements. Monthly batching lengthens cycle time rather than shortening it.
These are 14 of the 70 questions in the full Operations-Management pack.
Get All 70 QuestionsGet all 70 questions & answers
Full access options for WGU Operations-Management
Self-study
PDF Version
- 70 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 70 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 70 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the Operations-Management Exam (WGU Operations Management) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.