2026 Actual ScrumStudy SMC Dumps, Updated Exam Questions for Guaranteed Pass

Scrum Master Certified (SMC) - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorScrumStudy
Exam codeSMC
Exam nameScrum Master Certified (SMC)
Questions in pack100
Last updatedNovember 21, 2026
Related certificationsScrum Master Certification

Free practice questions with explanations

ScrumStudy SMC Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
12
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Agile Overview

    A government agency has contracted a team to deliver a citizen portal. The sponsor insists that the team commit to the full scope and fixed date at the start of the project, and wants a detailed change-control board to approve every requirement before development begins. The team lead argues that requirements for the portal are expected to shift as user research continues over the next six months. Which Agile principle best addresses the sponsor's concern while still allowing the team to respond to changing requirements?

  2. 2 Question 2 Single choice Scaling Scrum

    Four Scrum teams in a logistics company build a shared warehouse management system. Each team has its own Product Owner and Sprint cycle. Integration defects are discovered only during the quarterly release, and the teams frequently block each other on shared components. The program manager wants a lightweight, recurring mechanism that keeps the teams coordinated without adding a new layer of management or merging the teams into one backlog. Which mechanism should the Scrum Master set up first?

  3. 3 Question 3 Single choice Scrum Overview

    A Scrum team of seven developers is in the middle of a 4-week Sprint. On day six, the Product Owner asks the team to add a new reporting feature that a major customer needs before the end of the month. The team estimates the feature at about 60 percent of the remaining Sprint capacity. The Scrum Master notes that the Sprint Goal is unrelated to reporting and that the Sprint Backlog has already been committed. The team wants to keep their commitment and protect their focus. What is the most appropriate action?

  4. 4 Question 4 Single choice Scrum Phases

    A newly formed product team is starting work on a mobile banking app. The sponsor has asked for a clear view of the product vision, the major stakeholders, and the funding envelope before any development is scheduled. The Scrum Master wants the team to establish a foundation that supports later planning without spending weeks on detailed design. Which activity should be completed first, and which phase is it part of?

  5. 5 Question 5 Single choice Agile Overview

    A financial services company is adopting Agile across several departments. One department wants to measure progress by counting the number of signed-off requirement documents delivered each month. Another department wants to adopt Kanban because its work arrives unpredictably and has no fixed iteration length. A third team has adopted XP practices such as pair programming and test-first development. An executive asks which Agile method fits the unpredictable-arrival department best. Which recommendation is most appropriate?

  6. 6 Question 6 Single choice Scaling Scrum

    An organisation scaling Scrum across a portfolio of product lines notices that senior managers are still assigning individual developers to projects each quarter, which disrupts stable Scrum teams. The Scrum Master is asked to recommend how traditional resource-management roles should map to Scrum during the transition. Executive sponsors are concerned about losing oversight of spending. Which mapping is most appropriate?

  7. 7 Question 7 Single choice Scrum Overview

    A Scrum team has completed its Sprint Review, but the Product Owner notices that two stakeholders, who joined late, have raised concerns about a feature that was accepted at the Review. The Product Owner is considering reopening the acceptance criteria and altering the Sprint Backlog that was reviewed. The team has already begun planning the next Sprint. The Scrum Master must advise the Product Owner. What is the best advice?

  8. 8 Question 8 Single choice Scrum Phases

    A team is in the Plan and Estimate phase for a new product release. The Product Owner has a prioritised backlog of 45 items, but the Development Team has never estimated work for this codebase. The team is tempted to estimate all 45 items in a single long session to produce a complete release forecast before the Sprint begins. The Scrum Master wants an approach that keeps estimates reliable and the planning effort proportionate. What should the Scrum Master recommend?

  9. 9 Question 9 Single choice Agile Overview

    A product group is evaluating whether to shift from a traditional phase-gated process to Agile. A senior architect argues that Agile means no planning and no documentation, while a project manager argues that Agile requires a complete project plan signed off before any work begins. A Scrum Master is asked to explain the Agile Manifesto's position on plans and documentation to both leaders. Which explanation is most accurate?

  10. 10 Question 10 Single choice Scaling Scrum

    An enterprise has three Scrum teams building components of one product, and a fourth team responsible for the shared platform. The platform team's backlog is dominated by urgent requests from the other teams, which are routed through email to a single platform engineer. Delivery delays are growing and the platform engineer is overloaded. The Scrum Master proposes a change. Which change is the best first step for coordinating these dependencies in a scaled Scrum setting?

  11. 11 Question 11 Single choice Scrum Roles

    A Development Team of six members is preparing for Sprint Planning. The team includes a specialist tester who has been assigned to the team only part-time, a senior engineer who prefers to make all technical decisions alone, and a junior developer who rarely speaks up in meetings. The Product Owner expects the team to commit to a Sprint Goal and Sprint Backlog during the meeting. The Scrum Master wants the team to function as a self-organising unit. What should the Scrum Master do first?

  12. 12 Question 12 Single choice Scrum Phases

    A team is in the Review and Retrospect phase after completing a four-week Sprint. The Sprint Review showed that the delivered increment met the Sprint Goal, but the Product Owner has reported that two of the features did not meet stakeholder expectations. The team's retrospective reveals that story acceptance criteria were unclear for those features. The Scrum Master wants to ensure the next Sprint benefits from this learning. Which action should be taken during the Review and Retrospect phase to address the root cause?

These are 12 of the 100 questions in the full SMC pack.

Get All 100 Questions

Get all 100 questions & answers

735 Satisfied customers
94.7% Pass rate feedback
83.8% Said questions matched
96% Found material helpful

Full access options for ScrumStudy SMC

Self-study

PDF Version

$40.00 $20.00
  • 100 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 100 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the SMC Exam (Scrum Master Certified (SMC)) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed